| Plan Review Stops For Permit 20060467 |
| Review Stop |
B |
BUILDING (STRUCTURAL) |
| Rev No |
2 |
Status |
P |
Date |
2020-07-24 |
|
|
Cont ID |
|
| Sent By |
rmcphers |
Date |
2020-07-24 |
Time |
12:58 |
Rev Time |
0.00 |
| Received By |
rmcphers |
Date |
2020-07-24 |
Time |
12:58 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
B |
BUILDING (STRUCTURAL) |
| Rev No |
1 |
Status |
F |
Date |
2020-07-07 |
|
|
Cont ID |
|
| Sent By |
rmcphers |
Date |
2020-07-07 |
Time |
15:36 |
Rev Time |
0.00 |
| Received By |
rmcphers |
Date |
2020-07-07 |
Time |
14:25 |
Sent To |
|
|
| Notes |
| 2020-07-07 15:36:25 | NEW SFR | | | REVIEWED BY ROGER MCPHERSON | | | 561-805-6716 | | | [email protected]. | | | | | | | | | CORRECTIONS NEEDED - FBC WPB AMENDMENTS 107 | | | 1) PLEASE PROVIDE A SITE PLAN SHOWING THE PROPERTY | | | LINES, BUILDING SET BACKS AND LOT DRAINAGE. FBC R401.3 | | | |
|
|
| Review Stop |
E |
ELECTRICAL |
| Rev No |
1 |
Status |
P |
Date |
2020-07-07 |
|
|
Cont ID |
|
| Sent By |
jleahy |
Date |
2020-07-07 |
Time |
12:57 |
Rev Time |
0.00 |
| Received By |
jleahy |
Date |
2020-07-07 |
Time |
12:37 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
3 |
Status |
N |
Date |
2020-08-20 |
|
|
Cont ID |
|
| Sent By |
rmcphers |
Date |
2020-08-20 |
Time |
07:41 |
Rev Time |
0.00 |
| Received By |
rmcphers |
Date |
2020-08-11 |
Time |
10:39 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
2 |
Status |
N |
Date |
2020-08-08 |
|
|
Cont ID |
|
| Sent By |
lmarchan |
Date |
2020-08-08 |
Time |
07:45 |
Rev Time |
0.00 |
| Received By |
lmarchan |
Date |
2020-07-09 |
Time |
08:54 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
1 |
Status |
N |
Date |
2020-07-08 |
|
|
Cont ID |
|
| Sent By |
lmarchan |
Date |
2020-07-08 |
Time |
15:01 |
Rev Time |
0.00 |
| Received By |
lmarchan |
Date |
2020-06-17 |
Time |
07:54 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
IMPACT |
COUNTY IMPACT FEES |
| Rev No |
2 |
Status |
P |
Date |
2020-09-03 |
|
|
Cont ID |
|
| Sent By |
lmarchan |
Date |
2020-09-03 |
Time |
13:16 |
Rev Time |
0.00 |
| Received By |
lmarchan |
Date |
2020-08-27 |
Time |
10:45 |
Sent To |
|
|
| Notes |
| 2020-09-02 06:55:41 | RECEIPT MU-2020-033102 - $9401.07 - PAID | | 2020-08-27 10:46:07 | 8/27/20 EMAILED IMPACT FEE OFFICE FOR REVIEW. LEM |
|
|
| Review Stop |
IMPACT |
COUNTY IMPACT FEES |
| Rev No |
1 |
Status |
F |
Date |
2020-07-07 |
|
|
Cont ID |
|
| Sent By |
rmcphers |
Date |
2020-07-07 |
Time |
15:42 |
Rev Time |
0.00 |
| Received By |
rmcphers |
Date |
2020-07-07 |
Time |
15:42 |
Sent To |
|
|
| Notes |
| 2020-07-07 15:43:02 | PLANS WILL BE REVIEWED BY THE PBC IMPACT FEE OFFICE | | | DIGITALLY VIA PROJECTDOX UPON NOTIFICATION BY THIS | | | OFFICE. NOTIFICATION MAY OCCUR WHEN PLANS ARE NEAREST | | | FINAL FORM. YOU MAY COORDINATE WITH THE IMPACT FEE | | | OFFICE AT (561) 233-5025 OR SIMPLY UPLOAD THE MUNICIPAL | | | IMPACT FEE QUESTIONNAIRE FORM TO YOUR PROJECT AND NAME | | | THE FILE MUNICIPAL IMPACT FEE QUESTIONNAIRE. THE FORM | | | CAN BE FOUND AT: HTTP://DISCOVER.PBCGOV.ORG/PZB/ADMINIS | | | TRATION/PDF/IMPACTFEES/FORMS/QUESTIONNAIRE.PDF | | | | | | UPON APPROVAL AND FEE PAYMENT, PLEASE UPLOAD THE | | | RECEIPT TO YOUR PROJECT OR EMAIL IT TO | | | [email protected] . | | | |
|
|
| Review Stop |
M |
MECHANICAL (A/C) |
| Rev No |
3 |
Status |
P |
Date |
2020-08-13 |
|
|
Cont ID |
|
| Sent By |
hmoser |
Date |
2020-08-13 |
Time |
12:33 |
Rev Time |
0.00 |
| Received By |
hmoser |
Date |
2020-08-13 |
Time |
11:48 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
M |
MECHANICAL (A/C) |
| Rev No |
2 |
Status |
F |
Date |
2020-07-20 |
|
|
Cont ID |
|
| Sent By |
medwards |
Date |
2020-07-20 |
Time |
09:57 |
Rev Time |
0.00 |
| Received By |
medwards |
Date |
2020-07-20 |
Time |
09:57 |
Sent To |
|
|
| Notes |
| 2020-07-20 09:58:10 | 2ND REVIEW FBC-2017 MECHANICAL | | | PERMIT-20060467 | | | | | | CODES IN EFFECT: | | | | | | FBC M- FLORIDA MECHANICAL CODE SIXTH EDITION 2017 | | | FBC EC- FLORIDA ENERGY CONSERVATION CODE SIXTH EDITION | | | 2017 | | | FBC RES- FLORIDA RESIDENTIAL BUILDING CODE SIXTH | | | EDITION 2017 | | | FS- FLORIDA STATUTES | | | FAC- FLORIDA ADMINISTRATIVE CODE | | | WPB- WEST PALM BEACH AMENDMENTS TO THE FBC SIXTH | | | EDITION 2017 | | | | | | PLAN REVIEW RESULTS: DENIED. | | | | | | 1) PLEASE ADDRESS THE 2 ITEMS BELOW FRO THE FIRST | | | REVIEW: | | | | | | 2) NOTE 4 OF 1ST REVIEW- THE AHU IN THE GARAGE MUST BE | | | PROTECTED FROM IMPACT. FBC RES M1307.3.1 | | | | | | 3) NOTE 8 OF 1ST REVIEW- DUCTS IN THE GARAGE AND DUCTS | | | PENETRATING THE WALLS OR CEILINGS SEPARATING THE | | | DWELLING FROM THE GARAGE SHALL BE CONSTRUCTED OF A | | | MINIMUM NO.26 GAGE SHEET METAL. FBC RES R302.5.2 | | | | | | | | | | | | WHEN RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE | | | LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY | | | RE-SUBMITTAL FORM. ADDITIONALLY, PLEASE INSERT | | | CORRECTED PLAN SHEETS INTO THE SETS, REMOVE THE OLD | | | SHEETS FROM THE PLAN SETS, BIND THEM TOGETHER | | | SEPARATELY AND MARK VOID OR OLD ON THEM. PLEASE RETAIN | | | THEM FOR REFERENCE WITH THE NEW SUBMITTED PLANS. THIS | | | PROCESS WILL ALSO APPLY TO ANY DOCUMENTS SUCH AS | | | PRODUCT APPROVALS OR CALCULATIONS BEING REPLACED OR | | | UPDATED. | | | | | | | | | MICHAEL EDWARDS | | | MECHANICAL EXAMINER | | | 401 CLEMATIS STREET | | | WEST PALM BEACH FL. 33401 | | | 561-805-6728 | | | [email protected] | | | |
|
|
| Review Stop |
M |
MECHANICAL (A/C) |
| Rev No |
1 |
Status |
F |
Date |
2020-07-08 |
|
|
Cont ID |
|
| Sent By |
medwards |
Date |
2020-07-08 |
Time |
14:04 |
Rev Time |
0.00 |
| Received By |
medwards |
Date |
2020-07-08 |
Time |
12:29 |
Sent To |
|
|
| Notes |
| 2020-07-08 14:04:47 | 1ST REVIEW FBC-2017 MECHANICAL | | | PERMIT-20060467 | | | | | | CODES IN EFFECT: | | | | | | FBC EC- FLORIDA ENERGY CONSERVATION CODE SIXTH EDITION | | | 2017 | | | FBC RES- FLORIDA RESIDENTIAL BUILDING CODE SIXTH | | | EDITION 2017 | | | FS- FLORIDA STATUTES | | | FAC- FLORIDA ADMINISTRATIVE CODE | | | WPB- WEST PALM BEACH AMENDMENTS TO THE FBC SIXTH | | | EDITION 2017 | | | | | | PLAN REVIEW RESULTS: DENIED. | | | | | | 1) PLEASE PROVIDE ENERGY CALCULATIONS. FBC EC | | | 101.5.1.1.2 | | | | | | 2) PLEASE PROVIDE THE MANUAL S AND J CALCULATIONS. FBC | | | RES M1401.3 | | | | | | 3) PLEASE PROVIDE SPEC SHEETS ON THE AHU. FBC FS | | | 107.2.1 | | | | | | 4) PLEASE SHOW HOW YOU ARE PROTECTING THE AHU IN THIS | | | GARAGE. FBC M 303.4 | | | | | | 5) PLEASE SHOW CONDENSATION LINES AND WHERE THEY DRAIN | | | TO THE EXTERIOR. THE PLUMBING SHEET DOES NOT SHOW A | | | DRAIN AT THE AHU. FBC RES M1411.3 | | | | | | 6) PLEASE SHOW THAT THE RETURN AIR IS BALANCED. FBC M | | | 601.6 | | | | | | 7) PLEASE PROVIDE DRYER DUCT MATERIAL AND TOTAL LENGTH. | | | FBC M 504.8.1, FBC M 504.8.3 | | | | | | 8) THE DRAWING INDICATES THAT THE AHU IS IN THE GARAGE, | | | PLEASE SHOW THE DUCT FIRE RATING. FBC RES R3.2.5.2 | | | | | | | | | WHEN RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE | | | LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY | | | RE-SUBMITTAL FORM. ADDITIONALLY, PLEASE INSERT | | | CORRECTED PLAN SHEETS INTO THE SETS, REMOVE THE OLD | | | SHEETS FROM THE PLAN SETS, BIND THEM TOGETHER | | | SEPARATELY AND MARK VOID OR OLD ON THEM. PLEASE RETAIN | | | THEM FOR REFERENCE WITH THE NEW SUBMITTED PLANS. THIS | | | PROCESS WILL ALSO APPLY TO ANY DOCUMENTS SUCH AS | | | PRODUCT APPROVALS OR CALCULATIONS BEING REPLACED OR | | | UPDATED. | | | | | | | | | MICHAEL EDWARDS | | | MECHANICAL EXAMINER | | | 401 CLEMATIS STREET | | | WEST PALM BEACH FL. 33401 | | | 561-805-6728 | | | [email protected] | | | |
|
|
| Review Stop |
P |
PLUMBING |
| Rev No |
1 |
Status |
P |
Date |
2020-07-06 |
|
|
Cont ID |
|
| Sent By |
cthroop |
Date |
2020-07-06 |
Time |
12:19 |
Rev Time |
0.00 |
| Received By |
cthroop |
Date |
2020-07-06 |
Time |
12:03 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
R |
ROOF PLAN REVIEW |
| Rev No |
1 |
Status |
P |
Date |
2020-07-07 |
|
|
Cont ID |
|
| Sent By |
rmcphers |
Date |
2020-07-07 |
Time |
15:42 |
Rev Time |
0.00 |
| Received By |
rmcphers |
Date |
2020-07-07 |
Time |
15:42 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
SIGNATURE |
ELECTRONIC SIGNATURE SHEET |
| Rev No |
4 |
Status |
P |
Date |
2020-08-20 |
|
|
Cont ID |
|
| Sent By |
rmcphers |
Date |
2020-08-20 |
Time |
07:40 |
Rev Time |
0.00 |
| Received By |
rmcphers |
Date |
2020-08-20 |
Time |
07:40 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
SIGNATURE |
ELECTRONIC SIGNATURE SHEET |
| Rev No |
3 |
Status |
F |
Date |
2020-07-24 |
|
|
Cont ID |
|
| Sent By |
rmcphers |
Date |
2020-07-24 |
Time |
12:58 |
Rev Time |
0.00 |
| Received By |
rmcphers |
Date |
2020-07-24 |
Time |
12:58 |
Sent To |
|
|
| Notes |
| 2020-07-24 13:00:08 | THE PROVIDED SURVEY = SIGNED AND SEALED DRAWINGS IN | | | PROJECTDOX NEED TO BE DIGITALLY/ELECTRONICALLY SIGNED | | | BY THE SURVEYOR TO BE USED IN ELECTRONIC PLAN REVIEW. | | | DRAWINGS DO NOT SHOW IN "ADOBE READER" AS | | | DIGITALLY/ELECTRONICALLY SIGNED. - OR - IF YOUR | | | SURVEYOR DOES NOT HAVE AN ELECTRONIC OR DIGITAL | | | SIGNATURE - PLEASE DROP OFF (CITY HALL DROP BOX) THE | | | ORIGINAL SIGNED AND SEALED DRAWINGS/DOCUMENTS ALONG | | | WITH A "PLAN REVIEW REQUEST FORM" EXPLAINING THE REASON | | | FOR SUBMITTING THE DOCUMENT OR DRAWINGS. PLAN REVIEW | | | REQUEST FORM CAN BE OBTAINED BY E MAILING [email protected] | | | AND ASKING FOR THE FORM. (AT THIS TIME DROP BOX ITEMS | | | MAY TAKE 2 TO 3 WEEKS TO PROCESS, TO SEND TO PLAN | | | REVIEW - DUE TO LIMITED STAFF INSIDE THE BUILDING | | | DEPT.) |
|
|
| Review Stop |
SIGNATURE |
ELECTRONIC SIGNATURE SHEET |
| Rev No |
2 |
Status |
P |
Date |
2020-07-20 |
|
|
Cont ID |
|
| Sent By |
medwards |
Date |
2020-07-20 |
Time |
10:09 |
Rev Time |
0.00 |
| Received By |
medwards |
Date |
2020-07-20 |
Time |
09:58 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
SIGNATURE |
ELECTRONIC SIGNATURE SHEET |
| Rev No |
1 |
Status |
P |
Date |
2020-07-07 |
|
|
Cont ID |
|
| Sent By |
rmcphers |
Date |
2020-07-07 |
Time |
15:41 |
Rev Time |
0.00 |
| Received By |
rmcphers |
Date |
2020-07-07 |
Time |
15:41 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
Z |
ZONING |
| Rev No |
3 |
Status |
P |
Date |
2020-08-18 |
|
|
Cont ID |
|
| Sent By |
kalexand |
Date |
2020-08-18 |
Time |
16:47 |
Rev Time |
0.00 |
| Received By |
kalexand |
Date |
2020-08-18 |
Time |
16:47 |
Sent To |
I |
|
| Notes |
|
|
| Review Stop |
Z |
ZONING |
| Rev No |
2 |
Status |
P |
Date |
2020-08-07 |
|
|
Cont ID |
|
| Sent By |
kalexand |
Date |
2020-08-07 |
Time |
09:41 |
Rev Time |
0.00 |
| Received By |
kalexand |
Date |
2020-08-07 |
Time |
09:25 |
Sent To |
I |
|
| Notes |
|
|
| Review Stop |
Z |
ZONING |
| Rev No |
1 |
Status |
F |
Date |
|
|
|
Cont ID |
|
| Sent By |
kalexand |
Date |
2020-06-29 |
Time |
|
Rev Time |
|
| Received By |
|
Date |
2020-06-29 |
Time |
|
Sent To |
I |
|
| Notes |
| 2020-06-29 08:45:49 | ZONING PLAN REVIEW | | | ________________________________________ | | | | | | DATE OF REVIEW: 6/29/20 | | | ________________________________________ | | | | | | REVIEW STATUS: FAILED | | | ________________________________________ | | | | | | PLEASE PROVIDE A WRITTEN RESPONSE TO THE FOLLOWING PLAN | | | REVIEW COMMENTS: | | | | | | 1. PLEASE PROVIDE A SURVEY INDICATING THE BUILDING | | | SETBACKS AS REQUIRED BY SEC. 94-76(A)(2) OF THE ZONING | | | AND LAND DEVELOPMENT CODE. | | | | | | ________________________________________ | | | | | | PLEASE NOTE THAT SUBMITTAL OF ADDITIONAL AND/OR REVISED | | | MATERIALS MAY RESULT IN NEW PLAN REVIEW COMMENTS. | | | | | | IF THE RESUBMITTAL IS NOT PREPARED BY A DESIGN | | | PROFESSIONAL (ARCHITECT OR ENGINEER), AND THE PAGES ARE | | | 11X17 OR SMALLER, YOU MAY RESUBMIT, ALONG WITH A | | | COMPLETED RESUBMITTAL FORM, VIA EMAIL TO | | | [email protected]. THE EMAIL SHOULD INCLUDE THE PERMIT | | | NUMBER AND "RESUBMITTAL" IN THE SUBJECT LINE. THE | | | RESUBMITTAL FORM CAN BE FOUND AT THIS WEBSITE: | | | | | | HTTP://WPB.ORG/DEPARTMENTS/DEVELOPMENT-SERVICES/FORMS/B | | | UILDING-PERMIT-FORMS | | | | | | IF THE FORM IS TEMPORARILY UNAVAILABLE, PLEASE REQUEST | | | THAT IT BE SENT TO YOU BY EMAILING [email protected] | | | ________________________________________ | | | | | | QUESTIONS/COMMENTS, PLEASE CONTACT THE FOLLOWING: | | | | | | KIZZI ALEXANDRE, ASSOCIATE PLANNER | | | CITY OF WEST PALM BEACH | | | DEVELOPMENT SERVICES DEPARTMENT ? PLANNING DIVISION | | | 401 CLEMATIS STREET - P.O. BOX 3147 | | | WEST PALM BEACH, FLORIDA 33402 | | | | | | P: 561.822.1442 | | | TTY: 800.955.8771 | | | E: [email protected] | | | | | | W: WPB.ORG | | | |
|
|