Plan Review Details - Permit 20050443
Plan Review Stops For Permit 20050443
Review Stop ASBESTOS CONFIRM RPT SENT TO PBC HEALTH
Rev No 2 Status P Date 2020-07-27 Cont ID  
Sent By jwitmer Date 2020-07-27 Time 10:16 Rev Time 0.00
Received By jwitmer Date   Time   Sent To  
Notes
***NONE***

Review Stop ASBESTOS CONFIRM RPT SENT TO PBC HEALTH
Rev No 1 Status F Date 2020-05-27 Cont ID  
Sent By jwitmer Date 2020-05-27 Time 09:43 Rev Time 0.00
Received By jwitmer Date 2020-05-27 Time 09:18 Sent To  
Notes
2020-05-27 09:41:43PLEASE PROVIDE A SIGNED ACKNOWLEDGEMENT FROM THE
 CONTRACTOR, ON LETTERHEAD, STATING THAT THE
 INSTRUCTIONS ON THE WEBSITE OF ASBESTOS PROGRAM
 COORDINATOR, FLORIDA DEPARTMENT OF HEALTH PALM BEACH
 COUNTY WILL BE FOLLOWED AND THAT NOTIFICATION WILL BE
 GIVEN TIMELY. ADDITIONAL INFORMATION REGARDING ASBESTOS
 REQUIREMENTS CAN BE FOUND ON THEIR WEBSITE:
  
 HTTP://PALMBEACH.FLORIDAHEALTH.GOV/PROGRAMS-AND-SERVICE
 S/ENVIRONMENTAL-HEALTH/AIR-QUALITY/ASBESTOS-DEMOLITION-
 RENOVATION.HTML
 19120504
 THE CONTRACTOR ACKNOWLEDGEMENT CAN BE SENT VIA EMAIL TO
 [email protected]. THE INFORMATION SHOULD BE IN PDF
 FORMAT AS AN ATTACHMENT TO THE EMAIL. PLEASE INCLUDE
 THE PERMIT NUMBER AND ?ASBESTOS? IN THE SUBJECT LINE.
  

Review Stop B BUILDING (STRUCTURAL)
Rev No 3 Status P Date 2020-08-31 Cont ID  
Sent By jwitmer Date 2020-08-31 Time 08:30 Rev Time 0.00
Received By jwitmer Date 2020-08-31 Time 08:00 Sent To  
Notes
2020-08-31 08:30:41DATE: MON. JULY 27TH/ AUGUST 31ST/ / 2020
 ACTION:BUILDING PROVISO
  
 1) SHEET A1 INDICATES THE AIR HANDLER IS TO BE
 REPLACED, NOTE 5 INDICATES DUCT WORK TO REMAIN.
 IF THE BI-FOLD DOORS ARE USED TO TRANSFER THE RETURN
 AIR TO THE UNIT THEN THE LOUVER DOORS NEED TO BE METAL.
 2017 FBC-B SECTION 2801.1 MECHANICAL EQUIPMENT AND
 SYSTEMS SHALL BE CONSTRUCTED, INSTALLED AND MAINTAINED
 IN ACCORDANCE WITH THE FBC-M AND FBC-B FOR PLENUMS.
 JAMES A. WITMER BN, PX, SFP, CBO
 SENIOR COMMERCIAL COMBINATION PLANS EXAMINER

Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status P Date 2020-07-27 Cont ID  
Sent By jwitmer Date 2020-07-27 Time 10:16 Rev Time 0.00
Received By jwitmer Date 2020-07-27 Time 09:45 Sent To  
Notes
2020-07-27 10:06:59DATE: MON. JULY 27TH/ 2020
 ACTION:BUILDING PROVISO
  
 1) SHEET A1 INDICATES THE AIR HANDLER IS TO BE
 REPLACED, NOTE 5 INDICATES DUCT WORK TO REMAIN, THE
 PLANS ARE SILENT AS TO HOW THE RETURN AIR IS GETTING TO
 THE AIR HANDLER.
 IF THE BI-FOLD DOORS ARE USED TO TRANSFER THE RETURN
 AIR TO THE UNIT THEN THE LOUVER DOORS NEED TO BE METAL.
 2017 FBC-B SECTION 2801.1 MECHANICAL EQUIPMENT AND
 SYSTEMS SHALL BE CONSTRUCTED, INSTALLED AND MAINTAINED
 IN ACCORDANCE WITH THE FBC-M AND FBC-B FOR PLENUMS.
 JAMES A. WITMER BN, PX, SFP, CBO
 SENIOR COMMERCIAL COMBINATION PLANS EXAMINER

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status F Date 2020-05-27 Cont ID  
Sent By jwitmer Date 2020-05-27 Time 09:45 Rev Time 0.00
Received By jwitmer Date 2020-05-27 Time 09:18 Sent To  
Notes
2020-05-27 09:40:382017 FBC- BUILDING PLAN REVIEW
 W. P. B. PERMIT: 20050443
 ADD: 917 N FLAGLER DR. SUITE: 212
 CONT: WENDELL HALL
 TEL: 561-863-5525
 E-MAIL: [email protected]
  
 2017 FLORIDA BUILDING CODE W 2017 WEST PALM BEACH
 AMENDMENTS TO THE FLORIDA BUILDING CODE, CHAPTER 1,
 ADMINISTRATION
  
 2017 EXISTING BUILDING CODE. 801.3 COMPLIANCE. ALL NEW
 CONSTRUCTION ELEMENTS, COMPONENTS, SYSTEMS, AND SPACES
 SHALL COMPLY WITH THE REQUIREMENTS OF THE FLORIDA
 BUILDING CODE, BUILDING.
  
 1ST REVIEW
 DATE: WED. / MAY 27TH/ 2020
 ACTION: DENIED
  
 1) THEE COVERSHEET LIST BOTH THE WEST PALM BEACH
 BUILDING AND ZONING DIVISIONS AS 2300 N. JOG RD. PLEASE
 CORRECT PLAN SINCE IS THE LOCATION OF THE PALM BEACH
 COUNTY BUILDING & PLANNING DEPARTMENTS. 107.2.1.2
 ADDITIONAL INFORMATION REQUIRED.
  
 2) SHEET A1 INDICATES THE AIR HANDLER IS TO BE
 REPLACED, NOTE 5 INDICATES DUCT WORK TO REMAIN, THE
 PLANS ARE SILENT AS TO HOW THE RETURN AIR IS GETTING TO
 THE AIR HANDLER. IS THE BI-FOLD LOUVER DOOR A LOUVER
 DOOR AND THE RETURN AIR GOES THROUGH THE LOUVER? IS THE
 BI-FOLD DOOR A WOOD LOUVER?
 2017 FBC-B SECTION 2801.1 MECHANICAL EQUIPMENT AND
 SYSTEMS SHALL BE CONSTRUCTED, INSTALLED AND MAINTAINED
 IN ACCORDANCE WITH THE FBC-M AND FBC-B FOR PLENUMS.
  
 3) A TRANSMITTAL LETTER LISTING THE ORIGINAL REVIEW
 COMMENT NUMBER, WITH A DESCRIPTION OF THE REVISION
 MADE, IDENTIFYING THE SHEET OR SPECIFICATION PAGE WHERE
 THE CHANGES CAN BE FOUND WILL HELP TO EXPEDITE YOUR
 PERMIT. THANK YOU FOR YOUR ANTICIPATED COOPERATION.
  
 PLEASE NOTE WE ARE WORKING FROM HOME IF YOU WOULD LIKE
 TO CONTACT ME, MY CELL NUMBER IS 561-718-9724.
 JAMES A. WITMER BN, PX, SFP, CBO
 SENIOR COMMERCIAL COMBINATION PLANS EXAMINER
 BUILDING DIVISION / DEVELOPMENT SERVICES DEPARTMENT
 401 CLEMATIS ST. WEST PALM BEACH. FL 33402
 TEL: 561-805-6717
 FAX: 561-805-6676
 E-MAIL: [email protected]
  
  
  

Review Stop E ELECTRICAL
Rev No 1 Status N Date 2020-06-05 Cont ID  
Sent By jleahy Date 2020-06-05 Time 09:44 Rev Time 0.00
Received By jleahy Date 2020-06-05 Time 09:44 Sent To  
Notes
***NONE***

Review Stop FIRE FIRE DEPARTMENT
Rev No 3 Status P Date 2020-08-27 Cont ID  
Sent By pleduc Date 2020-08-27 Time   Rev Time 0.00
Received By pleduc Date 2020-08-27 Time 11:37 Sent To  
Notes
***NONE***

Review Stop FIRE FIRE DEPARTMENT
Rev No 2 Status P Date 2020-07-23 Cont ID  
Sent By pleduc Date 2020-07-23 Time   Rev Time 0.00
Received By pleduc Date 2020-07-23 Time 13:59 Sent To  
Notes
***NONE***

Review Stop FIRE FIRE DEPARTMENT
Rev No 1 Status P Date 2020-05-21 Cont ID  
Sent By pleduc Date 2020-05-21 Time   Rev Time 0.00
Received By pleduc Date 2020-05-20 Time 10:47 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 3 Status N Date 2020-08-31 Cont ID  
Sent By lcrespo Date 2020-08-31 Time 16:42 Rev Time 0.00
Received By lcrespo Date 2020-08-26 Time 15:52 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2020-08-10 Cont ID  
Sent By cpuell Date 2020-08-10 Time 12:38 Rev Time 0.00
Received By cpuell Date 2020-07-22 Time 09:41 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2020-06-18 Cont ID  
Sent By tklarge Date 2020-06-18 Time 13:46 Rev Time 0.00
Received By tklarge Date 2020-05-19 Time 13:36 Sent To  
Notes
***NONE***

Review Stop M MECHANICAL (A/C)
Rev No 3 Status P Date 2020-08-31 Cont ID  
Sent By jwitmer Date 2020-08-31 Time 08:33 Rev Time 0.00
Received By jwitmer Date   Time   Sent To  
Notes
***NONE***

Review Stop M MECHANICAL (A/C)
Rev No 2 Status P Date 2020-07-31 Cont ID  
Sent By hmoser Date 2020-07-31 Time 13:35 Rev Time 0.00
Received By hmoser Date 2020-07-31 Time 13:24 Sent To  
Notes
***NONE***

Review Stop M MECHANICAL (A/C)
Rev No 1 Status P Date 2020-06-01 Cont ID  
Sent By medwards Date 2020-06-01 Time 10:40 Rev Time 0.00
Received By medwards Date 2020-05-29 Time 12:53 Sent To  
Notes
***NONE***

Review Stop P PLUMBING
Rev No 3 Status P Date 2020-08-31 Cont ID  
Sent By lcrespo Date 2020-08-31 Time 16:42 Rev Time 0.00
Received By lcrespo Date 2020-08-31 Time 16:42 Sent To  
Notes
2020-08-31 16:50:26A SUB PLUMBING PERMIT IS REQUIRED BY A LICENSED
 CONTRACTOR FOR THE SCOPE OF WORK PER THE WPB AMENDMENTS
 TO THE FBC SEC. 105.1.
  
 08/31/20 REVIEWED FOR CODE COMPLIANCE (PLUMBING)
  
 BY REVIEWING THE PLANS / SPECIFICATIONS FOR CODE
 COMPLIANCE DOES NOT RELIEVE THE OWNER, DESIGN
 PROFESSIONAL,
 CONTRACTORS OR THEIR REPRESENTATIVES FROM THE
 RESPONSIBILITY TO COMPLY WITH ALL LOCAL, STATE AND
 NATIONAL CODES AND STANDARDS IN EFFECT AT THE TIME OF
 PERMIT ISSUANCE. OUR REVIEW IS NOT A CHECK OF EVERY
 ITEM AND DOES NOT PREVENT THIS DEPARTMENT FROM
 REQUIRING CORRECTIONS DURING CONSTRUCTION. ANY CHANGES
 / ALTERATIONS TO APPROVED PLANS SHALL BE APPROVED TO
 AVOID VOIDING OF THE PERMIT.
  
 LUIS A. CRESPO
 PLUMBING PLAN EXAMINER / INSPECTOR
 EMAIL: [email protected] OFFICE: 561 805-6720
  

Review Stop P PLUMBING
Rev No 2 Status F Date 2020-08-05 Cont ID  
Sent By abelisle Date 2020-08-05 Time 17:02 Rev Time 0.00
Received By abelisle Date 2020-08-05 Time 16:44 Sent To I
Notes
2020-08-05 17:05:458/5/2020 2ND PLUMBING REVIEW **DENIED** WITH COMMENTS
 NOTE - A COMPREHENSIVE REVIEW COULD NOT BE DONE AT THIS
 TIME AND ADDITIONAL PLAN REVIEW COMMENTS MAY BE
 GENERATED UPON THE RE-REVIEW OF SUBMITTED CORRECTIONS.
  
 1) THERE IS A NOTE ON THE PLANS THAT READS"NO PLUMBING
 OR ELECTRICAL WORK TO BE DONE" BUT THE PLANS CLEARLY
 INDICATE THAT NEW PLUMBING FIXTURES WILL BE REPLACED.
 CLARIFY.( 2ND REQUES )T
  
 ATELYO BELISLE
 PLUMBING INSPECTOR /
 PLUMBING PLAN REVIEW
 AVAILABLE FROM 1:00 PM TO 4:00 PM
 [email protected]
 561-805-6695
  
  
  
  
  

Review Stop P PLUMBING
Rev No 1 Status F Date 2020-06-18 Cont ID  
Sent By tklarge Date 2020-06-18 Time 13:46 Rev Time 0.00
Received By tklarge Date 2020-06-18 Time 13:38 Sent To  
Notes
2020-06-18 13:46:29THERE IS A NOTE ON THE PLANS THAT READS"NO PLUMBING OR
 ELECTRICAL WORK TO BE DONE" BUT THE PLANS CLEARLY
 INDICATE THAT NEW PLUMBING FIXTURES WILL BE REPLACED.
 CLARIFY.
  
 TIM LARGE
 CHIEF PLUMBING INSPECTOR
 PLUMBING PLAN REVIEW
 561-805-6692
 [email protected]
  
  
  
  

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 2 Status P Date 2020-08-31 Cont ID  
Sent By jwitmer Date 2020-08-31 Time 08:33 Rev Time 0.00
Received By jwitmer Date   Time   Sent To  
Notes
***NONE***

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 1 Status P Date 2020-05-29 Cont ID  
Sent By medwards Date 2020-05-29 Time 12:59 Rev Time 0.00
Received By medwards Date 2020-05-29 Time 12:57 Sent To  
Notes
***NONE***


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved