Plan Review Details - Permit 20050100
Plan Review Stops For Permit 20050100
Review Stop ASBESTOS CONFIRM RPT SENT TO PBC HEALTH
Rev No 2 Status P Date 2020-06-23 Cont ID  
Sent By rmcphers Date 2020-06-23 Time 09:37 Rev Time 0.00
Received By rmcphers Date 2020-06-23 Time 09:37 Sent To  
Notes
***NONE***

Review Stop ASBESTOS CONFIRM RPT SENT TO PBC HEALTH
Rev No 1 Status F Date 2020-06-21 Cont ID  
Sent By jwitmer Date 2020-06-21 Time 14:00 Rev Time 0.00
Received By jwitmer Date 2020-06-21 Time 13:27 Sent To  
Notes
2020-06-21 14:00:54PLEASE PROVIDE A SIGNED ACKNOWLEDGEMENT FROM THE
 CONTRACTOR, ON LETTERHEAD, STATING THAT THE
 INSTRUCTIONS ON THE WEBSITE OF ASBESTOS PROGRAM
 COORDINATOR, FLORIDA DEPARTMENT OF HEALTH PALM BEACH
 COUNTY WILL BE FOLLOWED AND THAT NOTIFICATION WILL BE
 GIVEN TIMELY. ADDITIONAL INFORMATION REGARDING ASBESTOS
 REQUIREMENTS CAN BE FOUND ON THEIR WEBSITE:
  
 HTTP://PALMBEACH.FLORIDAHEALTH.GOV/PROGRAMS-AND-SERVICE
 S/ENVIRONMENTAL-HEALTH/AIR-QUALITY/ASBESTOS-DEMOLITION-
 RENOVATION.HTML
 19120504
 THE CONTRACTOR ACKNOWLEDGEMENT CAN BE SENT VIA EMAIL TO
 [email protected]. THE INFORMATION SHOULD BE IN PDF
 FORMAT AS AN ATTACHMENT TO THE EMAIL. PLEASE INCLUDE
 THE PERMIT NUMBER AND ?ASBESTOS? IN THE SUBJECT LINE.
  

Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status P Date 2020-08-03 Cont ID  
Sent By jwitmer Date 2020-08-03 Time 13:02 Rev Time 0.00
Received By jwitmer Date 2020-08-03 Time 12:45 Sent To  
Notes
***NONE***

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status P Date 2020-06-21 Cont ID  
Sent By jwitmer Date 2020-06-21 Time 13:58 Rev Time 0.00
Received By jwitmer Date 2020-06-21 Time 13:27 Sent To  
Notes
***NONE***

Review Stop E ELECTRICAL
Rev No 2 Status P Date 2020-07-30 Cont ID  
Sent By jleahy Date 2020-07-30 Time 07:43 Rev Time 0.00
Received By jleahy Date 2020-07-30 Time 07:43 Sent To  
Notes
***NONE***

Review Stop E ELECTRICAL
Rev No 1 Status P Date 2020-07-07 Cont ID  
Sent By jleahy Date 2020-07-07 Time 12:04 Rev Time 0.00
Received By jleahy Date 2020-07-07 Time 11:57 Sent To  
Notes
***NONE***

Review Stop FIRE FIRE DEPARTMENT
Rev No 1 Status P Date 2020-06-17 Cont ID  
Sent By pleduc Date 2020-06-17 Time   Rev Time 0.00
Received By pleduc Date 2020-06-17 Time 12:55 Sent To  
Notes
2020-06-17 14:44:20THIS PLAN WAS REVIEWED AND APPROVED BY PETER LEDUC,
 FIRE MARSHAL, WITH THE FOLLOWING COMMENTS:
  
 PLEASE CONSIDER THE FOLLOWING AS PROVISO:
  
 THESE PROVISO COMMENTS WILL BE VERIFIED AND CONFIRMED
 AT THE TIME OF FIRE INSPECTION. FAILURE TO FOLLOW THESE
 PROVISO COMMENTS WILL RESULT IN A FAILED FIRE
 INSPECTION.
  
 1) PROTECT FIRE SPRINKLERS AND FIRE ALARM DEVICES AND
 EQUIPMENT.
  
 2) DO NOT PAINT OVER SPRINKLER HEADS AND/OR FIRE ALARM
 DEVICES/EQUIPMENT.
  
 3) THE FS AND FA SYSTEMS SHALL BE MAINTAINED THROUGHOUT
 DEMO AND CONSTRUCTION.
  
 4) ANY REQUIRED FIRE SPRINKLER AND/OR FIRE ALARM WORK
 SHALL BE DONE UNDER SEPARATE PERMIT AND SHOP DRAWINGS.
  
 PETER LEDUC
 FIRE MARSHAL
 561-804-4709
 [email protected]
  

Review Stop I INCOMING/PROCESSING
Rev No 3 Status N Date   Cont ID  
Sent By   Date 2020-08-03 Time 13:02 Rev Time 0.00
Received By lmarchan Date 2020-07-31 Time 14:16 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2020-07-30 Cont ID  
Sent By jleahy Date 2020-07-30 Time 07:44 Rev Time 0.00
Received By jleahy Date 2020-07-17 Time 16:15 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2020-07-07 Cont ID  
Sent By jleahy Date 2020-07-07 Time 12:06 Rev Time 0.00
Received By jleahy Date 2020-06-16 Time 07:52 Sent To  
Notes
***NONE***

Review Stop P PLUMBING
Rev No 1 Status P Date 2020-07-06 Cont ID  
Sent By rmcdouga Date 2020-07-06 Time 08:42 Rev Time 0.00
Received By rmcdouga Date 2020-07-06 Time 07:30 Sent To  
Notes
2020-07-06 08:42:46TIM HUNT
 * PROVISO* SHOWER PAN MATERIAL MANUFACTURES
 INSTALLATION MANUAL MUST BE ON-SITE FOR INSPECTIONS.
 TUB/ SHOWER VALVES MUST BE ASSE 1016 APPROVED. BIDET
 MUST BE TEMPERED TO MAX 110 DEGREES BY A APPROVED ASSE
 1070 DEVICE.

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 3 Status P Date 2020-07-31 Cont ID  
Sent By jleahy Date 2020-07-31 Time 15:24 Rev Time 0.00
Received By jleahy Date 2020-07-31 Time 15:23 Sent To  
Notes
2020-07-31 14:17:05SIGNATURE DOCUMENTS UPLOADED INTO SIGNATURES FOLDER

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 2 Status F Date 2020-07-30 Cont ID  
Sent By jleahy Date 2020-07-30 Time 07:43 Rev Time 0.00
Received By jleahy Date 2020-07-30 Time 07:43 Sent To  
Notes
2020-07-30 07:44:09PLAN IS REQUIRED TO BE SIGNED AND SEALED BY THE DESIGN
 PROFESSIONAL RESPONSIBLE FOR THE DESIGN. FBC 107.2.1,
 FS 471, 481

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 1 Status F Date 2020-07-07 Cont ID  
Sent By jleahy Date 2020-07-07 Time 12:04 Rev Time 0.00
Received By jleahy Date 2020-07-07 Time 12:04 Sent To  
Notes
2020-07-07 12:06:29CODES IN EFFECT:
 FBC = FLORIDA BUILDING CODE 2014 5TH EDITION
 FBC CE = FLORIDA BUILDING CODE ENERGY CONSERVATION 2014
 5TH EDITION
 FBC RE = FLORIDA RESIDENTIAL CODE 2014 5TH EDITION,
 PART VIII ELECTRICAL
 NEC = NFPA 70 2011 EDITION, NATIONAL ELECTRICAL CODE
 FS = FLORIDA STATUTES
  
 ELECTRICAL REVIEW STATUS: DENIED, SEE COMMENTS BELOW.
  
 FLORIDA BUILDING CODE 2017 6TH EDITION
 FLORIDA BUILDING CODE ENERGY CONSERVATION 2017 6TH ED
 NFPA 70 2014 EDITION
  
 JAKE LEAHY BN, BU, PX
 ELECTRICAL PLANS EXAMINER II
 561-805-6713
 [email protected]
  
  
 PLAN IS NOT DIGITALLY SIGNED BY THE DESIGNER OF RECORD
  
 PLAN IS REQUIRED TO BE SIGNED AND SEALED BY A DESIGN
 PROFESSIONAL OR THE ELECTRICAL CONTRACTOR QUALIFIER. FS
 471.003(2)(H); 471.025; FBC 107.2.1
  
  