| 2020-01-30 14:59:40 | A THOROUGH AND COMPLETE PLAN REVIEW CANNOT BE COMPLETED |
| | AT THIS TIME DUE TO LACK OF INFORMATION SUBMITTED ON |
| | THE PLANS. ADDITIONAL PLAN REVIEW COMMENTS MAY BE |
| | GENERATED DURING PLAN RESUBMISSION. |
| | 1. INCLUDE DATA MATERIAL SHEETS FOR MATERIALS TO BE |
| | UTILIZED. |
| | 2. WHAT IS THE SCOPE OF THE ADDITIONAL FIRE LINE TO BE |
| | ADDED TO AN EXISTING SYSTEM? |
| | 3. IF APPLICABLE, DEMOLITION PLANS TO BE SBMITTED FOR |
| | MATERIALS TO BE REPLACED. |
| | 4. PER NFPA 13 & 24, SECTION 10.8.1.1, ALL TEES, PLUGS, |
| | CAPS, BENDS, REDUCERS, VALVES, AND HYDRANT BRANCHES |
| | SHALL BE RESTRAINED AGAINST MOVEMENT BY USING THRUST |
| | BLOCKS OR RESTRAINED JOINT SYSTEMS. |
| | 5. PER NFPA 13 & 24, SECTION 10.8.3.5, AFTER |
| | INSTALLATION, RODS, NUTS, BOLTS, WASHERS, CLAMPS, AND |
| | OTHER RESTRAINING DEVICES SHALL BE CLEANED AND |
| | THOROUGHLY COATED WITH A BITUMINOUS OR OTHER ACCEPTABLE |
| | CORROSION-RETARDING MATERIAL. |
| | 6. PER NFPA 13 & 24, SECTION 10.10.2.1.3, UNDERGROUND |
| | PIPING, FROM THE WATER SUPPLY TO THE SYSTEM RISER, AND |
| | LEAD-IN CONNECTIONS TO THE SYSTEM RISER SHALL BE |
| | COMPLETELY FLUSHED BEFORE CONNECTION IS MADE TO |
| | DOWNSTREAM FIRE PROTECTION SYSTEM PIPING. THE MINIMUM |
| | RATE OF FLOW SHALL BE NOT LESS THAN THE FLOW NECESSARY |
| | TO PROVIDE A VELOCITY OF 10 FEET PER SECOND. |
| | 7. PER NFPA 13 & 24, SECTION 10.10.1, THE INSTALLING |
| | CONTRACTOR SHALL BE RESPONSIBLE FOR THE COMPLETING AND |
| | SIGNING THE CONTRACTOR?S MATERIAL AND TEST |
| | CERTIFICATE(S) SHOWN IN FIGURE 10.10.1. |
| | 8. PER NFPA 13 & 24, SECTION 10.10.2.2.1 ALL PIPING AND |
| | ATTACHED APPURTENANCES SUBJECTED TO SYSTEM WORKING |
| | PRESSURE SHALL BE HYDROSTATICALLY TESTED AT |
| | 200 PSI OR 50 PSI IN EXCESS OF THE SYSTEM WORKING |
| | PRESSURE, WHICHEVER IS GREATER, AND SHALL MAINTAIN THAT |
| | PRESSURE +/-5 PSI FOR 2 HOURS |
| | |
| | S. THOMAS |
| | 561-804-4728 |