Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status P Date 2020-02-04 Cont ID  
Sent By rmcphers Date 2020-02-04 Time 08:16 Rev Time 0.00
Received By rmcphers Date 2020-02-04 Time 07:52 Sent To  
Notes
***NONE***

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status F Date 2019-12-17 Cont ID  
Sent By shill Date 2019-12-17 Time 16:47 Rev Time 0.00
Received By shill Date 2019-12-17 Time 16:32 Sent To  
Notes
2019-12-17 16:47:53****CORRECTIONS****
  
 SAMANTHA HILL
 BUILDING PLANS EXAMINER
 [email protected]
 561-805-6724
  
 FBC = FLORIDA BUILDING CODE, 6TH EDITION (2017)
 FBC B = FBC BUILDING
 FBC EB = FBC EXISTING BUILDING
 FBC A = FBC ACCESSIBILITY
 FBC EC = FBC ENERGY CONSERVATION
 FBC R = FBC RESIDENTIAL
  
 1. APPLICATION IS FOR A GENERATOR; PLANS SUBMITTED
 INCLUDE DETAILS WHICH DO NOT APPEAR PERTINENT TO THE
 GENERATOR INSTALLATION. FOR INSTANCE, SHEET E6.1
 INCLUDES SITE LIGHTING POLES. EITHER REMOVE OR CROSS
 OFF DETAILS NOT APPLICABLE TO THIS PERMIT, FBC 107.
  
 2. FBC B 1609, I WAS UNABLE TO LOCATE A STRUCTURAL
 DETAIL FOR ANCHORING OF THE GENERATOR. THE DETAIL
 SHOULD INCLUDE WIND DESIGN CRITERIA. EITHER PROVIDE OR
 ADVISE ON WHICH PAGE THIS CAN BE FOUND.
  
  

Review Stop E ELECTRICAL
Rev No 2 Status P Date 2020-01-13 Cont ID  
Sent By jleahy Date 2020-01-13 Time 13:46 Rev Time 0.00
Received By jleahy Date 2020-01-13 Time 13:46 Sent To  
Notes
***NONE***

Review Stop E ELECTRICAL
Rev No 1 Status F Date 2019-12-24 Cont ID  
Sent By jleahy Date 2019-12-24 Time 14:31 Rev Time 0.00
Received By jleahy Date 2019-12-24 Time 14:31 Sent To  
Notes
2019-12-24 15:27:15FLORIDA BUILDING CODE 2017 6TH EDITION
 FLORIDA BUILDING CODE ENERGY CONSERVATION 2017 6TH ED
 NFPA 70 2014 EDITION
  
 JAKE LEAHY BN, BU, PX
 ELECTRICAL PLANS EXAMINER II
 561-805-6713
 [email protected]
  
 1) VALUE FOR THE GENERATOR PERMIT IS LOW, SUBMIT A
 SIGNED CONTRACT FOR WORK INVOLVED SHOWING GENERATOR,
 TRANSFER SWITCH, ENCLOSURE, AND LABOR.
  
 109.3 BUILDING PERMIT VALUATIONS. IF, IN THE OPINION OF
 THE BUILDING OFFICIAL, THE CLAIMED VALUATION OF
 BUILDING, ALTERATION, STRUCTURE, ELECTRICAL, GAS,
 MECHANICAL OR PLUMBING SYSTEMS APPEARS TO BE
 UNDERESTIMATED ON THE APPLICATION, THE PERMIT SHALL BE
 DENIED, UNLESS THE APPLICANT CAN SHOW DETAILED,
 QUANTITY ESTIMATES, AND/OR BONA FIDE SIGNED CONTRACTS
 (EXCLUDING LAND VALUE) TO MEET THE APPROVAL OF THE
 BUILDING OFFICIAL. FOR PERMITTING PURPOSES, VALUATION
 OF BUILDINGS AND SYSTEMS SHALL BE TOTAL REPLACEMENT
 VALUE TO INCLUDE STRUCTURAL, ELECTRIC, PLUMBING,
 MECHANICAL, INTERIOR FINISH, RELATIVE SITE WORK,
 ARCHITECTURAL AND DESIGN FEES, MARKETING COSTS,
 OVERHEAD AND PROFIT; EXCLUDING ONLY LAND VALUE.
 VALUATION REFERENCES MAY INCLUDE THE LATEST PUBLISHED
 DATA OF NATIONAL CONSTRUCTION COST ANALYSIS SERVICES
 (MARSHALL-SWIFT, MEANS, ETC.), AS PUBLISHED BY
 INTERNATIONAL CODE CONGRESS. FINAL BUILDING PERMIT
 VALUATION SHALL BE SET BY THE BUILDING OFFICIAL.

Review Stop FIRE FIRE DEPARTMENT
Rev No 2 Status P Date 2020-01-23 Cont ID  
Sent By pleduc Date 2020-01-23 Time   Rev Time 0.00
Received By pleduc Date 2020-01-23 Time 11:44 Sent To  
Notes
***NONE***

Review Stop FIRE FIRE DEPARTMENT
Rev No 1 Status F Date 2019-12-09 Cont ID  
Sent By pleduc Date 2019-12-09 Time   Rev Time 0.00
Received By pleduc Date 2019-12-06 Time 12:55 Sent To  
Notes
2019-12-09 11:53:26THIS PLAN WAS REVIEWED AND FAILED BY PETER LEDUC, FIRE
 MARSHAL, WITH THE FOLLOWING COMMENTS:
  
  
 1) THERE ARE NO INDICATIONS OR PRODUCT SUBMITTALS OF
 THE GENERATOR TYPE NOR FUEL SUPPLY.
  
 PLEASE PROVIDE THE GENERATOR SPECIFICATION SHEETS AND
 FUEL SUPPLY.
  
  
 2) THERE ARE NO INDICATIONS OF WHAT CALSSIFICATION,
 TYPE NOR LEVEL PER NFPA 110, EMERGENCY AND STANDBY
 POWER SYSTEMS
  
 CHAPTER 4 CLASSIFICATION OF EMERGENCY POWER SUPPLY
 SYSTEMS (EPSSS)
 4.1* GENERAL. THE EPSS SHALL PROVIDE A SOURCE OF
 ELECTRICAL
 POWER OF REQUIRED CAPACITY, RELIABILITY, AND QUALITY TO
 LOADS FOR
 A LENGTH OF TIME AS SPECIFIED IN TABLE 4.1(A) AND
 WITHIN A SPECIFIED
 TIME FOLLOWING LOSS OR FAILURE OF THE NORMAL POWER
 SUPPLY
 AS SPECIFIED IN TABLE 4.1(B).
  
 4.2* CLASS. THE CLASS DEFINES THE MINIMUM TIME, IN
 HOURS, FOR
 WHICH THE EPSS IS DESIGNED TO OPERATE AT ITS RATED LOAD
 WITHOUT
 BEING REFUELED OR RECHARGED. [SEE TABLE 4.1(A).]
 4.3 TYPE. THE TYPE DEFINES THE MAXIMUM TIME, IN
 SECONDS,
 THAT THE EPSS WILL PERMIT THE LOAD TERMINALS OF THE
 TRANSFER
 SWITCH TO BE WITHOUT ACCEPTABLE ELECTRICAL POWER. TABLE
 4.1(B)
 PROVIDES THE TYPES DEFINED BY THIS STANDARD.
 4.4* LEVEL. THIS STANDARD RECOGNIZES TWO LEVELS OF
 EQUIPMENT
 INSTALLATION, PERFORMANCE, AND MAINTENANCE.
 4.4.1* LEVEL 1 SYSTEMS SHALL BE INSTALLED WHERE FAILURE
 OF THE
 EQUIPMENT TO PERFORM COULD RESULT IN LOSS OF HUMAN LIFE
 OR
 SERIOUS INJURIES.
 4.4.2* LEVEL 2 SYSTEMS SHALL BE INSTALLED WHERE FAILURE
 OF THE
 EPSS TO PERFORM IS LESS CRITICAL TO HUMAN LIFE AND
 SAFETY.
 4.4.3 ALL EQUIPMENT SHALL BE PERMANENTLY INSTALLED.
 4.4.4* LEVEL 1 AND LEVEL 2 SYSTEMS SHALL ENSURE THAT
 ALL LOADS
 SERVED BY THE EPSS ARE SUPPLIED WITH ALTERNATE POWER
 THAT
 MEETS ALL THE FOLLOWING CRITERIA:
 (1) OF A QUALITY WITHIN THE OPERATING LIMITS OF THE
 LOAD
 (2) FOR A DURATION SPECIFIED FOR THE CLASS AS DEFINED
 IN TABLE
 4.1(A)
 (3) WITHIN THE TIME SPECIFIED FOR THE TYPE AS DEFINED
 IN TABLE
 4.1(B)
  
 PLEASE REVIEW AND PROVIDE DETAILS.
  
  
 3) THERE ARE NO INDICATIONS OF THE EXHAUST SYSTEM.
  
 7.10 EXHAUST SYSTEM.
 7.10.1 THE EXHAUST SYSTEM EQUIPMENT AND INSTALLATION,
 INCLUDING
 PIPING, MUFFLER, AND RELATED ACCESSORIES, SHALL BE IN
 ACCORDANCE WITH NFPA37, STANDARD FOR THE INSTALLATION
 AND USE OF
 STATIONARY COMBUSTION ENGINES AND GAS TURBINES, AND
 OTHER APPLICABLE
 STANDARDS.
 7.10.2 EXHAUST SYSTEM INSTALLATION SHALL BE GASTIGHT TO
 PREVENT
 EXHAUST GAS FUMES FROM ENTERING INHABITED ROOMS OR
 BUILDINGS
 AND TERMINATE IN SUCH A MANNER THAT TOXIC FUMES CANNOT
 REENTER A BUILDING OR STRUCTURE, PARTICULARLY THROUGH
 WINDOWS,
 AIR VENTILATION INLETS, OR THE ENGINE AIR-INTAKE
 SYSTEM.
 7.10.3* EXHAUST PIPING SHALL BE CONNECTED TO THE PRIME
 MOVER
 BY MEANS OF A FLEXIBLE CONNECTOR AND SHALL BE
 INDEPENDENTLY
 SUPPORTED THEREAFTER SO THAT NO DAMAGING WEIGHT OR
 STRESS IS
 APPLIED TO THE ENGINE EXHAUST MANIFOLD OR TURBOCHARGER.
  
 PLEASE REVIEW AND PROVIDE DETAILS
  
  
 4) THE AREA FOR THE GENERATOR APPEARS TO OUTSIDE THE
 STRUCTURE IN AN ENCLOSURE.
  
 PLEASE CONFIRM THE FOUNDATION IS NOT SEPARATE FROM THE
 MAIN BUILDING SLAB. IF NOT, PLEASE PROVIDE SLAB
 DETAILS.
  
 7.2.2 OUTDOOR EPS INSTALLATIONS.
 7.2.2.1 THE EPS SHALL BE INSTALLED IN A SUITABLE
 ENCLOSURE LOCATED
 OUTSIDE THE BUILDING AND CAPABLE OF RESISTING THE
 ENTRANCE
 OF SNOW OR RAIN AT A MAXIMUM WIND VELOCITY AS REQUIRED
 BY LOCAL BUILDING CODES.
 7.2.2.2 EPSS EQUIPMENT SHALL BE PERMITTED TO BE
 INSTALLED IN
 THE EPS ENCLOSURE.
 7.2.2.3 NO OTHER EQUIPMENT, INCLUDING ARCHITECTURAL
 APPURTENANCES,
 EXCEPT THOSE THAT SERVE THIS SPACE, SHALL BE PERMITTED
 IN THE EPS ENCLOSURE.
 7.2.3* LEVEL 1 EPSS EQUIPMENT SHALL NOT BE INSTALLED IN
 THE
 SAME ROOM WITH THE NORMAL SERVICE EQUIPMENT, WHERE THE
 SERVICE
 EQUIPMENT IS RATED OVER 150 VOLTS TO GROUND AND EQUAL
 TO
 OR GREATER THAN 1000 AMPERES.
 7.2.4* THE ROOMS, ENCLOSURES, OR SEPARATE BUILDINGS
 HOUSING
 LEVEL 1 OR LEVEL 2 EPSS EQUIPMENT SHALL BE DESIGNED AND
 LOCATED
 TO MINIMIZE DAMAGE FROM FLOODING, INCLUDING THAT
 CAUSED BY THE FOLLOWING:
 (1) FLOODING RESULTING FROM FIRE FIGHTING
 (2) SEWER WATER BACKUP
 (3) OTHER DISASTERS OR OCCURRENCES
  
 PROVIDE DETAILS.
  
 5) THERE ARE NO MOUNTING DETAILS
  
 7.4 MOUNTING.
 7.4.1 ROTATING ENERGY CONVERTERS SHALL BE INSTALLED ON
 SOLID
 FOUNDATIONS TO PROHIBIT SAGGING OF FUEL, EXHAUST, OR
 LUBRICATINGOIL
 PIPING AND DAMAGE TO PARTS RESULTING IN LEAKAGE AT
 JOINTS.
 7.4.1.1 SUCH FOUNDATIONS OR STRUCTURAL BASES SHALL
 RAISE THE
 ENGINE AT LEAST 150 MM (6 IN.) ABOVE THE FLOOR OR GRADE
 LEVEL
 AND BE OF SUFFICIENT ELEVATION TO FACILITATE
 LUBRICATING-OIL DRAINAGE
 AND EASE OF MAINTENANCE.
 7.4.2 FOUNDATIONS SHALL BE OF THE SIZE (MASS) AND TYPE
 RECOMMENDED
 BY THE ENERGY CONVERTER MANUFACTURER.
 7.4.3 WHERE REQUIRED TO PREVENT TRANSMISSION OF
 VIBRATION
 DURING OPERATION, THE FOUNDATION SHALL BE ISOLATED FROM
 THE
 SURROUNDING FLOOR OR OTHER FOUNDATIONS, OR BOTH, IN
 ACCORDANCE
 WITH THE MANUFACTURER?S RECOMMENDATIONS AND ACCEPTED
 STRUCTURAL ENGINEERING PRACTICES.
  
 PLEASE PROVIDE DETAILS.
  
  
 6) THERE IS NO INDICATIONS FOR THE NEED OF VENTILATION
 FOR THE PROPOSED GENERATOR AND/OR THE ENCLOSURES'
 ABILITY TO VENTILATE.
  
 7.7 HEATING, COOLING, AND VENTILATING.
 7.7.1* WITH THE EPS RUNNING AT RATED LOAD, VENTILATION
 AIRFLOW
 SHALL BE PROVIDED TO LIMIT THE MAXIMUM AIR TEMPERATURE
 IN THE
 EPS ROOM OR THE ENCLOSURE HOUSING THE UNIT TO THE
 MAXIMUM
 AMBIENT AIR TEMPERATURE REQUIRED BY THE EPS
 MANUFACTURER.
 7.7.1.1 CONSIDERATION SHALL BE GIVEN TO ALL THE HEAT
 EMITTED TO
 THE EPS EQUIPMENT ROOM BY THE ENERGY CONVERTER,
 UNINSULATED
 OR INSULATED EXHAUST PIPES, AND OTHER HEAT-PRODUCING
 EQUIPMENT.
  
 PLEASE REVIEW AND PROVIDE DETAILS.
  
  
 7) WHEN RESUBMITTING, PLEASE PROVIDE PLAN SHEET
 REVISION CLOUDS OR NUMBERED NARRATIVE RESPONSES TO THE
 ABOVE.
  
  
 8) ADDITIONAL COMMENTS MAY BE PROVIDED ON THE
 RE-SUBMITTAL OF THE ABOVE.
  
  
 PETER LEDUC
 FIRE MARSHAL
 561-804-4709
 [email protected]
  

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2020-02-04 Cont ID  
Sent By rmcphers Date 2020-02-04 Time 08:18 Rev Time 0.00
Received By rmcphers Date 2020-01-22 Time 11:08 Sent To  
Notes
2020-02-04 08:19:54EMAIL SENT TO PERMIT LIBRARY

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2020-01-09 Cont ID  
Sent By lmarchan Date 2020-01-09 Time 12:55 Rev Time 0.00
Received By lmarchan Date 2019-12-04 Time 10:36 Sent To  
Notes
***NONE***

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 1 Status P Date 2019-12-17 Cont ID  
Sent By shill Date 2019-12-17 Time 16:49 Rev Time 0.00
Received By shill Date 2019-12-17 Time 16:49 Sent To  
Notes
***NONE***

Review Stop Z ZONING
Rev No 2 Status P Date 2020-01-29 Cont ID  
Sent By eschneid Date 2020-01-29 Time 09:49 Rev Time 0.50
Received By eschneid Date 2020-01-29 Time 08:53 Sent To  
Notes
***NONE***

Review Stop Z ZONING
Rev No 1 Status F Date 2020-01-09 Cont ID  
Sent By eschneid Date 2020-01-09 Time 12:06 Rev Time 0.50
Received By eschneid Date 2020-01-09 Time 11:38 Sent To  
Notes
2020-01-09 12:06:43FAILED
  
 1) PROVIDE THE FULL HEIGHT OF THE GENERATOR, TO INCLUDE
 THE STAND, FUEL TANK AND EXHAUST VENTS AS WELL AS THE
 HEIGHT OF THE GENERATOR ENCLOSURE WALL. THE WALL HEIGHT
 MUST EXCEED THE FULL HEIGHT OF THE GENERATOR.
  
 2) REMOVE THE SITE LIGHTING SHEET FROM THE PERMIT AS
 THIS IS THE GENERATOR PERMIT, NOT THE SITE LIGHTING
 PERMIT.
  
 CONTACT ERIC SCHNEIDER @ (561) 822-1446.
 [email protected]


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved