| Plan Review Stops For Permit 19090551 |
| Review Stop |
B |
BUILDING (STRUCTURAL) |
| Rev No |
3 |
Status |
P |
Date |
2019-12-20 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2019-12-20 |
Time |
14:17 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2019-12-20 |
Time |
14:17 |
Sent To |
|
|
| Notes |
| 2019-12-20 14:50:31 | DIGITALLY SIGNED PLANS WERE SUBMITTED BY EMAIL. |
|
|
| Review Stop |
B |
BUILDING (STRUCTURAL) |
| Rev No |
2 |
Status |
F |
Date |
2019-12-19 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2019-12-19 |
Time |
15:29 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2019-12-19 |
Time |
15:29 |
Sent To |
I |
|
| Notes |
| 2019-12-19 15:35:44 | PLAN | | | REVIEW COMMENTS | | | | | | 2ND REVIEW: FBC SIXTH EDITION (2017) | | | ROBERT MCDOUGAL, CBO | | | COMMERCIAL COMBINATION PLANS EXAMINER | | | (561) 805-6714 | | | [email protected] | | | | | | DENIED BY BUILDING | | | PLEASE ADDRESS THE ITEMS NOTED BELOW: | | | | | | 1) FIRST COMMENT WAS NOT ADDRESSED. THE GENERATOR PAD | | | DETAILS THAT WERE SUBMITTED DO NOT HAVE THE ENGINEER'S | | | ORIGINAL SIGNATURE AS REQUIRED BY SECTION 471.025, | | | F.S., AND RULE 61G15-23.001, F.A.C. SUBMIT TWO SETS OF | | | GENERATOR PAD AND GENERATOR TO PAD ANCHORING DETAILS. | | | PRE-FABRICATED PADS REQUIRE SIGNED AND SEALED | | | ENGINEERING. FBC 107.2.1 |
|
|
| Review Stop |
B |
BUILDING (STRUCTURAL) |
| Rev No |
1 |
Status |
F |
Date |
2019-10-08 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2019-10-08 |
Time |
17:34 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2019-10-08 |
Time |
17:34 |
Sent To |
I |
|
| Notes |
| 2019-10-08 17:40:46 | PLAN | | | REVIEW COMMENTS | | | | | | 1ST REVIEW: FBC SIXTH EDITION (2017) | | | ROBERT MCDOUGAL, CBO | | | COMMERCIAL COMBINATION PLANS EXAMINER | | | (561) 805-6714 | | | [email protected] | | | | | | DENIED BY BUILDING | | | PLEASE ADDRESS THE ITEMS NOTED BELOW: | | | | | | 1) SUBMIT TWO SETS OF GENERATOR PAD AND GENERATOR TO | | | PAD ANCHORING DETAILS. PRE-FABRICATED PADS REQUIRE | | | SIGNED AND SEALED ENGINEERING. FBC 107.2.1 |
|
|
| Review Stop |
E |
ELECTRICAL |
| Rev No |
3 |
Status |
P |
Date |
2020-01-09 |
|
|
Cont ID |
|
| Sent By |
jleahy |
Date |
2020-01-09 |
Time |
10:49 |
Rev Time |
0.00 |
| Received By |
jleahy |
Date |
2020-01-09 |
Time |
10:49 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
E |
ELECTRICAL |
| Rev No |
2 |
Status |
F |
Date |
2019-12-23 |
|
|
Cont ID |
|
| Sent By |
jleahy |
Date |
2019-12-23 |
Time |
13:44 |
Rev Time |
0.00 |
| Received By |
jleahy |
Date |
2019-12-23 |
Time |
13:44 |
Sent To |
|
|
| Notes |
| 2019-12-23 13:46:37 | FLORIDA BUILDING CODE 2017 6TH EDITION | | | FLORIDA BUILDING CODE ENERGY CONSERVATION 2017 6TH ED | | | NFPA 70 2014 EDITION | | | | | | JAKE LEAHY BN, BU, PX | | | ELECTRICAL PLANS EXAMINER II | | | 561-805-6713 | | | [email protected] | | | | | | 1) VALUE OF WORK LOW PLEASE SUBMIT A SIGNED CONTRAC FOR | | | THE WORK INVOLVED SHOWING TOTAL PRICE OF INSTALLATION. | | | | | | 109.3 BUILDING PERMIT VALUATIONS. IF, IN THE OPINION OF | | | THE BUILDING OFFICIAL, THE CLAIMED VALUATION OF | | | BUILDING, ALTERATION, STRUCTURE, ELECTRICAL, GAS, | | | MECHANICAL OR PLUMBING SYSTEMS APPEARS TO BE | | | UNDERESTIMATED ON THE APPLICATION, THE PERMIT SHALL BE | | | DENIED, UNLESS THE APPLICANT CAN SHOW DETAILED, | | | QUANTITY ESTIMATES, AND/OR BONA FIDE SIGNED CONTRACTS | | | (EXCLUDING LAND VALUE) TO MEET THE APPROVAL OF THE | | | BUILDING OFFICIAL. FOR PERMITTING PURPOSES, VALUATION | | | OF BUILDINGS AND SYSTEMS SHALL BE TOTAL REPLACEMENT | | | VALUE TO INCLUDE STRUCTURAL, ELECTRIC, PLUMBING, | | | MECHANICAL, INTERIOR FINISH, RELATIVE SITE WORK, | | | ARCHITECTURAL AND DESIGN FEES, MARKETING COSTS, | | | OVERHEAD AND PROFIT; EXCLUDING ONLY LAND VALUE. | | | VALUATION REFERENCES MAY INCLUDE THE LATEST PUBLISHED | | | DATA OF NATIONAL CONSTRUCTION COST ANALYSIS SERVICES | | | (MARSHALL-SWIFT, MEANS, ETC.), AS PUBLISHED BY | | | INTERNATIONAL CODE CONGRESS. FINAL BUILDING PERMIT | | | VALUATION SHALL BE SET BY THE BUILDING OFFICIAL |
|
|
| Review Stop |
E |
ELECTRICAL |
| Rev No |
1 |
Status |
P |
Date |
2019-10-03 |
|
|
Cont ID |
|
| Sent By |
jleahy |
Date |
2019-10-03 |
Time |
10:40 |
Rev Time |
0.00 |
| Received By |
jleahy |
Date |
2019-10-03 |
Time |
10:40 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
G |
GAS REVIEW |
| Rev No |
1 |
Status |
N |
Date |
2019-10-04 |
|
|
Cont ID |
|
| Sent By |
lcrespo |
Date |
2019-10-04 |
Time |
06:36 |
Rev Time |
0.00 |
| Received By |
lcrespo |
Date |
2019-10-04 |
Time |
06:36 |
Sent To |
|
|
| Notes |
| 2019-10-04 06:37:51 | GAS REVIEW DONE UNDER PERMIT 19090705 AND IT'S HAS | | | PASSED. |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
2 |
Status |
N |
Date |
2019-12-19 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2019-12-19 |
Time |
15:35 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2019-12-18 |
Time |
14:32 |
Sent To |
|
|
| Notes |
| 2019-12-19 14:32:33 | RESUB ROUTED TO RMCDOUGAL |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
1 |
Status |
N |
Date |
2019-10-08 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2019-10-08 |
Time |
17:34 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2019-09-25 |
Time |
12:56 |
Sent To |
|
|
| Notes |
| 2019-09-26 12:56:58 | ROUTED TO ZONING INBOX |
|
|
| Review Stop |
Z |
ZONING |
| Rev No |
1 |
Status |
P |
Date |
2019-09-27 |
|
|
Cont ID |
|
| Sent By |
rfalcone |
Date |
2019-09-27 |
Time |
13:40 |
Rev Time |
0.00 |
| Received By |
rfalcone |
Date |
2019-09-27 |
Time |
13:40 |
Sent To |
|
|
| Notes |
|
|