| Plan Review Stops For Permit 19090347 |
| Review Stop |
AIPP |
ART IN PUBLIC PLACES |
| Rev No |
1 |
Status |
P |
Date |
2021-04-30 |
|
|
Cont ID |
|
| Sent By |
scwelter |
Date |
2021-04-30 |
Time |
11:22 |
Rev Time |
0.00 |
| Received By |
scwelter |
Date |
2021-04-30 |
Time |
11:23 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
B |
BUILDING (STRUCTURAL) |
| Rev No |
2 |
Status |
P |
Date |
2019-10-18 |
|
|
Cont ID |
|
| Sent By |
jgomez |
Date |
2019-10-18 |
Time |
18:03 |
Rev Time |
0.00 |
| Received By |
jgomez |
Date |
2019-10-18 |
Time |
09:55 |
Sent To |
|
|
| Notes |
| 2019-10-18 10:02:49 | BUILDING REVIEW APPROVED WITH PROVISO: | | | 1- THIS BUILDING REVIEW IS FOR THE VERTICAL | | | CONSTRUCTION PHASE ONLY. | | | ARCHITECTURAL PLANS AND LIFESAFETY PLANS ARE FOR | | | REFERENCE ONLY. COMPLETE REVIEW WILL BE PERFORMED UNDER | | | THE MAIN BUILDING PERMIT #19030235. | | | 2- ARCHITECTURAL AND STRUCTURAL PLANS SPECIFY | | | FIRE-RETARDANT-TREATED WOOD TRUSSES AS ALLOWED BY SEC. | | | 603.1 FBC-BUILDING. | | | NEED TO REVISE ALL DETAILS/SPECIFICATIONS SHOWING ALL | | | STRUCTURAL FRAMING MEMBER TO BE FIRE-RETARDANT-TREATED | | | WOOD AS WELL. THIS APPLIES TO ANY LEDGER, BEAM, ETC. |
|
|
| Review Stop |
B |
BUILDING (STRUCTURAL) |
| Rev No |
1 |
Status |
F |
Date |
2019-10-02 |
|
|
Cont ID |
|
| Sent By |
jgomez |
Date |
2019-10-02 |
Time |
14:50 |
Rev Time |
0.00 |
| Received By |
jgomez |
Date |
2019-10-01 |
Time |
18:43 |
Sent To |
|
|
| Notes |
| 2019-10-02 14:52:39 | BUILDING VERTICAL SHELL. RESIDENTIAL (R2) BUILDING | | | REVIEW COMMENTS | | | CODE: FBC 6TH EDITION (2017) AND CITY AMENDMENTS. | | | | | | 1- COVER SHEET 001-A-0.0 WAS NOT SIGNED AND SEALED. | | | NEED DIGITAL SIGNATURE. | | | 61G1-16.005 PROCEDURES FOR DIGITALLY SIGNING AND | | | SEALING AND FOR ELECTRONICALLY TRANSMITTING PLANS, | | | SPECIFICATIONS, REPORTS OR OTHER DOCUMENTS. | | | | | | 2- ALL THE STRUCTURAL DRAWINGS SPECIFY WOOD TRUSSES. | | | ALL THE ARCHITECTURAL PLANS ON BUILDING PERMIT 19030235 | | | SPECIFY METAL TRUSSES. THIS IS A TYPE 1B BUILDING. THE | | | BUILDING ELEMENTS ON A TYPE 1B CONSTRUCTION BUILDING | | | NEED TO BE OF NONCOMBUSTIBLE MATERIALS. SEC. 602.2 | | | FBC-BUILDING. REVISE ALL STRUCTURAL DRAWINGS. REVISE | | | ALL STRUCTURAL PLANS AND DETAILS THAT ARE SPECIFYING | | | WOOD TRUSSES OR WOOD LEDGERS AND REVISE CORRESPONDING | | | STRUCTURAL CONNECTIONS AS WELL. SEC. 1601.1 | | | FBC-BUILDING. COORDINATE WITH THE ARCHITECTURAL PLANS. | | | | | | IN ORDER TO AVOID MULTIPLE SUBMITTALS, PLEASE FEEL FREE | | | TO CONTACT ME IF YOU HAVE ANY QUESTIONS REGARDING THESE | | | COMMENTS, | | | JULIO GOMEZ | | | COMMERCIAL COMBINATION PLANS EXAMINER | | | DEVELOPMENT SERVICES DEPARTMENT | | | BUILDING DIVISION | | | (561)805-6712 | | | [email protected] | | | | | | | | | REMAINDER FOR FOUNDATION PERMIT APPROVED UNDER PERMIT | | | #19030239. | | | | | | | | | FOUNDATION PERMIT APPROVED WITH PROVISO | | | 1- SHEET A-2.1: REVISE TYPO ON SIZE OF GRATE ON THE | | | GRATE DETAIL. CALCULATIONS SPECIFY 4.75' NOT 14.75'. | | | AND PROVIDE COMPLETE DETAILS/SPECIFICATIONS FOR THE | | | CONSTRUCTION OF THE GRATES. SEE SEC. 2.7.2.1 ASCE/SEI | | | 24-14. | | | NOTE: TAKE INTO CONSIDERATION ACCESS TO THE CREATED | | | CRAWL SPACE. | | | 2- REVISE/CLARIFY "CONSTRUCTION DRAWINGS" ELEVATION | | | CERTIFICATE. SEE REDLINED ELEVATION CERTIFICATE. | | | ADDITIONAL ELEVATION CERTIFICATES WILL BE REQUIRED FOR | | | BUILDING UNDER CONSTRUCTION AND FINISHED CONSTRUCTION. | | | 3- SURVEYOR'S NOTE #13 SPECIFIES BASE FLOOD ELEVATION | | | OF 12.7 FEET. SPECIFY IF N.A.V.D 1988 OR N.G.V.D 1929. | | | 4- BASED ON THE HEIGHT OF THE BUILDING, A BARRIER AND | | | COVERED WALKWAY FOR PROTECTION OF PEDESTRIANS WILL BE | | | REQUIRED. SEC. 3306.1 FBC-BUILDING. | | | 5- ART IN PUBLIC PLACES. PLEASE CONTACT MS. SYBILLE | | | WELTER ART IN PUBLIC PLACES COORDINATOR 822-1515 | | | E-MAIL: [email protected] FOR MORE INFORMATION. | | | | | | | | | |
|
|
| Review Stop |
E |
ELECTRICAL |
| Rev No |
1 |
Status |
P |
Date |
2019-10-04 |
|
|
Cont ID |
|
| Sent By |
jleahy |
Date |
2019-10-04 |
Time |
08:09 |
Rev Time |
0.00 |
| Received By |
jleahy |
Date |
2019-10-04 |
Time |
07:33 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
ENG |
ENGINEERING CSD |
| Rev No |
2 |
Status |
P |
Date |
2019-10-22 |
|
|
Cont ID |
|
| Sent By |
rrossano |
Date |
2019-10-22 |
Time |
|
Rev Time |
0.00 |
| Received By |
rrossano |
Date |
2019-10-22 |
Time |
|
Sent To |
|
|
| Notes |
|
|
| Review Stop |
ENG |
ENGINEERING CSD |
| Rev No |
1 |
Status |
F |
Date |
2019-10-09 |
|
|
Cont ID |
|
| Sent By |
rrossano |
Date |
2019-10-09 |
Time |
|
Rev Time |
|
| Received By |
rrossano |
Date |
2019-10-09 |
Time |
|
Sent To |
|
|
| Notes |
| 2019-10-09 12:01:48 | PLEASE ADDRESS BUILDING COMMENTS. |
|
|
| Review Stop |
FIRE |
FIRE DEPARTMENT |
| Rev No |
2 |
Status |
P |
Date |
2019-10-16 |
|
|
Cont ID |
|
| Sent By |
pleduc |
Date |
2019-10-16 |
Time |
|
Rev Time |
0.00 |
| Received By |
pleduc |
Date |
2019-10-16 |
Time |
10:06 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
FIRE |
FIRE DEPARTMENT |
| Rev No |
1 |
Status |
P |
Date |
2019-10-08 |
|
|
Cont ID |
|
| Sent By |
pleduc |
Date |
2019-10-03 |
Time |
|
Rev Time |
0.00 |
| Received By |
pleduc |
Date |
2019-09-16 |
Time |
14:19 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
2 |
Status |
N |
Date |
2019-10-24 |
|
|
Cont ID |
|
| Sent By |
lmarchan |
Date |
2019-10-24 |
Time |
12:03 |
Rev Time |
0.00 |
| Received By |
lmarchan |
Date |
2019-10-15 |
Time |
13:05 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
1 |
Status |
N |
Date |
2019-10-11 |
|
|
Cont ID |
|
| Sent By |
cpuell |
Date |
2019-10-11 |
Time |
16:26 |
Rev Time |
0.00 |
| Received By |
cpuell |
Date |
2019-10-01 |
Time |
09:43 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
IMPACT |
COUNTY IMPACT FEES |
| Rev No |
2 |
Status |
P |
Date |
2019-10-24 |
|
|
Cont ID |
|
| Sent By |
lmarchan |
Date |
2019-10-24 |
Time |
12:03 |
Rev Time |
0.00 |
| Received By |
lmarchan |
Date |
2019-10-07 |
Time |
10:38 |
Sent To |
|
|
| Notes |
| 2019-10-24 12:02:56 | RECEIPT 2019-1025-34 - $420,632.63 - PAID | | | (PLANS STAMPED ON PERMIT 19030235) | | 2019-10-07 10:38:47 | 10/7/19 EMAILED IMPACT FEE OFFICE FOR REVIEW. LEM |
|
|
| Review Stop |
IMPACT |
COUNTY IMPACT FEES |
| Rev No |
1 |
Status |
F |
Date |
2019-10-02 |
|
|
Cont ID |
|
| Sent By |
jgomez |
Date |
2019-10-02 |
Time |
10:56 |
Rev Time |
0.00 |
| Received By |
jgomez |
Date |
2019-10-02 |
Time |
10:56 |
Sent To |
|
|
| Notes |
| 2019-10-02 10:56:56 | IMPACT FEES - DIGITAL SUBMITTALS | | | PLANS WILL BE REVIEWED BY THE PBC IMPACT FEE OFFICE | | | DIGITALLY VIA PROJECTDOX UPON NOTIFICATION BY THIS | | | OFFICE. NOTIFICATION MAY OCCUR WHEN PLANS ARE NEAREST | | | FINAL FORM. YOU MAY COORDINATE WITH THE IMPACT FEE | | | OFFICE AT (561) 233-5025 OR SIMPLY UPLOAD THE MUNICIPAL | | | IMPACT FEE QUESTIONNAIRE FORM TO YOUR PROJECT AND NAME | | | THE FILE MUNICIPAL IMPACT FEE QUESTIONNAIRE. THE FORM | | | CAN BE FOUND AT: HTTP://DISCOVER.PBCGOV.ORG/PZB/ADMINIS | | | TRATION/PDF/IMPACTFEES/FORMS/QUESTIONNAIRE.PDF UPON | | | APPROVAL AND FEE PAYMENT, PLEASE UPLOAD THE RECEIPT TO | | | YOUR PROJECT OR EMAIL IT TO [email protected] . | | | | | | |
|
|
| Review Stop |
NFIP |
NFIP REVIEW ACTIVITY |
| Rev No |
2 |
Status |
P |
Date |
2019-10-18 |
|
|
Cont ID |
|
| Sent By |
jgomez |
Date |
2019-10-18 |
Time |
11:33 |
Rev Time |
0.00 |
| Received By |
jgomez |
Date |
2019-10-18 |
Time |
11:33 |
Sent To |
|
|
| Notes |
| 2019-10-18 11:44:26 | PROVISO: | | | | | | | | | | | | | | | 1) THIS PROPOSED BUILDING IS GOING TO BE BUILT IN A AE | | | FLOOD ZONE WITH THE BASE FLOOD BFE: 12.7 FEET NAV88. | | | DURING THE PERMITTING OF THIS STRUCTURE THERE WILL BE | | | REQUIRED (3) DIFFERENT FLOOD ZONE CERTIFICATES: | | | | | | (1)CONSTRUCTION DRAWINGS ELEVATION CERTIFICATE WAS | | | PROVIDED AND IS OK. | | | | | | THE OTHER TWO ELEVATIONS CERTIFICATES NEED TO BE | | | PROVIDED DURING CONSTRUCTION AND THEY ARE: | | | | | | (2) ONCE THE FIRST FLOOR SLAB IS POURED THE 2ND | | | ELEVATION CERTIFICATE IS REQUIRED. W. P. B. | | | ADMINISTRATIVE CODE 110.3 REQUIRED INSPECTIONS 1.2 | | | FLOOR/ SLAB INSPECTION. IN FLOOD HAZARD AREAS, UPON | | | PLACEMENT OF THE LOWEST FLOOR, INCLUDING BASEMENT, AND | | | PRIOR TO FURTHER VERTICAL CONSTRUCTION, THE ELEVATION | | | CERTIFICATION, REQUIRED IN SECTION 1612.5, SHALL BE | | | SUBMITTED TO THE BUILDING OFFICIAL. | | | | | | (3) BEFORE THE ISSUANCE OF A CERTIFICATE OF OCCUPANCY | | | OR A CERTIFICATE OF COMPLETION THE 3RD FLOOD ZONE | | | CERTIFICATE IS REQUIRED WITH THE HEIGHT OF ALL EXTERIOR | | | ATTENDANTS A/C PADS OR OTHER SLABS FOR GENERATORS. | | | W. P. B. ADMINISTRATIVE CODE 110.3 REQUIRED INSPECTIONS | | | (6) FINAL INSPECTION. TO BE MADE AFTER THE BUILDING IS | | | COMPLETED AND READY FOR OCCUPANCY. 6.1. LOWEST FLOOR | | | ELEVATION. IN FLOOD HAZARD AREAS, AS PART OF THE FINAL | | | INSPECTION, A FINAL CERTIFICATION OF THE LOWEST FLOOR | | | ELEVATION SHALL BE SUBMITTED TO THE AUTHORITY HAVING | | | JURISDICTION. |
|
|
| Review Stop |
NFIP |
NFIP REVIEW ACTIVITY |
| Rev No |
1 |
Status |
F |
Date |
2019-10-02 |
|
|
Cont ID |
|
| Sent By |
jgomez |
Date |
2019-10-02 |
Time |
13:22 |
Rev Time |
0.00 |
| Received By |
jgomez |
Date |
2019-10-02 |
Time |
13:22 |
Sent To |
|
|
| Notes |
| 2019-10-02 13:22:54 | | | | 1) THIS PROPOSED BUILDING IS GOING TO BE BUILT IN A AE | | | FLOOD ZONE WITH THE BASE FLOOD BFE: 12.7 FEET NAV88. | | | DURING THE PERMITTING OF THIS STRUCTURE THERE WILL BE | | | REQUIRED (3) DIFFERENT FLOOD ZONE CERTIFICATES | | | REQUIRED: | | | (1) A FLOOD ZONE CERTIFICATE IS REQUIRED AS PART OF THE | | | PLAN REVIEW DOCUMENTS WITH THE PROPOSED FINISH FLOOR | | | HEIGHT. W. P. B. ADMINISTRATIVE CODE 107.3.5.1.1 | | | BUILDING MINIMUM PLAN REVIEW CRITERIA FOR COMMERCIAL | | | BUILDINGS. (8) FLOOD REQUIREMENTS ELEVATIONS, | | | ENCLOSURES, FLOOD DAMAGE-RESISTANT MATERIALS. | | | | | | (2) ONCE THE FIRST FLOOR SLAB IS POURED THE 2ND | | | ELEVATION CERTIFICATE IS REQUIRED. W. P. B. | | | ADMINISTRATIVE CODE 110.3 REQUIRED INSPECTIONS 1.2 | | | FLOOR/ SLAB INSPECTION. IN FLOOD HAZARD AREAS, UPON | | | PLACEMENT OF THE LOWEST FLOOR, INCLUDING BASEMENT, AND | | | PRIOR TO FURTHER VERTICAL CONSTRUCTION, THE ELEVATION | | | CERTIFICATION, REQUIRED IN SECTION 1612.5, SHALL BE | | | SUBMITTED TO THE BUILDING OFFICIAL. | | | | | | (3) BEFORE THE ISSUANCE OF A CERTIFICATE OF OCCUPANCY | | | OR A CERTIFICATE OF COMPLETION THE 3RD FLOOD ZONE | | | CERTIFICATE IS REQUIRED WITH THE HEIGHT OF ALL EXTERIOR | | | ATTENDANTS A/C PADS OR OTHER SLABS FOR GENERATORS. | | | W. P. B. ADMINISTRATIVE CODE 110.3 REQUIRED INSPECTIONS | | | (6) FINAL INSPECTION. TO BE MADE AFTER THE BUILDING IS | | | COMPLETED AND READY FOR OCCUPANCY. 6.1. LOWEST FLOOR | | | ELEVATION. IN FLOOD HAZARD AREAS, AS PART OF THE FINAL | | | INSPECTION, A FINAL CERTIFICATION OF THE LOWEST FLOOR | | | ELEVATION SHALL BE SUBMITTED TO THE AUTHORITY HAVING | | | JURISDICTION. |
|
|
| Review Stop |
P |
PLUMBING |
| Rev No |
2 |
Status |
P |
Date |
2019-10-18 |
|
|
Cont ID |
|
| Sent By |
shill |
Date |
2019-10-18 |
Time |
05:58 |
Rev Time |
0.00 |
| Received By |
shill |
Date |
2019-10-16 |
Time |
07:51 |
Sent To |
|
|
| Notes |
| 2019-10-18 05:58:31 | REVIEWED REMOTELY BY TIM HUNT | | | |
|
|
| Review Stop |
P |
PLUMBING |
| Rev No |
1 |
Status |
F |
Date |
2019-10-02 |
|
|
Cont ID |
|
| Sent By |
shill |
Date |
2019-10-02 |
Time |
08:47 |
Rev Time |
0.00 |
| Received By |
shill |
Date |
2019-10-01 |
Time |
17:25 |
Sent To |
|
|
| Notes |
| 2019-10-02 08:49:04 | PLUMBING 1ST REVIEW**DENIED** | | | | | | 1) SHT. P5.6 STACK # 17 AND SHT. 5.7 STACK 32 AS THE | | | SHOWERS AND KITCHEN SHARING THE SAME VENT STACK. ONLY | | | OTHER BATHROOM FIXTURES ARE PERMITTED TO SHARE THE SAME | | | VERTICAL WET VENT. FBC-P 912.1.2 | | | 2) BACKFLOW FOR THE POOL MARK UP SHALL BE A LEAD FREE | | | RPZ AND NOT PVB AS CALLED OUT ON SHT. P6.2. BACKFLOWS | | | REQUIRED SEPARATE PERMITS BUT ALL BACKFLOWS CAN BE | | | PULLED UNDER 1 PERMIT. BACKFLOWS SHALL ONLY BE | | | INSTALLED BY LICENSE PLUMBING CONTRACTORS. 2017 CITY OF | | | WPB CROSS CONNECTION MANUAL. | | | 3) TANKLESS HWH CALLED OUT ON SHT. 6.2 DETAIL #2 MIXING | | | VALVE MUST BE AN APPROVED ASSE 1070 DEVICE. FBC-P | | | 607.1.2 | | | 4) ALL WATER HEATER DETAILS ON SHT. 6.2 CALL OUT ?? | | | WALL INSULATIONS ON THE HOT AND HOT WATER RETURN | | | PIPING. THE MIN THICKNESS ALLOWED IS 1? WALL THICKNESS. | | | FBC-P 607.5, FBC-ENERGY C404.4 | | | 5) BEING THAT A CHECK VALVE MUST BE INSTALLED ON THE | | | COLD WATER SUPPLY OF EACH HWH FOR THE HOT WATER RETURN | | | LINE THIS CREATES A CLOSED SYSTEM REQUIRED A THERMO | | | EXPANSION DEVICE. PROVIDE A MEANS OF THERMO EXPANSION | | | AS REQUIRED IN FBC-P 607.3. THIS COMMENT WAS ALSO ON | | | THE 1ST REVIEW OF THE SLAB PLAN REVIEW PERMIT # | | | 19030235 | | | TIM HUNT | | | PLUMBING PLANS EXAMINER | | | CITY OF WEST PALM BEACH (CGA SOLUTIONS) | | | 561-248-2703 | | | [email protected] | | | |
|
|
| Review Stop |
SIGNATURE |
ELECTRONIC SIGNATURE SHEET |
| Rev No |
2 |
Status |
P |
Date |
2019-10-16 |
|
|
Cont ID |
|
| Sent By |
shill |
Date |
2019-10-16 |
Time |
16:52 |
Rev Time |
0.00 |
| Received By |
shill |
Date |
2019-10-16 |
Time |
16:52 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
SIGNATURE |
ELECTRONIC SIGNATURE SHEET |
| Rev No |
1 |
Status |
P |
Date |
2019-10-04 |
|
|
Cont ID |
|
| Sent By |
shill |
Date |
2019-10-04 |
Time |
08:35 |
Rev Time |
0.00 |
| Received By |
shill |
Date |
2019-10-04 |
Time |
08:35 |
Sent To |
|
|
| Notes |
| 2019-10-04 08:11:59 | ELECTRICAL SIGNATURE OK JLEAHY |
|
|
| Review Stop |
THRESHOLD |
THRESHOLD INSPECTOR DOCUMENTS |
| Rev No |
1 |
Status |
P |
Date |
2019-10-02 |
|
|
Cont ID |
|
| Sent By |
jgomez |
Date |
2019-10-02 |
Time |
13:24 |
Rev Time |
0.00 |
| Received By |
jgomez |
Date |
2019-10-02 |
Time |
13:23 |
Sent To |
|
|
| Notes |
| 2019-10-02 13:26:15 | | | | THRESHOLD COMPANY: | | | ONM&J | | | | | | THRESHOLD INSPECTOR: | | | JOSEPH F. MINCUZZI PE 38162/THRESHOLD REGISTRATION 952 | | | | | | THRESHOLD INSPECTOR REPRESENTATIVES: | | | CHARLES MOCK BN 3682 | | | ERIC HERNANDEZ BN 3465 | | | VICTOR DAVIS BN 4790 | | | | | | |
|
|
| Review Stop |
Z |
ZONING |
| Rev No |
2 |
Status |
P |
Date |
2019-10-16 |
|
|
Cont ID |
|
| Sent By |
jroach |
Date |
2019-10-16 |
Time |
|
Rev Time |
0.00 |
| Received By |
jroach |
Date |
2019-10-16 |
Time |
|
Sent To |
|
|
| Notes |
| 2019-10-22 16:51:07 | ZONING PLAN REVIEW | | | ________________________________________ | | | | | | DATE OF REVIEW: 10.16.2019 | | | PERMIT NO.: 19090347 | | | ________________________________________ | | | | | | REVIEW STATUS: PASSED WITH PROVISOS | | | ________________________________________ | | | | | | THIS REVIEW HAS BEEN PASSED SUBJECT TO THE FOLLOWING | | | PROVISOS: | | | | | | 1. THE SCOPE OF THIS REVIEW IS LIMITED TO THE BUILDING | | | STRUCTURE ONLY! | | | | | | 2. SEPARATE PERMITS REQUIRED FOR THE BUILDING | | | STRUCTURE, SURROUNDING SITE WORK, HARDSCAPE, FENCING, | | | PARKING, LANDSCAPING, SIGNAGE, ETC. | | | | | | 3. THE PROJECT IS SUBJECT TO ALL DEVELOPMENT ORDER | | | CONDITIONS, AS OUTLINED IN RESOLUTION NO. 22-19, AS | | | APPROVED BY THE CITY COMMISSION ON FEBRUARY 25, 2019, | | | AND AS MAY BE AMENDED. | | | ________________________________________ | | | | | | PLEASE NOTE THAT SUBMITTAL OF ADDITIONAL AND/OR REVISED | | | MATERIALS MAY RESULT IN NEW PLAN REVIEW COMMENTS. | | | ________________________________________ | | | | | | QUESTIONS/COMMENTS, PLEASE CONTACT THE FOLLOWING: | | | | | | JOHN P. ROACH, AICP, PRINCIPAL PLANNER | | | CITY OF WEST PALM BEACH | | | DEVELOPMENT SERVICES DEPARTMENT ? PLANNING DIVISION | | | 401 CLEMATIS STREET - P.O. BOX 3147 | | | WEST PALM BEACH, FLORIDA 33402 | | | | | | P: 561.822.1448 | | | TTY: 800.955.8771 | | | E: [email protected] | | | | | | W: WPB.ORG | | | |
|
|
| Review Stop |
Z |
ZONING |
| Rev No |
1 |
Status |
P |
Date |
2019-10-11 |
|
|
Cont ID |
|
| Sent By |
roach |
Date |
2019-10-11 |
Time |
15:33 |
Rev Time |
0.00 |
| Received By |
jroach |
Date |
2019-10-11 |
Time |
15:31 |
Sent To |
|
|
| Notes |
| 2019-10-11 15:34:12 | ZONING PLAN REVIEW | | | ________________________________________ | | | | | | DATE OF REVIEW: 10.11.2019 | | | PERMIT NO.: 19090347 | | | ________________________________________ | | | | | | REVIEW STATUS: PASSED WITH PROVISOS | | | ________________________________________ | | | | | | THIS REVIEW HAS BEEN PASSED SUBJECT TO THE FOLLOWING | | | PROVISOS: | | | | | | 1. THE SCOPE OF THIS REVIEW IS LIMITED TO THE BUILDING | | | STRUCTURE ONLY! | | | | | | 2. SEPARATE PERMITS REQUIRED FOR THE BUILDING | | | STRUCTURE, SURROUNDING SITE WORK, HARDSCAPE, FENCING, | | | PARKING, LANDSCAPING, SIGNAGE, ETC. | | | | | | 3. THE PROJECT IS SUBJECT TO ALL DEVELOPMENT ORDER | | | CONDITIONS, AS OUTLINED IN RESOLUTION NO. 22-19, AS | | | APPROVED BY THE CITY COMMISSION ON FEBRUARY 25, 2019, | | | AND AS MAY BE AMENDED. | | | ________________________________________ | | | | | | PLEASE NOTE THAT SUBMITTAL OF ADDITIONAL AND/OR REVISED | | | MATERIALS MAY RESULT IN NEW PLAN REVIEW COMMENTS. | | | ________________________________________ | | | | | | QUESTIONS/COMMENTS, PLEASE CONTACT THE FOLLOWING: | | | | | | JOHN P. ROACH, AICP, PRINCIPAL PLANNER | | | CITY OF WEST PALM BEACH | | | DEVELOPMENT SERVICES DEPARTMENT ? PLANNING DIVISION | | | 401 CLEMATIS STREET - P.O. BOX 3147 | | | WEST PALM BEACH, FLORIDA 33402 | | | | | | P: 561.822.1448 | | | TTY: 800.955.8771 | | | E: [email protected] | | | | | | W: WPB.ORG | | | |
|
|