| 2019-09-17 17:25:30 | 09/17/2019 1ST GAS REVIEW **DENIED** WITH COMMENTS |
| | |
| | NOTE: A FULL AND COMPREHENSIVE PLAN REVIEW COULD NOT BE |
| | ACCOMPLISHED AT THIS TIME DUE TO THE QUALITY OF THE |
| | SUBMITTED PLANS. ADDITIONAL COMMENTS MAY BE GENERATED |
| | ON THE RESUBMITTAL REVIEW. |
| | |
| | 1. THE ADDRESS OF THE PROJECT OR RESIDENCE MUST BE ON |
| | PLAN IN FULL, NUMBER, ST. CITY AND ZIP CODE PER THE WPB |
| | AMENDMENTS TO THE FBC SEC.107.2.1 INFORMATION ON |
| | CONSTRUCTION DOCUMENTS. |
| | 2. GAS RISER DIAGRAM REQUIRED AND CLEARLY SHOWS THE |
| | LENGTH OF ALL CUT SECTIONS OF PIPE PER THE 2017 FBC |
| | RES. SECS. G2413.4.1, G2413.4.2. |
| | 3. INDICATE THE DELIVERY PRESSURE (PSI) OF THE SYSTEM |
| | ON THE ISOMETRIC PER THE 2017 FBC RES. SEC. G2413.2. |
| | 4. SHOW THE TYPE OF PIPE MATERIAL BEING INSTALLED, ALL |
| | PIPE SIZES, AND THE CORRESPONDING EHD NUMBER OF THE |
| | CORRUGATED STAINLESS-STEEL TUBING (IF APPLICABLE) FOR |
| | EACH PIPE SIZE PER THE WPB AMENDMENTS TO THE FBC |
| | SEC.107.2.1 INFORMATION ON CONSTRUCTION DOCUMENTS. |
| | 5. SHOW THE LOCATION OF ALL MP (STEP-DOWN) REGULATORS. |
| | A LISTED SHUTOFF VALVE SHALL BE INSTALLED IMMEDIATELY |
| | AHEAD OF EACH MP REGULATOR PER THE 2017 FBC RES. SEC. |
| | G2420.4. |
| | 6. SUBMIT TWO COPIES OF A HOUSE PLAN SHOWING THE |
| | LOCATION OF THE TANKLESS WATER HEATER AND THE LOCATION |
| | AND DISTANCE OF ANY OPERABLE DOORS OR WINDOWS IN |
| | RELATION TO THE WATER HEATER. THE LOCATION OF THE WATER |
| | HEATER SHALL COMPLY WITH THE MANUFACTURER'S |
| | INSTALLATION INSTRUCTIONS. YOU CAN USE THE HOUSE PLAN |
| | AND IT CAN BE HAND DRAWN PER THE WPB AMENDMENTS TO THE |
| | FBC SEC. 107.2.1. INFORMATION ON CONSTRUCTION |
| | DOCUMENTS. |
| | 7. PLEASE SUBMIT MANUFACTURES SPECIFICATION FOR |
| | APPLIANCES, I.E. DRYER, STOVE AND TANKLESS. WHAT WAS |
| | SUBMITTED ON THESE APPLIANCES ARE PRODUCT INFORMATION |
| | NOT SPECIFICATION OR AND INSTALLATIONS INSTRUCTION, |
| | PLEASE REFER TO THIS WEBSITE FOR A SAMPLE OF THE |
| | TANK-LESS (SEE LAST PAGE) PER THE 2017 FBC RES. SEC. |
| | G2408.1. HTTPS://WWW.AIRSOLUTIONS.CA/IMAGES/PRODUCTS/NA |
| | VIEN/PRODUCTS/NPE-SERIES/NAVIEN-NPE-BROCHURE.PDF |
| | 8. THIS TANKLESS UNIT CALL FOR 10.5" WATER COLUMN AND |
| | IF THE SERVICE METER DISCHARGES IS A 12" WATER COLUMN |
| | REQUIRING A REGULATOR FOR THIS UNIT AS PER |
| | MANUFACTURER'S SPECIFICATION. SUBMIT MANUFACTURER'S |
| | SPECIFICATIONS FOR THE PRESSURE REGULATORS. REGULATORS |
| | INSTALLED ON THE EXTERIOR OF THE BUILDING SHALL BE |
| | APPROVED FOR OUTDOOR INSTALLATION PER THE 2017 FBC RES. |
| | SEC. G2421.1. |
| | 9. SUBMIT COMBUSTION AIR CALCULATIONS FOR THE ADDED GAS |
| | APPLIANCES. WHERE IS COMBUSTION AIR PROVIDED BY THE |
| | BUILDING'S MECHANICAL VENTILATION SYSTEM, THE SYSTEM |
| | SHALL PROVIDE THE SPECIFIED COMBUSTION AIR RATE IN |
| | ADDITION TO THE REQUIRED VENTILATION AIR PER THE 2017 |
| | FBC RES. SEC. G2407.9.3. COMBINED COMBUSTION AIR AND |
| | VENTILATION AIR SYSTEM. |
| | 10. IF USING LOUVERS SHOW THE LOCATION OF THE LOUVERS |
| | THAT ARE BEING INSTALLED FOR THE COMBUSTION AIR. THE |
| | LOUVERS CANNOT BE LOCATED ON AN EXTERIOR WALL THAT IS |
| | FIRE RATED AS THE FIRE RATING OF THE WALL MUST BE |
| | MAINTAINED. |
| | 11. PLEASE SHOW ALL UNIONS IN FRONT OF REGULATOR 1' OF |
| | EITHER SIDE PER THE 2017 FBC RES. SEC G2421.2. |
| | 12. LABEL SHUTOFF VALVE ON GAS ISOMERIC PER THE 2017 |
| | FBC RES. SEC. G2401.1.3. |
| | 13. SHOW DRIP LEG ON EQUIPMENT INSTALLED PER THE 2017 |
| | FBC RES. SEC. G2419.2 OR 2017 FBC FG 408.2 |
| | 14. GAS APPLIANCES SHALL BE LISTED AND LABELED. THE |
| | INSTALLATION MANUALS FOR ALL GAS APPLIANCES/EQUIPMENT |
| | SHALL BE ONSITE AT THE TIME OF INSPECTION PER THE 2017 |
| | FBC RES. SEC. G2413.2 AND G2404.3. |
| | 15. NEED A SHUTOFF VALVE AND HARD CAP FOR FUTURE |
| | GENERATOR AND POOL HEATER SHOW ON GAS ISOMERIC PER THE |
| | 2017 FBC RES. SEC. G2401.1.3. |
| | 16. SUBMIT SPEC THAT SHOW THE POOL HEATER SHALL HAVE A |
| | MINIMUM THERMAL EFFICIENCY OF 82% PLEASE PER THE 2017 |
| | FBC-ENERGY SEC. R403.10.4. |
| | |
| | |
| | WHEN RESUBMITTING PLANS PLEASE INDICATE THE REVISION & |
| | REMOVE ANY VOIDED SHEETS & REPLACE ANY PAGES AS |
| | NECESSARY. A TRANSMITTAL LETTER LISTING THE ORIGINAL |
| | REVIEW COMMENT NUMBER, WITH A DESCRIPTION OF THE |
| | REVISION, MADE, IDENTIFYING THE SHEET OR SPECIFICATION |
| | PAGE WHERE THE CHANGES CAN BE FOUND WILL HELP TO |
| | EXPEDITE YOUR PERMIT. THANK YOU FOR YOUR ANTICIPATED |
| | COOPERATION. |
| | |
| | LUIS A. CRESPO |
| | PLUMBING INSPECTOR / |
| | PLUMBING PLAN REVIEW |
| | AVAILABLE FROM 1:00 PM TO 4:00 PM |
| | [email protected] |
| | |