| 2019-09-16 18:17:02 | 09/16/2019 1ST GAS/LP/TANK REVIEW **DENIED** WITH |
| | COMMENTS |
| | |
| | NOTE - A COMPREHENSIVE REVIEW COULD NOT BE DONE AT THIS |
| | TIME AND ADDITIONAL PLAN REVIEW COMMENTS MAY BE |
| | GENERATED UPON THE RE-REVIEW OF SUBMITTED CORRECTIONS. |
| | |
| | 1. A SUB PLUMBING PERMIT (GAS) LP BY A LICENSED |
| | CONTRACTOR IS REQUIRED FOR THE SCOPE OF WORK PER THE |
| | WPB AMENDMENTS TO THE FBC SEC. 105.1 |
| | 2. GAS RISER DIAGRAM REQUIRED PER THE WPB AMENDMENTS TO |
| | THE FBC SEC. 107.5.1.5 (9) COMMERCIAL GAS |
| | 3. SUBMIT AN ISOMETRIC DRAWING THAT CLEARLY SHOWS THE |
| | LENGTH OF ALL CUT SECTIONS OF PIPE AND TYPE OF PIPE PER |
| | 2017 FBC FG SECS. 402.4.1, 402.4.2. |
| | 4. INDICATE THE DELIVERY PRESSURE (PSI) OF THE SYSTEM |
| | ON THE PLAN PER 2017 FBC FG SEC. 402.2. |
| | 5. PLEASE SHOW SHUTOFF VALVES, UNIONS, DRIP LEGS, BTU |
| | AND REGULATORS ON ISOMETRIC PER THE 2017 FBC FG SEC. |
| | 409.4. |
| | 6. PLEASE SHOW ALL UNIONS IN FRONT OF REGULATOR 1? OF |
| | EITHER SIDE PER THE 2017 FBC FG SEC 410.2. |
| | 7. SHOW THE DISTANCE FROM THE POINT OF DELIVERY, (GAS |
| | METER / MP REGULATOR / LP TANK) TO THE MOST REMOTE |
| | OUTLET IN THE BUILDING AND/OR SYSTEM PER THE 2017 FBC |
| | FG SEC. 402.4.1. |
| | 8. PLAN ARE TOO SMALL TO READ NOTES, PLANS SHALL BE |
| | DRAWN TO A MINIMUM 1/8 INCH SCALE ON E.01 PER THE WPB |
| | AMENDMENT TO FBC SEC. 107.2.1.3 QUALITY OF BUILDING |
| | PLANS. |
| | 9. SUBMIT TWO COPIES OF THE SIZING TABLE USED IN THE |
| | DESIGN FOR THE GAS SYSTEM OR PLACE A NOTE ON BOTH SETS |
| | OF PLANS LISTING THE SIZING TABLES FROM GAS CODES OR |
| | ANOTHER STANDARD THAT WERE USED IN THE DESIGN OF THIS |
| | SYSTEM PER THE 2017 FBC FG SEC. 402. |
| | 10. IF A REGULATOR IS REQUIRED SUBMIT MANUFACTURER?S |
| | SPECIFICATIONS FOR THE PRESSURE REGULATORS. REGULATORS |
| | INSTALLED ON THE EXTERIOR OF THE BUILDING SHALL BE |
| | APPROVED FOR OUTDOOR INSTALLATION PER THE 2017 FBC FG |
| | SEC. 410.1. |
| | 11. CLEARLY, INDICATE ON THE PLAN IF THE LP TANK IS |
| | ABOVE GROUND OR BELOW GROUND, AND SHOW THE METHOD OF |
| | REQUIRED PROTECTION FOR THE LP TANK AND APPURTENANCES |
| | PER NFPA 58. IF THE TANK IS BELOW GROUND IT SHALL BE |
| | ANCHORED PER NFPA 58 SEC.3-2.2.7 (H). IF ABOVE GROUND, |
| | THE TANK SHALL BE SECURELY ANCHORED TO WITHSTAND 170 |
| | MPH ULT WIND LOAD PER THE FLORIDA BUILDING CODE. WPB |
| | AMENDMENTS TO THE FBC SEC. 107.2.1 INFORMATION ON |
| | CONSTRUCTION DOCUMENTS. |
| | 12. SHOW THE DEPTH OF THE LP GAS CONTAINER IF BELOW |
| | GRADE. COMPLY WITH NFPA 58 SEC. 6.6.6.1. |
| | 13. FOR A CATHODIC PROTECTION SYSTEM SHALL BE REQUIRED |
| | PER NFPA 58 SECS. 5.2.1.11, 6.6.6.1 (I) AND SHALL BE |
| | MONITORED PER NFPA 58 SEC.6.6.6.1 (J). SUBMIT DETAILS |
| | ON THE TYPE OF CATHODIC PROTECTION, SIZE (LBS.) & A |
| | NUMBER OF MAGNESIUM BAG(S), SIZE & TYPE OF ANODE CABLE |
| | AND AMOUNT OF WATER TO ACTIVATE IT. |
| | 14. IF AN UNDERGROUND UNIT CLEARLY INDICATE ON TIE-DOWN |
| | SHEET IF THE LP TANK TIE-DOWN METHOD AND IF YOU ARE |
| | USING STRAPS OR CABLE, IF CABLE HOW IS IT PROTECTED FOR |
| | THE LP TANK AND APPURTENANCES PER NFPA 58. WPB |
| | AMENDMENTS TO THE FBC SEC. 107.2.1 INFORMATION ON |
| | CONSTRUCTION DOCUMENTS. |
| | 15. PROVIDE THE SIZE OF THE HOLD-DOWN CABLES/STRAPS FOR |
| | THE TANK AND THE TYPE AND LENGTH OF GROUND ANCHORS TO |
| | BE INSTALLED TO PREVENT FLOTATION. NFPA 58 SEC. |
| | 6.6.1.6. |
| | 16. THE TANK SHALL BE A MIN OF 10' FROM ANY SOURCE OF |
| | IGNITION ACCORDING TO NFPA TABLE 6.3.4.3 SEPARATION |
| | DISTANCE BETWEEN CONTAINER PRESSURE RELIEF VALVE AND |
| | BUILDING OPENINGS. |
| | 17. SHOW THE DISTANCE OF THE LP TANK FROM THE EXTERIOR |
| | WALL OF THE STRUCTURE TO THE CONTAINER SURFACE AND ALSO |
| | FROM THE PROPERTY LINE TO THE CONTAINER SURFACE. COMPLY |
| | WITH NFPA 58-11 SEC. 6.3.1 & TABLE 6.3.1. |
| | 18. SHOW THE CAPACITY AND LOCATION OF THE LP TANK ON |
| | THE PLANS AND SHOW THE TYPE OF TANK (HORIZONTAL ASME OR |
| | VERTICAL ASME). WPB AMENDMENTS TO THE FBC SEC. 107.2.1 |
| | INFORMATION ON CONSTRUCTION DOCUMENTS. |
| | |
| | |
| | WHEN RESUBMITTING PLANS PLEASE INDICATE THE REVISION & |
| | REMOVE ANY VOIDED SHEETS & REPLACE ANY PAGES AS |
| | NECESSARY. A TRANSMITTAL LETTER LISTING THE ORIGINAL |
| | REVIEW COMMENT NUMBER, WITH A DESCRIPTION OF THE |
| | REVISION, MADE, IDENTIFYING THE SHEET OR SPECIFICATION |
| | PAGE WHERE THE CHANGES CAN BE FOUND WILL HELP TO |
| | EXPEDITE YOUR PERMIT. THANK YOU FOR YOUR ANTICIPATED |
| | COOPERATION. |
| | |
| | |
| | LUIS A. CRESPO |
| | PLUMBING INSPECTOR / |
| | PLUMBING PLAN REVIEW |
| | AVAILABLE FROM 1:00 PM TO 4:00 PM |
| | [email protected] |
| | 561-805-6720 |
| | |