Plan Review Details - Permit 19060646
Plan Review Stops For Permit 19060646
Review Stop I INCOMING/PROCESSING
Rev No 4 Status N Date 2019-08-26 Cont ID  
Sent By jgomez Date 2019-08-26 Time 16:36 Rev Time 0.00
Received By jgomez Date 2019-08-26 Time 16:28 Sent To I
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 3 Status N Date 2019-08-23 Cont ID  
Sent By jgomez Date 2019-08-23 Time 17:13 Rev Time 0.00
Received By jgomez Date 2019-08-23 Time 17:03 Sent To  
Notes
2019-08-23 17:04:24RECEIVED E-MAIL FROM A/C CONTRACTOR.
  
 ATTACHED YOU WILL FIND UPDATED LOAD CALCULATIONS AND
 SIGNED EER. PLEASE LET US KNOW IF YOU HAVE ANY
 QUESTIONS OR CONCERNS.
  
 ANA KING
 PERMIT COORDINATOR
 KYZAR AIR CONDITIONING, INC.
 239 TALL PINES RD, WPB FL 33413
 561-640-100 EXT 102
 LICENSED & INSURED - CAC1814778
  

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2019-07-25 Cont ID  
Sent By jgomez Date 2019-07-25 Time 18:13 Rev Time 0.00
Received By jgomez Date 2019-07-24 Time 14:22 Sent To I
Notes
2019-07-25 14:22:58RESUB ROUTED TO JGOMEZ

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2019-06-17 Cont ID  
Sent By jgomez Date 2019-06-17 Time 08:46 Rev Time 0.00
Received By jgomez Date 2019-06-13 Time 15:56 Sent To I
Notes
2019-06-14 15:56:39REVISION ROUTED TO JGOMEZ

Review Stop M MECHANICAL (A/C)
Rev No 4 Status P Date 2019-08-26 Cont ID  
Sent By jgomez Date 2019-08-26 Time 16:36 Rev Time 0.00
Received By jgomez Date 2019-08-26 Time 16:28 Sent To  
Notes
***NONE***

Review Stop M MECHANICAL (A/C)
Rev No 3 Status F Date 2019-08-23 Cont ID  
Sent By jgomez Date 2019-08-23 Time 17:13 Rev Time 0.00
Received By jgomez Date 2019-08-23 Time 17:04 Sent To  
Notes
2019-08-23 17:13:36RESIDENTIAL (R3) MECHANICAL REVISION THIRD CHECKLIST.
 CODE: FBC 6TH EDITION (2017) AND CITY AMENDMENTS.
  
 NOTE:
 THIS MECHANICAL REVIEW WILL BE PASSED ONCE THE ENERGY
 CALCULATIONS ARE PROPERLY SIGNED BY THE OWNER AT THE
 BOTTOM OF PAGE 1 OF 5 AS REQUIRED BELOW.
  
 1- THE ENERGY FORM R405-2017 IS REQUIRED TO BE SIGNED
 AND DATED BY THE OWNER, ARCHITECT OR OWNER'S LEGALLY
 DESIGNATED AGENT AS REQUIRED BY SEC. R103.1.1.2
 FBC-ENERGY CONSERVATION, 6TH EDITION (2017) PRIOR TO
 RECEIVING THE PERMIT TO BEGIN CONSTRUCTION.
  
 IF YOU HAVE ANY QUESTIONS, PLEASE CONTACT
 JULIO GOMEZ
 COMMERCIAL COMBINATION PLANS EXAMINER
 DEVELOPMENT SERVICES DEPARTMENT
 BUILDING DIVISION
 (561)805-6712
 [email protected]
  
  
2019-08-23 17:05:01RECEIVED E-MAIL FROM A/C CONTRACTOR.
  
 ATTACHED YOU WILL FIND UPDATED LOAD CALCULATIONS AND
 SIGNED EER. PLEASE LET US KNOW IF YOU HAVE ANY
 QUESTIONS OR CONCERNS.
  
 ANA KING
 PERMIT COORDINATOR
 KYZAR AIR CONDITIONING, INC.
 239 TALL PINES RD, WPB FL 33413
 561-640-100 EXT 102
 LICENSED & INSURED - CAC1814778
  

Review Stop M MECHANICAL (A/C)
Rev No 2 Status F Date 2019-07-25 Cont ID  
Sent By jgomez Date 2019-07-25 Time 18:09 Rev Time 0.00
Received By jgomez Date 2019-07-25 Time 17:39 Sent To  
Notes
2019-07-25 17:39:29RESIDENTIAL (R3) MECHANICAL REVISION SECOND CHECKLIST.
 CODE: FBC 6TH EDITION (2017) AND CITY AMENDMENTS.
  
 1- OK.
  
 2- MECHANICAL REVIEW WAS APPROVED ON 04/02/18 WITH THE
 PROVISO REQUESTING ENERGY CALCULATIONS TO BE REVISED TO
 MATCH EQUIPMENT. REVISED ENERGY CALCULATIONS WERE NOT
 SUBMITTED. NEED TO SUBMIT REVISED ENERGY CALCULATIONS.
 SEE COPY OF PROVISO BELOW.
  
 RESPONSE:
 REPEAT COMMENT. ENERGY CALCULATIONS WERE NOT REVISED.
  
  
  
  
 MECHANICAL REVIEW APPROVED WITH PROVISO:
 1- REVISE THE SEER EFFICIENCY SHOWN ON THE ENERGY
 CALCULATIONS TO MATCH SEER SHOWN ON A/C PLANS AND
 EQUIPMENT AHRI CERTIFICATE.
  
 PLEASE NOTE THAT SUBMITTAL OF ADDITIONAL AND/OR REVISED
 MATERIALS MAY RESULT IN NEW PLAN REVIEW COMMENTS.
  
 IF YOU HAVE ANY QUESTIONS, PLEASE CONTACT
 JULIO GOMEZ
 COMMERCIAL COMBINATION PLANS EXAMINER
 DEVELOPMENT SERVICES DEPARTMENT
 BUILDING DIVISION
 (561)805-6712
 [email protected]
  
  

Review Stop M MECHANICAL (A/C)
Rev No 1 Status F Date 2019-06-17 Cont ID  
Sent By jgomez Date 2019-06-17 Time 08:36 Rev Time 0.00
Received By jgomez Date 2019-06-17 Time 08:20 Sent To  
Notes
2019-06-17 08:21:17RESIDENTIAL (R3) MECHANICAL REVISION REVIEW COMMENTS
 CODE: FBC 6TH EDITION (2017) AND CITY AMENDMENTS.
  
 1- MECHANICAL PLANS NEED TO BE SIGNED AND SEALED BY THE
 ARCHITECT OF RECORD. CHAPTER 481 F.S.
  
 2- MECHANICAL REVIEW WAS APPROVED ON 04/02/18 WITH THE
 PROVISO REQUESTING ENERGY CALCULATIONS TO BE REVISED TO
 MATCH EQUIPMENT. REVISED ENERGY CALCULATIONS WERE NOT
 SUBMITED. NEED TO SUBMIT REVISED ENERGY CALCULATIONS.
 SEE COPY OF PROVISO BELOW.
  
 MECHANICAL REVIEW APPROVED WITH PROVISO:
 1- REVISE THE SEER EFFICIENCY SHOWN ON THE ENERGY
 CALCULATIONS TO MATCH SEER SHOWN ON A/C PLANS AND
 EQUIPMENT AHRI CERTIFICATE.
  
 PLEASE NOTE THAT SUBMITTAL OF ADDITIONAL AND/OR REVISED
 MATERIALS MAY RESULT IN NEW PLAN REVIEW COMMENTS.
  
 IF YOU HAVE ANY QUESTIONS, PLEASE CONTACT
 JULIO GOMEZ
 COMMERCIAL COMBINATION PLANS EXAMINER
 DEVELOPMENT SERVICES DEPARTMENT
 BUILDING DIVISION
 (561)805-6712
 [email protected]
  
  


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved