Plan Review Details - Permit 19051381
Plan Review Stops For Permit 19051381
Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2019-06-21 Cont ID  
Sent By tklarge Date 2019-06-21 Time 06:35 Rev Time 0.00
Received By tklarge Date 2019-06-20 Time 16:41 Sent To  
Notes
2019-06-20 16:41:47RESUB ROUTED TO TKLARGE

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2019-06-06 Cont ID  
Sent By tklarge Date 2019-06-06 Time 07:07 Rev Time 0.00
Received By tklarge Date 2019-05-29 Time 14:57 Sent To  
Notes
2019-05-30 14:57:38PLUMB <5K

Review Stop P PLUMBING
Rev No 2 Status P Date 2019-06-21 Cont ID  
Sent By tklarge Date 2019-06-21 Time 06:36 Rev Time 0.00
Received By tklarge Date 2019-06-21 Time 05:33 Sent To  
Notes
***NONE***

Review Stop P PLUMBING
Rev No 1 Status F Date 2019-06-06 Cont ID  
Sent By tklarge Date 2019-06-06 Time 07:07 Rev Time 0.00
Received By tklarge Date 2019-06-06 Time 06:25 Sent To  
Notes
2019-06-06 07:03:381) SHOW THE LOCATION AND TERMINATION POINTS OF THE ROOF
 DRAINS PIPING ON THE PLAN VIEW OF THE BUILDING. WPB
 AMEND. TO FBC SEC. 107.2.1.
 2) CLEANOUTS ARE REQUIRED IN THE STORM RISERS PER 2017
 FBC-PLUMBING SEC.1101.8.
 3) WHAT PROVISIONS ARE BEING MADE FOR SECONDARY
 (EMERGENCY OVERFLOW) PROVISIONS? INDICATE ON THE PLANS.
 4) ROOF DRAINAGE SHALL DISCHARGE A MINIMUM OF ONE FOOT
 AWAY FROM THE STRUCTURE SIDEWALL PER 2017 FBC-BUILDING
 SEC.1503.7.
  
 TIM LARGE
 CHIEF PLUMBING INSPECTOR
 PLUMBING PLAN REVIEW
 561-805-6692
 [email protected]
  