| Plan Review Stops For Permit 19051075 |
| Review Stop |
B |
BUILDING (STRUCTURAL) |
| Rev No |
2 |
Status |
P |
Date |
2019-06-25 |
|
|
Cont ID |
|
| Sent By |
pvalenti |
Date |
2019-06-25 |
Time |
13:12 |
Rev Time |
0.00 |
| Received By |
pvalenti |
Date |
2019-06-25 |
Time |
13:12 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
B |
BUILDING (STRUCTURAL) |
| Rev No |
1 |
Status |
P |
Date |
2019-06-05 |
|
|
Cont ID |
|
| Sent By |
pvalenti |
Date |
2019-06-05 |
Time |
10:55 |
Rev Time |
0.00 |
| Received By |
pvalenti |
Date |
2019-06-05 |
Time |
10:55 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
E |
ELECTRICAL |
| Rev No |
2 |
Status |
P |
Date |
2019-06-25 |
|
|
Cont ID |
|
| Sent By |
jleahy |
Date |
2019-06-25 |
Time |
11:38 |
Rev Time |
0.00 |
| Received By |
jleahy |
Date |
2019-06-25 |
Time |
11:38 |
Sent To |
B |
|
| Notes |
|
|
| Review Stop |
E |
ELECTRICAL |
| Rev No |
1 |
Status |
P |
Date |
2019-06-05 |
|
|
Cont ID |
|
| Sent By |
jleahy |
Date |
2019-06-05 |
Time |
10:15 |
Rev Time |
0.00 |
| Received By |
jleahy |
Date |
2019-06-05 |
Time |
10:15 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
G |
GAS REVIEW |
| Rev No |
2 |
Status |
N |
Date |
2019-06-24 |
|
|
Cont ID |
|
| Sent By |
thunt |
Date |
2019-06-24 |
Time |
07:44 |
Rev Time |
0.00 |
| Received By |
thunt |
Date |
2019-06-24 |
Time |
07:44 |
Sent To |
|
|
| Notes |
| 2019-06-24 07:44:19 | GAS SUB PERMIT# 19060657 |
|
|
| Review Stop |
G |
GAS REVIEW |
| Rev No |
1 |
Status |
F |
Date |
2019-05-30 |
|
|
Cont ID |
|
| Sent By |
thunt |
Date |
2019-05-30 |
Time |
14:40 |
Rev Time |
0.00 |
| Received By |
thunt |
Date |
2019-05-30 |
Time |
14:40 |
Sent To |
|
|
| Notes |
| 2019-05-30 14:43:52 | 1ST GAS REVIEW**DENIED** | | | | | | 1) CPC CONTRACTOR IS NOT PERMITTED UNDER F.S 489 TO | | | PERFORM GAS WORK. A PLUMBING CONTRACTOR OR L.P 408E | | | MUST APPLY FOR PERMIT | | | | | | 2) NO PLANS HAVE BEEN SUBMITTED. PROVIDE GAS ISOMETRIC | | | DRAWING SHOWING PIPE SIZE, PIPE MATERIAL, AND PROVIDE | | | SIZING CHARHTS THAT SYSTEM IS BASED OFF OF. IF AN | | | EXISTING SYSTEM YOU MUST INCLUDE THE BTU LOAD OF ALL | | | EXISTING APL ON SYSTEM. FBC 107.3.5 | | | | | | 3) PLANS SHALL BE SIGNED AND SEALED. F.S 471 | | | | | | | | | TIM HUNT | | | PLUMBING INSPECTOR/PLUMBING PLAN EXAMINER | | | BUILDING DIVISION | | | CITY OF WEST PALM BEACH | | | 561-248-2703 | | | [email protected] | | | [email protected] | | | | | | | | | |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
2 |
Status |
N |
Date |
2019-06-25 |
|
|
Cont ID |
|
| Sent By |
pvalenti |
Date |
2019-06-25 |
Time |
13:29 |
Rev Time |
0.00 |
| Received By |
pvalenti |
Date |
2019-06-17 |
Time |
14:28 |
Sent To |
|
|
| Notes |
| 2019-06-18 14:29:08 | RESUB ROUTED TO ZONING INBOX |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
1 |
Status |
N |
Date |
2019-06-05 |
|
|
Cont ID |
|
| Sent By |
pvalenti |
Date |
2019-06-05 |
Time |
10:55 |
Rev Time |
0.00 |
| Received By |
pvalenti |
Date |
2019-05-22 |
Time |
10:47 |
Sent To |
|
|
| Notes |
| 2019-05-23 10:47:58 | ROUTED TO ZONING INBOX |
|
|
| Review Stop |
P |
PLUMBING |
| Rev No |
2 |
Status |
P |
Date |
2019-06-24 |
|
|
Cont ID |
|
| Sent By |
thunt |
Date |
2019-06-24 |
Time |
08:38 |
Rev Time |
0.00 |
| Received By |
thunt |
Date |
2019-06-24 |
Time |
08:38 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
P |
PLUMBING |
| Rev No |
1 |
Status |
F |
Date |
2019-05-30 |
|
|
Cont ID |
|
| Sent By |
thunt |
Date |
2019-05-30 |
Time |
14:43 |
Rev Time |
0.00 |
| Received By |
thunt |
Date |
2019-05-30 |
Time |
14:43 |
Sent To |
|
|
| Notes |
| 2019-05-30 14:45:15 | 1ST PLUMBING REVIEW**DENIED** | | | | | | PLANS SHALL BE SIGNED AND SEALED. F.S 471 | | | | | | | | | TIM HUNT | | | PLUMBING INSPECTOR/PLUMBING PLAN EXAMINER | | | BUILDING DIVISION | | | CITY OF WEST PALM BEACH | | | 561-248-2703 | | | [email protected] | | | [email protected] | | | | | | | | | |
|
|
| Review Stop |
Z |
ZONING |
| Rev No |
2 |
Status |
P |
Date |
2019-06-20 |
|
|
Cont ID |
|
| Sent By |
ajones |
Date |
2019-06-20 |
Time |
14:10 |
Rev Time |
0.00 |
| Received By |
ajones |
Date |
2019-06-20 |
Time |
14:10 |
Sent To |
P |
|
| Notes |
|
|
| Review Stop |
Z |
ZONING |
| Rev No |
1 |
Status |
P |
Date |
2019-05-28 |
|
|
Cont ID |
|
| Sent By |
mcruz |
Date |
2019-05-28 |
Time |
16:13 |
Rev Time |
0.00 |
| Received By |
mcruz |
Date |
2019-05-28 |
Time |
16:08 |
Sent To |
|
|
| Notes |
|
|