Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status P Date 2019-10-29 Cont ID  
Sent By pvalenti Date 2019-10-29 Time 16:53 Rev Time 0.00
Received By pvalenti Date 2019-10-29 Time 16:53 Sent To  
Notes
***NONE***

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status F Date 2019-06-05 Cont ID  
Sent By shill Date 2019-06-05 Time 06:56 Rev Time 0.00
Received By shill Date 2019-06-05 Time 06:55 Sent To  
Notes
2019-06-05 06:56:40****CORRECTIONS****
  
 SAMANTHA HILL
 BUILDING PLANS EXAMINER
 [email protected]
 561-805-6724
  
 FBC = FLORIDA BUILDING CODE, 6TH EDITION (2017)
 FBC B = FBC BUILDING
 FBC R = FBC RESIDENTIAL
 FBC EB = FBC EXISTING BUILDING
 FBC A = FBC ACCESSIBILITY
 FBC EC = FBC ENERGY CONSERVATION
  
 1. FBC 1609, PROVIDE A STRUCTURAL DETAIL FOR SLAB AND
 ANCHORING OF GENERATOR (DESIGN PROFESSIONAL REQUIRED).
  
  

Review Stop E ELECTRICAL
Rev No 2 Status P Date 2019-10-25 Cont ID  
Sent By fgiaquin Date 2019-10-25 Time 06:31 Rev Time 0.00
Received By fgiaquin Date 2019-10-25 Time 06:17 Sent To P
Notes
2019-10-25 06:32:04ALREADY PASSED BY JOHN PEARSON ON 5/27/2019

Review Stop E ELECTRICAL
Rev No 1 Status P Date 2019-05-27 Cont ID  
Sent By jpearson Date 2019-05-27 Time 15:18 Rev Time 0.00
Received By jpearson Date 2019-05-27 Time 15:18 Sent To  
Notes
***NONE***

Review Stop FIRE FIRE DEPARTMENT
Rev No 2 Status P Date 2019-10-01 Cont ID  
Sent By pleduc Date 2019-10-01 Time   Rev Time 0.00
Received By pleduc Date 2019-10-01 Time 15:37 Sent To E
Notes
2019-10-01 15:44:33THIS PLAN WAS REVIEWED AND APPROVED BY PETER LEDUC,
 FIRE MARSHAL, WITH THE FOLLOWING COMMENTS:
  
 PLEASE CONSIDER THE FOLLOWING AS PROVISO:
  
 THESE PROVISO COMMENTS WILL BE VERIFIED AND CONFIRMED
 AT THE TIME OF FIRE INSPECTION. FAILURE TO FOLLOW THESE
 PROVISO COMMENTS WILL RESULT IN A FAILED FIRE
 INSPECTION.
  
  
 1) INSTALL AND TEST PER NFPA 110 IF SUPPLYING POWER TO
 ANY LIFE SAFETY EQUIPMENT.
  
 PER NFPA 110
  
 1.1 SCOPE. THIS STANDARD CONTAINS REQUIREMENTS COVERING
 THE
 PERFORMANCE OF EMERGENCY AND STANDBY POWER SYSTEMS
 PROVIDING
 AN ALTERNATE SOURCE OF ELECTRICAL POWER TO LOADS IN
 BUILDINGS
 AND FACILITIES IN THE EVENT THAT THE PRIMARY POWER
 SOURCE
 FAILS.
 1.1.1 POWER SYSTEMS COVERED IN THIS STANDARD INCLUDE
 POWER
 SOURCES, TRANSFER EQUIPMENT, CONTROLS, SUPERVISORY
 EQUIPMENT,
 AND ALL RELATED ELECTRICAL AND MECHANICAL AUXILIARY AND
 ACCESSORY
 EQUIPMENT NEEDED TO SUPPLY ELECTRICAL POWER TO THE LOAD
 TERMINALS OF THE TRANSFER EQUIPMENT.
 1.1.2 THIS STANDARD COVERS INSTALLATION, MAINTENANCE,
 OPERATION,
 AND TESTING REQUIREMENTS AS THEY PERTAIN TO THE
 PERFORMANCE
 OF THE EMERGENCY POWER SUPPLY SYSTEM (EPSS).
  
 1.1.3 THIS STANDARD DOES NOT COVER THE FOLLOWING:
 (1) APPLICATION OF THE EPSS
 (2) EMERGENCY LIGHTING UNIT EQUIPMENT
 (3) DISTRIBUTION WIRING
 (4) UTILITY SERVICE WHEN SUCH SERVICE IS PERMITTED AS
 THE EPSS
 (5) PARAMETERS FOR STORED ENERGY DEVICES
 (6) THE EQUIPMENT OF SYSTEMS THAT ARE NOT CLASSED AS
 LEVEL 1
 OR LEVEL 2 SYSTEMS IN ACCORDANCE WITH CHAPTER 4 OF THIS
 STANDARD
  
 4.4* LEVEL. THIS STANDARD RECOGNIZES TWO LEVELS OF
 EQUIPMENT
 INSTALLATION, PERFORMANCE, AND MAINTENANCE.
 4.4.1* LEVEL 1 SYSTEMS SHALL BE INSTALLED WHERE FAILURE
 OF THE
 EQUIPMENT TO PERFORM COULD RESULT IN LOSS OF HUMAN LIFE
 OR
 SERIOUS INJURIES.
 4.4.2* LEVEL 2 SYSTEMS SHALL BE INSTALLED WHERE FAILURE
 OF THE
 EPSS TO PERFORM IS LESS CRITICAL TO HUMAN LIFE AND
 SAFETY.
 4.4.3 ALL EQUIPMENT SHALL BE PERMANENTLY INSTALLED.
 4.4.4* LEVEL 1 AND LEVEL 2 SYSTEMS SHALL ENSURE THAT
 ALL LOADS
 SERVED BY THE EPSS ARE SUPPLIED WITH ALTERNATE POWER
 THAT
 MEETS ALL THE FOLLOWING CRITERIA:
 (1) OF A QUALITY WITHIN THE OPERATING LIMITS OF THE
 LOAD
 (2) FOR A DURATION SPECIFIED FOR THE CLASS AS DEFINED
 IN TABLE
 4.1(A)
 (3) WITHIN THE TIME SPECIFIED FOR THE TYPE AS DEFINED
 IN TABLE
 4.1(B)
  
 PLEASE REVIEW AND ENSURE COMPLIANCE.
  
 PETER LEDUC
 FIRE MARSHAL
 561-804-4709
 [email protected]
  

Review Stop FIRE FIRE DEPARTMENT
Rev No 1 Status F Date 2019-06-05 Cont ID  
Sent By pleduc Date 2019-06-05 Time   Rev Time 0.00
Received By pleduc Date 2019-06-05 Time 10:50 Sent To I
Notes
2019-06-05 10:52:55THIS PLAN WAS REVIEWED AND FAILED BY PETER LEDUC, FIRE
 MARSHAL, WITH THE FOLLOWING COMMENTS:
  
 1) THERE ARE LIMITED LOCATIONS INDICATIONED.
  
 PLEASE PROVIDE THE LOCATION OF THIS GENERATOR INCLUDING
 ALL DIMENSIONS TO BUILDINGS; THE ONE IT SERVES AND
 NEIGHBORING, WINDOWS AND DOORS AND ENSURE THEY COMPLY
 WITH THE APPLICABLE CODES.
  
  
 2) THERE ARE NO FOUNDATION DETAILS.
  
 PLEASE PROVIDE DETAILS, INCLUDING LOCATION, DIMENSIONS,
 TIE-DOWNS, ETC.
  
  
 3) WHEN RESUBMITTING, PLEASE PROVIDE PLAN SHEET
 REVISION CLOUDS OR NUMBERED NARRATIVE RESPONSES TO THE
 ABOVE.
  
  
 4) ADDITIONAL COMMENTS MAY BE PROVIDED ON THE
 RE-SUBMITTAL OF THE ABOVE.
  
 PETER LEDUC
 FIRE MARSHAL
 561-804-4709
 [email protected]
  

Review Stop G GAS REVIEW
Rev No 3 Status N Date 2019-12-06 Cont ID  
Sent By abelisle Date 2019-12-06 Time 10:41 Rev Time 0.00
Received By abelisle Date 2019-12-06 Time 10:41 Sent To I
Notes
2019-12-06 10:42:48GAS IS ON PERMIT 19111126

Review Stop G GAS REVIEW
Rev No 2 Status F Date 2019-10-29 Cont ID  
Sent By abelisle Date 2019-10-29 Time 06:53 Rev Time 0.00
Received By abelisle Date 2019-10-29 Time 06:13 Sent To B
Notes
2019-10-29 06:53:5810/29/2019 1ST GAS REVIEW**DENIED** WITH COMMENTS NOTE
 - A COMPREHENSIVE REVIEW COULD NOT BE DONE AT THIS TIME
 AND ADDITIONAL PLAN REVIEW COMMENTS MAY BE GENERATED
 UPON THE RE-REVIEW OF SUBMITTED CORRECTIONS.
  
 1- TYPE OF GAS (LP OR NATURAL). WPB AMENDMENTS TO THE
 FBC SEC. 107.2.1 INFORMATION ON CONSTRUCTION DOCUMENTS.
  
 2- SUBMIT AN ISOMETRIC DRAWING THAT CLEARLY SHOWS THE
 LENGTH OF ALL CUT SECTIONS OF PIPE PER 2017 FBC FUEL
 GAS, SECS. 402.4.1, 402.4.2. OR 2017 FBC FUEL GAS RES
 SECS. G2413.4.1, G2413.4.2.
  
 3- GAS RISER DIAGRAM REQUIRED WPB AMENDMENTS TO THE FBC
 SEC. 107.5.1.5 (9) COMMERCIAL GAS
  
 4- SHOW THE LOCATION OF ALL MP (STEP-DOWN) REGULATORS.
 A LISTED SHUTOFF VALVE SHALL BE INSTALLED IMMEDIATELY
 AHEAD OF EACH MP REGULATOR. 2017 FBC FUEL GAS SEC.
 409.4, FBC FUEL GAS RES. SEC. G2420.4.
  
 5- INDICATE THE DELIVERY PRESSURE (PSI) OF THE SYSTEM
 ON THE PLAN PER 2017 FBC FUEL GAS SEC. 402.2 OR 2017
 FBC FUEL GAS RES. SEC. G2413.2.
  
 6- SUBMIT MANUFACTURER?S SPECIFICATIONS FOR THE
 PRESSURE REGULATORS. REGULATORS INSTALLED ON THE
 EXTERIOR OF THE BUILDING SHALL BE APPROVED FOR OUTDOOR
 INSTALLATION. 2017 FBC FUEL GAS SEC.410.1 OR 2017 FBC
 FUEL GAS RES. SEC. G2421.1.
  
 7- SUBMIT TWO COPIES OF THE GAS SIZING TABLE. WPB
 AMENDMENTS TO THE FBC SEC. 107.2.1.
  
 8- GAS PLAN REVIEW, A GAS PLAN HAS NOT BEEN INCLUDED IN
 THIS SUBMITTAL PACKAGE. A GAS PLAN REVIEW HAS NOT BEEN
 PERFORMED AT THIS TIME. A SEPARATE GAS PERMIT AND PLANS
 WILL BE REQUIRED FOR A CONTRACTOR TO PERFORM THE
 RELATED WORK. PROVIDE COMPLETE PLANS AND GAS RISER THAT
 REFLECTS THE ENTIRE SCOPE OF GAS WORK TO BE DONE AT
 THIS TIME. WPB AMENDMENTS TO FBC SEC. 107.2.1.
  
 9- WHEN RESUBMITTING PLANS PLEASE INDICATE THE REVISION
 & REMOVE ANY VOIDED SHEETS & REPLACE ANY PAGES AS
 NECESSARY. A TRANSMITTAL LETTER LISTING THE ORIGINAL
 REVIEW COMMENT NUMBER, WITH A DESCRIPTION OF THE
 REVISION, MADE, IDENTIFYING THE SHEET OR SPECIFICATION
 PAGE WHERE THE CHANGES CAN BE FOUND WILL HELP TO
 EXPEDITE YOUR PERMIT. THANK YOU FOR YOUR ANTICIPATED
 COOPERATION.
  
 ATELYO BELISLE
 PLUMBING INSPECTOR /
 PLUMBING PLANS EXAMINER
 AVAILABLE BY APPOINTMENT ONLY
 [email protected]
 561-805-6695
  

Review Stop G GAS REVIEW
Rev No 1 Status P Date 2019-05-20 Cont ID  
Sent By thunt Date 2019-05-20 Time 07:20 Rev Time 0.00
Received By thunt Date 2019-05-20 Time 07:20 Sent To  
Notes
2019-05-20 07:20:46GAS PERMIT REQUIRED

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2019-10-29 Cont ID  
Sent By abelisle Date 2019-12-06 Time 10:41 Rev Time 0.00
Received By pvalenti Date 2019-09-27 Time 14:20 Sent To  
Notes
2019-10-01 14:20:45RESUB ROUTED TO FIRE INBOX

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2019-06-05 Cont ID  
Sent By cpuell Date 2019-06-05 Time 15:50 Rev Time 0.00
Received By cpuell Date 2019-05-07 Time 14:03 Sent To  
Notes
2019-06-05 06:56:50TO FIRE
  
  
2019-05-08 14:03:14ROUTED TO ZONING INBOX

Review Stop Z ZONING
Rev No 1 Status P Date 2019-05-17 Cont ID  
Sent By mcruz Date 2019-05-17 Time 08:02 Rev Time 0.00
Received By mcruz Date 2019-05-17 Time 08:00 Sent To  
Notes
***NONE***


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved