| Plan Review Stops For Permit 19040527 |
| Review Stop |
B |
BUILDING (STRUCTURAL) |
| Rev No |
4 |
Status |
P |
Date |
2019-06-20 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2019-06-20 |
Time |
07:56 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2019-06-20 |
Time |
07:13 |
Sent To |
I |
|
| Notes |
|
|
| Review Stop |
B |
BUILDING (STRUCTURAL) |
| Rev No |
3 |
Status |
F |
Date |
2019-06-06 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2019-06-06 |
Time |
14:01 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2019-06-06 |
Time |
13:57 |
Sent To |
I |
|
| Notes |
| 2019-06-06 14:01:22 | PLAN | | | REVIEW COMMENTS | | | | | | 3RD REVIEW: FBC FIFTH EDITION (2014) | | | ROBERT MCDOUGAL, CBO | | | COMMERCIAL COMBINATION PLANS EXAMINER | | | (561) 805-6714 | | | [email protected] | | | | | | SUBMITTAL IS DENIED BY BUILDING. | | | PLEASE ADDRESS THE ITEMS NOTED BELOW: | | | | | | 1) THE NEW SIGNED AND SEALED DRAWINGS THAT WERE | | | SUBMITTED DO NOT HAVE THE SHOP DRAWING REVIEW STAMP | | | FROM THE ARCHITECT (DESIGNER OF RECORDS). | | | 2) IN ORDER TO AVOID NEEDLESS DELAYS, PLEASE REVIEW | | | SUBMITTALS FOR ERRORS PRIOR TO SUBMITTING THEM. |
|
|
| Review Stop |
B |
BUILDING (STRUCTURAL) |
| Rev No |
2 |
Status |
F |
Date |
2019-05-23 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2019-05-23 |
Time |
16:36 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2019-05-23 |
Time |
16:36 |
Sent To |
I |
|
| Notes |
| 2019-05-23 16:42:16 | PLAN | | | REVIEW COMMENTS | | | | | | 2ND REVIEW: FBC FIFTH EDITION (2014) | | | ROBERT MCDOUGAL, CBO | | | COMMERCIAL COMBINATION PLANS EXAMINER | | | (561) 805-6714 | | | [email protected] | | | | | | SUBMITTAL IS DENIED BY BUILDING. | | | PLEASE ADDRESS THE ITEMS NOTED BELOW: | | | | | | 1) ON SHEET 2 OF 10, THE MAXIMUM DESIGN LOAD PRESSURE | | | FOR ZONE 5 IS SPECIFIED AS -407 PSF AND IT SHOULD -47 | | | PSF TO MATCH THE APPROVED PLANS. FBC 107.2.1 PLEASE | | | CORRECT. | | | | | | 2) IN ORDER TO AVOID NEEDLESS DELAYS, PLEASE REVIEW | | | SUBMITTALS FOR ERRORS PRIOR TO SUBMITTING THEM. |
|
|
| Review Stop |
B |
BUILDING (STRUCTURAL) |
| Rev No |
1 |
Status |
F |
Date |
2019-05-07 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2019-05-07 |
Time |
18:24 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2019-05-07 |
Time |
18:03 |
Sent To |
I |
|
| Notes |
| 2019-05-07 18:23:51 | PLAN | | | REVIEW COMMENTS | | | | | | 1ST REVIEW: FBC FIFTH EDITION (2014) | | | ROBERT MCDOUGAL, CBO | | | COMMERCIAL COMBINATION PLANS EXAMINER | | | (561) 805-6714 | | | [email protected] | | | | | | SUBMITTAL IS DENIED BY BUILDING. | | | PLEASE ADDRESS THE ITEMS NOTED BELOW: | | | | | | 1) THE VULT WINDSPEED ON THE APPROVED PLANS IS 170 MPH | | | AND ON SHEET 1 OF THE DOOR AND WINDOW ENGINEERING IT IS | | | SPECIFIED AS 165 MPH. PLEASE COORDINATE THE TWO. FBC | | | 107.2.1 | | | | | | 2) THE MAXIMUM DESIGN LOAD PRESSURES FOR WALL ZONES 4 | | | AND 5 ON SHEET 1 OF THE DOOR AND WINDOW ENGINEERING IS | | | LOWER THAN THE ONES SPECIFIED ON THE APPROVED PLANS. | | | PLEASE COORDINATE THE TWO. FBC 107.2.1 | | | THE PLANS HAVE +35.2 PSF, -38.2 PSF FOR ZONE 4 AND | | | +35.2 PSF, -47.0 PSF FOR ZONE 5. | | | | | | 3) WHEN BEING SUBMITTED FOR PUBLIC RECORD, THE 10 | | | SHEETS OF DOOR AND WINDOW DRAWINGS FROM THE ENGINEER, | | | THOMAS J. TWOMEY, P.E. ARE REQUIRED TO HAVE THE | | | ENGINEER'S ORIGINAL HANDWRITTEN SIGNATURE AND SEAL IN | | | ACCORDANCE WITH FAC 61G15-23.003 AND FS 471. | | | |
|
|
| Review Stop |
HIST |
HISTORICAL |
| Rev No |
4 |
Status |
P |
Date |
2019-06-19 |
|
|
Cont ID |
|
| Sent By |
fmittner |
Date |
2019-06-19 |
Time |
10:10 |
Rev Time |
0.00 |
| Received By |
fmittner |
Date |
2019-06-19 |
Time |
10:10 |
Sent To |
B |
|
| Notes |
|
|
| Review Stop |
HIST |
HISTORICAL |
| Rev No |
3 |
Status |
P |
Date |
2019-06-05 |
|
|
Cont ID |
|
| Sent By |
fmittner |
Date |
2019-06-05 |
Time |
14:24 |
Rev Time |
0.00 |
| Received By |
fmittner |
Date |
2019-06-05 |
Time |
14:24 |
Sent To |
B |
|
| Notes |
|
|
| Review Stop |
HIST |
HISTORICAL |
| Rev No |
2 |
Status |
P |
Date |
2019-05-21 |
|
|
Cont ID |
|
| Sent By |
fmittner |
Date |
2019-05-21 |
Time |
12:59 |
Rev Time |
0.00 |
| Received By |
fmittner |
Date |
2019-05-21 |
Time |
12:59 |
Sent To |
B |
|
| Notes |
|
|
| Review Stop |
HIST |
HISTORICAL |
| Rev No |
1 |
Status |
P |
Date |
2019-05-02 |
|
|
Cont ID |
|
| Sent By |
fmittner |
Date |
2019-05-02 |
Time |
14:33 |
Rev Time |
0.00 |
| Received By |
fmittner |
Date |
2019-05-02 |
Time |
14:33 |
Sent To |
B |
|
| Notes |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
4 |
Status |
N |
Date |
2019-06-20 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2019-06-20 |
Time |
07:56 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2019-06-12 |
Time |
15:32 |
Sent To |
|
|
| Notes |
| 2019-06-13 15:32:59 | RESUB ROUTED TO HISTORIC INBOX |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
3 |
Status |
N |
Date |
2019-06-06 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2019-06-06 |
Time |
14:01 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2019-05-30 |
Time |
13:28 |
Sent To |
|
|
| Notes |
| 2019-05-31 13:28:27 | RESUB ROUTED TO HISTORIC INBOX |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
2 |
Status |
N |
Date |
2019-05-23 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2019-05-23 |
Time |
16:36 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2019-05-13 |
Time |
11:49 |
Sent To |
|
|
| Notes |
| 2019-05-14 11:49:58 | RESUB ROUTED TO HISTORIC INBOX |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
1 |
Status |
N |
Date |
2019-05-07 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2019-05-07 |
Time |
18:24 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2019-04-10 |
Time |
15:50 |
Sent To |
|
|
| Notes |
| 2019-04-11 15:50:13 | SUBMITTAL ROUTED TO HISTORIC INBOX |
|
|