Plan Review Details - Permit 19040105
Plan Review Stops For Permit 19040105
Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status P Date 2019-04-25 Cont ID  
Sent By rgathrig Date 2019-04-25 Time 12:06 Rev Time 0.00
Received By rgathrig Date 2019-04-25 Time 12:04 Sent To  
Notes
2019-04-25 12:06:18PASSED WITH PROVISO CONCERNING ALL PROVISOS FOR BASE
 BUILDING APPLY TO THIS INTERIOR BUILDOUT
 MUST PROVIDE ENERGY CODE CALS PRIOR TO FRAMING

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status F Date 2019-04-22 Cont ID  
Sent By shill Date 2019-04-22 Time 15:28 Rev Time 0.00
Received By shill Date 2019-04-22 Time 10:55 Sent To  
Notes
2019-04-22 15:32:49****CORRECTIONS****
  
 SAMANTHA HILL
 BUILDING PLANS EXAMINER
 [email protected]
 561-805-6724
  
 1. THIS PERMIT (19040105, UNIT 2101 AKA 21A) HAS A
 NARRATIVE WHICH REFERS TO REVISION 18060899, UNIT 22C.
 A COMPARISON CANNOT BE DONE AT THIS TIME.
  
 EITHER PROVIDE A MATRIX CORRELATING NEW SHEETS WITH
 PREVIOUSLY PASSED SHEETS (INCLUDE PERMIT OR REVISION
 NUMBER AND PAGE NAME IF NOT THE SAME), OR REQUEST A NEW
 REVIEW WHICH WILL HAVE STANDARD PROCESSING TIME.
  
  

Review Stop E ELECTRICAL
Rev No 1 Status P Date 2019-04-24 Cont ID  
Sent By jleahy Date 2019-04-24 Time 16:21 Rev Time 0.00
Received By jleahy Date 2019-04-24 Time 11:32 Sent To  
Notes
***NONE***

Review Stop E-LOWVOLT ELECTRICAL LOW VOLTAGE
Rev No 1 Status P Date 2019-04-25 Cont ID  
Sent By jleahy Date 2019-04-25 Time 09:38 Rev Time 0.00
Received By jleahy Date 2019-04-25 Time 09:37 Sent To  
Notes
***NONE***

Review Stop FIRE FIRE DEPARTMENT
Rev No 1 Status P Date 2019-04-25 Cont ID  
Sent By pleduc Date 2019-04-04 Time   Rev Time 0.00
Received By pleduc Date 2019-04-04 Time 13:38 Sent To  
Notes
2019-04-04 13:56:03PREVIOUS COMMENTS ADDRESSED.
  
  
  
 PETER LEDUC
 FIRE MARSHAL
 561-804-4709
 [email protected]
  
  

Review Stop G GAS REVIEW
Rev No 1 Status P Date 2019-04-25 Cont ID  
Sent By rgathrig Date 2019-04-25 Time 14:17 Rev Time 0.00
Received By rgathrig Date 2019-04-25 Time 14:17 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2019-04-26 Cont ID  
Sent By lmarchan Date 2019-04-26 Time 10:46 Rev Time 0.00
Received By lmarchan Date 2019-04-02 Time 09:43 Sent To  
Notes
***NONE***

Review Stop M MECHANICAL (A/C)
Rev No 1 Status P Date 2019-04-25 Cont ID  
Sent By rgathrig Date 2019-04-25 Time 12:07 Rev Time 0.00
Received By rgathrig Date 2019-04-25 Time 12:07 Sent To  
Notes
***NONE***

Review Stop P PLUMBING
Rev No 1 Status P Date 2019-04-25 Cont ID  
Sent By rgathrig Date 2019-04-25 Time 12:07 Rev Time 0.00
Received By rgathrig Date 2019-04-25 Time 12:06 Sent To  
Notes
***NONE***

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 1 Status P Date 2019-04-22 Cont ID  
Sent By shill Date 2019-04-22 Time 10:57 Rev Time 0.00
Received By shill Date 2019-04-22 Time 10:57 Sent To  
Notes
***NONE***