| 2019-05-02 10:10:04 | 2017 FBC- BUILDING PLAN REVIEW |
| | W. P. B. PERMIT: 19030479 |
| | ADD: 4801 DREHER TRL. N |
| | CONT: GAST CONSTRUCTION |
| | TEL: 561-281-1001 |
| | E-MAIL: [email protected] |
| | |
| | 2017 FLORIDA BUILDING CODE W 2017 WEST PALM BEACH |
| | AMENDMENTS TO THE FLORIDA BUILDING CODE, CHAPTER 1, |
| | ADMINISTRATION |
| | |
| | 1ST REVIEW |
| | DATE: THUS.MAY 02/ 2019 |
| | ACTION: DENIED |
| | |
| | 1) WITHIN THIS SUBMISSION THERE WAS NO SURVEY. THERE |
| | ARE 2 ISSUES AT HAND. THE CLOSENESS TO EXISTING |
| | BUILDINGS AND THE PROPOSED BUILDING IS LOCATED IN A AE |
| | FLOOD ZONE. THE LIFE SAFETY SHEETS NOR DOES THE SHEET |
| | A1 FLOOR PLAN PROVIDE AT WHAT MINIMUM HEIGHT THE FINISH |
| | FLOOR ELEVATION SHOULD BE. THE HEIGHT SHOULD READ IN |
| | NAV88 SINCE THE PROPOSED BUILDING IS IN A FLOOD ZONE. |
| | |
| | 1A) THE ISSUE WITH THIS PROPOSED LOCATION THE CIVIL |
| | SHEET C2.2 DOES NOT PROVIDE THE DISTANCE OF THE |
| | BUILDING TO THE NORTH OR TO THE WEST. THE DESIGNER OF |
| | RECORD WILL NEED TO DESIGNATE AN ASSUMED PROPERTY LINE |
| | BETWEEN BUILDING THAT WILL WORK FOR THE CONSTRUCTION |
| | TYPE AND OPENINGS OF THESE BUILDINGS AND THE NEW |
| | PROPOSED BUILDING. SEE THE 2017 FBC-B SECTION 503.1.2 |
| | BUILDINGS ON THE SAME LOT. TABLE 602 FIRE RESISTANCE |
| | RATING REQUIREMENTS FOR EXTERIOR WALLS BASED ON FIRE |
| | SEPARATION DISTANCE. TABLE 705.8. OPENINGS BASED ON |
| | FIRE SEPARATION. |
| | |
| | 1B) FBC BUILDING 1612 AND CITY OF WPB CODE OF SECTION |
| | 94-546. STRUCTURE IS LOCATED IN AN "AE? FLOOD ZONE WITH |
| | BFE @ 12.2 FEET. A FLOOD ELEVATION CERTIFICATE WILL BE |
| | REQUIRED. PLEASE REVIEW CITY ORDINANCE FOR THE CITY |
| | REQUIREMENTS AFTER OCT. 11/ 2017 AN ADDITIONAL ONE FOOT |
| | OF FREE BOARD WILL BE REQUIRED OR (2) FEET ABOVE BASE |
| | FLOOD. |
| | AFTER OCT. 11/ 2017 THE BUILDING DEPARTMENT WILL HAVE |
| | ADOPTED THE NEW FLOOD MAPS AND ALSO IN TOUGHS MAPS THE |
| | NAVD 88 ELEVATIONS. YOU CAN GO TO THE WEBSITE: |
| | WWW.NGS.NOAA.GOV/TOOLS/VERTCON/VERTCON.HTML FOR |
| | CONVERSIONS. |
| | DURING THE PERMITTING OF THIS STRUCTURE THERE WILL BE |
| | REQUIRED (3) DIFFERENT FLOOD ZONE CERTIFICATES |
| | REQUIRED: |
| | 1B) (1) A FLOOD ZONE CERTIFICATE IS REQUIRED AS PART OF |
| | THE PLAN REVIEW DOCUMENTS WITH THE PROPOSED FINISH |
| | FLOOR HEIGHT. W. P. B. ADMINISTRATIVE CODE 107.3.5.1.1 |
| | BUILDING MINIMUM PLAN REVIEW CRITERIA FOR COMMERCIAL |
| | BUILDINGS. (8) FLOOD REQUIREMENTS ELEVATIONS, |
| | ENCLOSURES, FLOOD DAMAGE-RESISTANT MATERIALS. |
| | |
| | 1B) (2) ONCE THE FIRST FLOOR SLAB IS POURED THE 2ND |
| | ELEVATION CERTIFICATE IS REQUIRED. W. P. B. |
| | ADMINISTRATIVE CODE 110.3 REQUIRED INSPECTIONS 1.2 |
| | FLOOR/ SLAB INSPECTION. IN FLOOD HAZARD AREAS, UPON |
| | PLACEMENT OF THE LOWEST FLOOR, INCLUDING BASEMENT, AND |
| | PRIOR TO FURTHER VERTICAL CONSTRUCTION, THE ELEVATION |
| | CERTIFICATION, REQUIRED IN SECTION 1612.5, SHALL BE |
| | SUBMITTED TO THE BUILDING OFFICIAL. |
| | |
| | 1B) (3) BEFORE THE ISSUANCE OF A CERTIFICATE OF |
| | OCCUPANCY OR A CERTIFICATE OF COMPLETION THE 3RD FLOOD |
| | ZONE CERTIFICATE IS REQUIRED WITH THE HEIGHT OF ALL |
| | EXTERIOR ATTENDANTS A/C PADS OR OTHER SLABS FOR |
| | GENERATORS. |
| | W. P. B. ADMINISTRATIVE CODE 110.3 REQUIRED INSPECTIONS |
| | (6) FINAL INSPECTION. TO BE MADE AFTER THE BUILDING IS |
| | COMPLETED AND READY FOR OCCUPANCY. 6.1. LOWEST FLOOR |
| | ELEVATION. IN FLOOD HAZARD AREAS, AS PART OF THE FINAL |
| | INSPECTION, A FINAL CERTIFICATION OF THE LOWEST FLOOR |
| | ELEVATION SHALL BE SUBMITTED TO THE AUTHORITY HAVING |
| | JURISDICTION. |
| | |
| | 2) NO SOILS REPORT HAS BEEN SUBMITTED FOR THIS REVIEW. |
| | THE SHEET S-4 UNDER THE HEADING OF FOUNDATION STATES |
| | THAT SITE PREPARATION & EXCAVATION WORK IS TO BE |
| | PREPARED IN STRICT ACCORDANCE WITH THE RECOMMENDATIONS |
| | ON THE SOILS AND FOUNDATIONS INVESTIGATION PREPARED BY |
| | AN APPROVED TESTING LABORATORY PRIOR TO FOUNDATION |
| | WORK. |
| | 2017 FBC-B SECTION 1803.5.2 QUESTIONABLE SOIL. WHERE |
| | THE CLASSIFICATION, STRENGTH OR COMPRESSIBILITY OF THE |
| | SOIL IS IN DOUBT OR WHERE A LOAD-BEARING VALUE SUPERIOR |
| | TO THAT SPECIFIED IN THIS CODE IS CLAIMED, THE BUILDING |
| | OFFICIAL SHALL BE PERMITTED TO REQUIRE THAT A |
| | GEOTECHNICAL INVESTIGATION BE CONDUCTED. |
| | |
| | 3) THIS REVIEW NO ENERGY DOCUMENTS WERE SUBMITTED. |
| | PLEASE SHOW COMPLIANCE WITH: |
| | 2017 ENERGY CODE SECTION C401.2 APPLICATION. |
| | COMMERCIAL BUILDINGS SHALL COMPLY WITH ONE OF THE |
| | FOLLOWING: |
| | 3.1.THE REQUIREMENTS OF ANSI/ASHRAE/IESNA 90.1, |
| | EXCLUDING SECTION 9.4.1.1(G) OF THE STANDARD. |
| | 3.2.THE REQUIREMENTS OF SECTIONS C402 THROUGH C405. IN |
| | ADDITION, COMMERCIAL BUILDINGS SHALL COMPLY WITH |
| | SECTION C406 AND TENANT SPACES SHALL COMPLY WITH |
| | SECTION C406.1.1. |
| | 3.3.THE REQUIREMENTS OF SECTIONS C402.5, C403.2, C404, |
| | C405.2, C405.3, C405.5, C405.6 AND C407. THE BUILDING |
| | ENERGY COST SHALL BE EQUAL TO OR LESS THAN 85 PERCENT |
| | OF THE STANDARD REFERENCE DESIGN BUILDING. |
| | |
| | 4) SHEET 003 SFSC STORAGE LIFE SAFETY SHEET SHOWS A 2 |
| | STORY BUILDING CLASSIFIED AS CONSTRUCTION TYPE V-B |
| | CONSTRUCTION, STORAGE OCCUPANCY. THE ISSUE WE SEE THAT |
| | THE 2 STORY BUILDING IS CONSIDERED AN ATRIUM. SEE THE |
| | DEFINITION OF ATRIUM IN THE 2017 THE FBC-B CHAPTER 2: |
| | ATRIUM. AN OPENING CONNECTING TWO OR MORE STORIES OTHER |
| | THAN ENCLOSED STAIRWAYS, ELEVATORS, HOIST WAYS, |
| | ESCALATORS, PLUMBING, ELECTRICAL, AIR-CONDITIONING OR |
| | OTHER EQUIPMENT, WHICH IS CLOSED AT THE TOP AND NOT |
| | DEFINED AS A MALL. STORIES, AS USED IN THIS DEFINITION, |
| | DO NOT INCLUDE BALCONIES WITHIN ASSEMBLY GROUPS OR |
| | MEZZANINES THAT COMPLY WITH SECTION 505. |
| | |
| | 4A) ATRIUMS REQUIRE AUTOMATIC SPRINKLER PROTECTION. SEE |
| | THE 2017 FBC-B SECTION 404.3 AUTOMATIC SPRINKLER |
| | PROTECTION. AN APPROVED AUTOMATIC SPRINKLER SYSTEM |
| | SHALL BE INSTALLED THROUGHOUT THE ENTIRE BUILDING. |
| | EXCEPTIONS: |
| | 1.THAT AREA OF A BUILDING ADJACENT TO OR ABOVE THE |
| | ATRIUM NEED NOT BE SPRINKLERED PROVIDED THAT PORTION OF |
| | THE BUILDING IS SEPARATED FROM THE ATRIUM PORTION BY |
| | NOT LESS THAN 2-HOUR FIRE BARRIERS CONSTRUCTED IN |
| | ACCORDANCE WITH SECTION 707 OR HORIZONTAL ASSEMBLIES |
| | CONSTRUCTED IN ACCORDANCE WITH SECTION 711, OR BOTH. |
| | |
| | 4B) COMPLIED WITH. THE QUESTION OF USING AN EXIT ACCESS |
| | STAIRWAY WITHIN THE 2 STORY ATRIUM WAS A QUESTION. |
| | FBC-B 1006.3 ALLOWS THE PATH OF TRAVEL TO AN EXIT SHALL |
| | NOT PASS THROUGH MORE THAN ONE ADJACENT STORY. TABLE |
| | 1006.3.2(2) STORIES WITH ONE EXIT OR EXIT ACCESS TO ONE |
| | EXIT, MAX. OCC. LOAD OF 29 AND COMMON PATH OF TRAVEL 75 |
| | FEET. SECTION 404.9.3. EXIT ACCESS TRAVEL DISTANCE AT |
| | OTHER THAN THE LEVEL OF EXIT DISCHARGE. |
| | |
| | 4C) WHAT THE PLAN IS DEFICIENT IN IS STATING, NO |
| | STORAGE BENEATH THE OPEN STAIRWAY FROM THE 2ND STORY. |
| | WHILE THE CODE DOES NOT STATE THIS FOR AN OPEN STAIRWAY |
| | IT DOES FOR ENCLOSURES UNDER INTERIOR STAIRWAYS SECTION |
| | 1011.7.3. AND ENCLOSURES UNDER EXTERIOR STAIRWAYS |
| | SECTION 1011.7.4. THIS IS THE ONLY MEANS OF EGRESS FROM |
| | THE SECOND FLOOR PLEASE SHOW HOW YOU WILL PROTECT THE |
| | STAIR FROM FIRE. |
| | |
| | 5A) DISCREPANCY IN PLANS, ELEVATION DIFFERENCE AT THE |
| | EDGE OF THE STAGE/ PLATFORM. SHEET 023 SFSC STORAGE |
| | C2.1 VERSES 008-SFSC STORAGE A5 ONE SHEET INDICATES A |
| | ELEVATION OF 14 FEET AT THE EDGE OF PLATFORM THE OTHER |
| | 13.7 FEET. PLEASE ALSO SEE SHEET S-1 EDGE OF SLAB -2 ? |
| | INCHES DIFFERENT ELEVATION THAN THE A SHEETS. |
| | |
| | 5B) IF THE AREA IN QUESTION PLATFORM IS NOT A STAGE A |
| | GUARDRAIL MAYBE REQUIRED IF THE DIFFERENCE IN GRADE IS |
| | MORE THAN 30 INCHES MEASURED VERTICALLY, SECTION 1015.2 |
| | WHERE REQUIRED, 2017 FBC-B. |
| | |
| | 6) 2017 FBC-B 1609.1.2 PROTECTION OF OPENINGS, |
| | 1609.6.4.4.1 COMPONENTS & CLADDING. FLORIDA DEPARTMENT |
| | OF COMMUNITY AFFAIRS, ADMINISTRATIVE CODE 61G20-3.005, |
| | RULE 9N-3 NOV. 01/ 2010 (31) SUB-CATEGORY OF PRODUCTS |
| | OR CONSTRUCTION SYSTEMS THAT WILL REQUIRE PRODUCT |
| | APPROVALS: |
| | (31)(A) EXTERIOR DOORS & ROOF HATCHES. |
| | (D) ROOFING PRODUCTS AND ASSEMBLIES |
| | |
| | 7) 107.3.4.2 DEFERRED SUBMITTALS. FOR THE PURPOSES OF |
| | THIS SECTION, DEFERRED SUBMITTALS ARE DEFINED AS THOSE |
| | PORTIONS OF THE DESIGN THAT ARE NOT SUBMITTED AT THE |
| | TIME OF THE APPLICATION AND THAT ARE TO BE SUBMITTED TO |
| | THE BUILDING OFFICIAL WITHIN A SPECIFIED PERIOD. |
| | DEFERRAL OF ANY SUBMITTAL ITEMS SHALL HAVE THE PRIOR |
| | APPROVAL OF THE BUILDING OFFICIAL. THE REGISTERED |
| | DESIGN PROFESSIONAL IN RESPONSIBLE CHARGE SHALL LIST |
| | THE DEFERRED SUBMITTALS ON THE CONSTRUCTION DOCUMENTS |
| | FOR REVIEW BY THE BUILDING OFFICIAL. |
| | |
| | DOCUMENTS FOR DEFERRED SUBMITTAL ITEMS SHALL BE |
| | SUBMITTED TO THE REGISTERED DESIGN PROFESSIONAL IN |
| | RESPONSIBLE CHARGE WHO SHALL REVIEW THEM AND FORWARD |
| | THEM TO THE BUILDING OFFICIAL WITH A NOTATION |
| | INDICATING THAT THE DEFERRED SUBMITTAL DOCUMENTS HAVE |
| | BEEN REVIEWED AND FOUND TO BE IN GENERAL CONFORMANCE TO |
| | THE DESIGN OF THE BUILDING. THE DEFERRED SUBMITTAL |
| | ITEMS SHALL NOT BE INSTALLED UNTIL THE DEFERRED |
| | SUBMITTAL DOCUMENTS HAVE BEEN APPROVED BY THE BUILDING |
| | OFFICIAL. |
| | |
| | 8) FOR ALL ROOFING PRODUCTS PLEASE IDENTIFY ALL ROOFING |
| | SUB-SYSTEMS AND THEIR ASSOCIATED PRESSURES FOR ROOF |
| | ZONE # 1. REVIEW THE PRODUCT APPROVAL LIMITATIONS, IF |
| | ENHANCED FASTENING IS ALLOWED FOR ROOF ZONES 2 & 3. |
| | FASTENER DENSITIES SHALL BE INCREASED FOR BOTH |
| | INSULATION & THE BASE SHEET AS CALCULATED IN COMPLIANCE |
| | WITH ROOFING APPLICATION STANDARDS RAS 117. CALCULATION |
| | PREPARED, SIGNED AND |
| | SEALED BY A FLORIDA REGISTERED PROFESSIONAL ENGINEER OR |
| | REGISTERED ARCHITECT. 1609.6.4.4.1 COMPONENTS & |
| | CLADDING. |
| | |
| | 9) IMPACT FEES - DIGITAL SUBMITTALS: PLANS WILL BE |
| | REVIEWED BY THE PBC IMPACT FEE OFFICE DIGITALLY VIA |
| | PROJECT DOX UPON NOTIFICATION BY THIS OFFICE. |
| | NOTIFICATION MAY OCCUR WHEN PLANS ARE NEAREST FINAL |
| | FORM. YOU MAY COORDINATE WITH THE IMPACT FEE OFFICE AT |
| | (561) 233-5025 OR SIMPLY UPLOAD THE MUNICIPAL IMPACT |
| | FEE QUESTIONNAIRE FORM TO YOUR PROJECT AND NAME THE |
| | FILE MUNICIPAL IMPACT FEE QUESTIONNAIRE. THE FORM CAN |
| | BE FOUND AT: HTTP://DISCOVER.PBCGOV.ORG/PZB/ADMINISTRAT |
| | ION/PDF/IMPACTFEES/FORMS/QUESTIONNAIRE.PDF UPON |
| | APPROVAL AND FEE PAYMENT, PLEASE UPLOAD THE RECEIPT TO |
| | YOUR PROJECT OR EMAIL IT TO [email protected] . |
| | |
| | 10) A TRANSMITTAL LETTER LISTING THE ORIGINAL REVIEW |
| | COMMENT NUMBER, WITH A DESCRIPTION OF THE REVISION |
| | MADE, IDENTIFYING THE SHEET OR SPECIFICATION PAGE WHERE |
| | THE CHANGES CAN BE FOUND WILL HELP TO EXPEDITE YOUR |
| | PERMIT. THANK YOU FOR YOUR ANTICIPATED COOPERATION. |
| | |
| | JAMES A. WITMER BN, PX, SFP, CBO |
| | SENIOR COMMERCIAL COMBINATION PLANS EXAMINER |
| | BUILDING DIVISION / DEVELOPMENT SERVICES DEPARTMENT |
| | 401 CLEMATIS ST. WEST PALM BEACH. FL 33402 |
| | TEL: 561-805-6717 |
| | FAX: 561-805-6676 |
| | E-MAIL: [email protected] |
| | |
| | |
| | |
| | |
| | |
| | |
| | |