Plan Review Details - Permit 19010178
Plan Review Stops For Permit 19010178
Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status P Date 2019-01-23 Cont ID  
Sent By rmcdouga Date 2019-01-23 Time 06:07 Rev Time 0.00
Received By rmcdouga Date 2019-01-23 Time 06:07 Sent To I
Notes
***NONE***

Review Stop E ELECTRICAL
Rev No 1 Status P Date 2019-01-10 Cont ID  
Sent By jleahy Date 2019-01-10 Time 17:34 Rev Time 0.00
Received By jleahy Date 2019-01-10 Time 17:34 Sent To  
Notes
***NONE***

Review Stop G GAS REVIEW
Rev No 1 Status N Date 2019-01-17 Cont ID  
Sent By tklarge Date 2019-01-17 Time 06:12 Rev Time 0.00
Received By tklarge Date 2019-01-17 Time 06:12 Sent To  
Notes
2019-01-17 06:12:55THERE IS NO HEATER ON THIS POOL.

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2019-03-07 Cont ID  
Sent By tklarge Date 2019-03-07 Time 04:19 Rev Time 0.00
Received By tklarge Date 2019-03-01 Time 12:25 Sent To P
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2019-01-23 Cont ID  
Sent By rmcdouga Date 2019-01-23 Time 06:07 Rev Time 0.00
Received By rmcdouga Date 2019-01-07 Time 09:27 Sent To  
Notes
2019-01-08 09:28:03ROUTED TO ZONING INBOX

Review Stop P PLUMBING
Rev No 2 Status P Date 2019-03-07 Cont ID  
Sent By tklarge Date 2019-03-07 Time 04:19 Rev Time 0.00
Received By tklarge Date 2019-03-07 Time 03:33 Sent To I
Notes
***NONE***

Review Stop P PLUMBING
Rev No 1 Status F Date 2019-01-17 Cont ID  
Sent By tklarge Date 2019-01-17 Time 06:12 Rev Time 0.00
Received By tklarge Date 2019-01-17 Time 06:01 Sent To  
Notes
2019-01-17 06:11:591) SUBMIT TOTAL DYNAMIC HEAD CALCULATIONS FOR THE
 MAXIMUM SYSTEM FLOW. THE MAXIMUM FLOW OF THE PUMP FROM
 ITS PUMP CURVE IS NO LONGER ALLOWED TO BE USED IN
 DETERMINING MAXIMUM SYSTEM FLOW RATE PER ANSI/APSP/ICC
 7 - 2013 SECS. 4.4.9, 4.4.9.1. THE 2013 EDITION
 ADDRESSES FLOW RATE IN GALLONS PER MINUTE (GPM). IT
 REQUIRES THAT MAXIMUM SYSTEM FLOW RATE DOES NOT EXCEED
 THE LISTED MAXIMUM FLOW RATE OF THE SUCTION OUTLET
 FITTING ASSEMBLY (DRAIN COVER).THE TDH CALCULATIONS
 MUST INCLUDE ALL OF THE SYSTEM COMPONENTS INCLUDING
 SUCTION AND RETURN PIPING, FITTINGS, VALVES, HEATER,
 FILTER, AND CHLORINATOR. ALL SYSTEM COMPONENTS EXCEPT
 THE PUMP.
 2) SUBMIT MANUFACTURER'S SPECS FOR THE MAIN DRAIN
 CCOVERS. WPB AMEND. TO FBC SEC. 107.2.1.
  
 TIM LARGE
 CHIEF PLUMBING INSPECTOR
 PLUMBING PLAN REVIEW
 561-805-6692
 [email protected]
  
  
  

Review Stop Z ZONING
Rev No 1 Status P Date 2019-01-09 Cont ID  
Sent By mcruz Date 2019-01-09 Time 09:16 Rev Time 0.00
Received By mcruz Date 2019-01-09 Time 09:10 Sent To PC
Notes
***NONE***


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved