Plan Review Details - Permit 18120386
Plan Review Stops For Permit 18120386
Review Stop G GAS REVIEW
Rev No 1 Status P Date 2019-01-14 Cont ID  
Sent By tklarge Date 2019-01-14 Time 13:31 Rev Time 0.00
Received By tklarge Date 2019-01-14 Time 13:31 Sent To I
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 3 Status N Date 2019-01-14 Cont ID  
Sent By tklarge Date 2019-01-14 Time 13:31 Rev Time 0.00
Received By tklarge Date 2019-01-14 Time 13:31 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2019-01-04 Cont ID  
Sent By tklarge Date 2019-01-04 Time 07:22 Rev Time 0.00
Received By tklarge Date 2019-01-02 Time 13:02 Sent To  
Notes
2019-01-03 13:02:37RESUB ROUTED TO TKLARGE

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2018-12-14 Cont ID  
Sent By lmarchan Date 2018-12-14 Time 10:13 Rev Time 0.00
Received By lmarchan Date 2018-12-11 Time 14:00 Sent To  
Notes
2018-12-12 14:00:44PLUMB<5K

Review Stop P PLUMBING
Rev No 4 Status P Date 2019-01-15 Cont ID  
Sent By gjohnson Date 2019-01-15 Time 13:46 Rev Time 0.00
Received By gjohnson Date 2019-01-15 Time 13:46 Sent To  
Notes
2019-01-15 13:47:38APPROVED PLAN STAMPED BY TIM LARGE ON 1/14/19

Review Stop P PLUMBING
Rev No 3 Status F Date 2019-01-04 Cont ID  
Sent By tklarge Date 2019-01-04 Time 07:22 Rev Time 0.00
Received By tklarge Date 2019-01-04 Time 06:22 Sent To  
Notes
2019-01-04 07:22:23THE CERTIFICATION THAT HAS BEEN SUBMITTED FROM IAPMO
 FOR THE SHOWER EXPIRED AFTER JUNE 2018. SUBMIT A VALID
 AND CURRENT CERTIFICATION.
  
 TIM LARGE
 CHIEF PLUMBING INSPECTOR
 PLUMBING PLAN REVIEW
 561-805-6692
 [email protected]
  
  

Review Stop P PLUMBING
Rev No 2 Status F Date 2018-12-14 Cont ID  
Sent By lmarchan Date 2018-12-14 Time 10:13 Rev Time 0.00
Received By lmarchan Date 2018-12-14 Time 10:13 Sent To  
Notes
2018-12-14 10:13:531) THIS BUILDING WAS BUILT IN COMPLIANCE WITH THE
 FEDERAL FAIR HOUSING ACT AND THE LEVEL OF ACCESSIBILITY
 MUST BE MAINTAINED. A 30 INCH WIDE MINIMUM BY 48 INCH
 DEEP MINIMUM CLEAR FLOOR SPACE MUST BE PROVIDED
 ADJACENT TO THE SHOWER AND BEGINNING FLUSH WITH THE
 CONTROL WALL OF THE SHOWER. SHOW THE REQUIRED CLEAR
 FLOOR SPACE ON BOTH DRAWINGS. NO PLUMBING FIXTURES MAY
 ENCROACH INTO THIS CLEAR FLOOR SPACE.
 2) THE EXISTING BACKING FOR FUTURE GRAB BARS SHALL NOT
 BE REMOVED.
 3) SUBMIT MANUFACTURER'S SPCEIFICATIONS FOR THE FIRE
 CAULKING TO BE USED. WPB AMEND. TO FBC SEC. 107.2.1.
 4) SUBMIT DETAILS AS TO HOW THE ACRYLIC WALL SYSTEM
 WILL BE SECURED TO THE EXISTING TILE WALL.WPB AMEND. TO
 FBC SEC. 107.2.1. IF AN ADHESIVE IS TO BE USED, SUBMIT
 SPECIFICATIONS.WPB AMEND. TO FBC SEC. 107.2.1.
 5) SUBMIT MANUFACTURER'S SPECIFICATIONS FOR THE
 PREFABRICATED SHOWER BASE AND WALL SYSTEM. THE UNIT
 SHALL COMPLY WITH 2017 FBC-PLUMBING SEC.417.1 AND ASME
 A112.19/CSA B45.1 OR CSA B45.5/IAPMO Z 124.
 6) THE NEW SHOWER VALVE SHALL BE BALANCED PRESSURE,
 THERMOSTATIC, OR COMBINATION
 BALANCED-PRESSURE/THERMOSTATIC AND COMPLY WITH ASSE
 1016/ASME A112.1016/CSA B125. 16 OR ASME A112.18.1/CSA
 B125.1 PER 2017 FBC PLUMBING SEC.424.3.
  
  

Review Stop P PLUMBING
Rev No 1 Status F Date 2018-12-14 Cont ID  
Sent By tklarge Date 2018-12-14 Time 10:16 Rev Time 0.00
Received By tklarge Date 2018-12-14 Time 09:46 Sent To I
Notes
2018-12-14 10:03:361) THIS BUILDING WAS BUILT IN COMPLIANCE WITH THE
 FEDERAL FAIR HOUSING ACT AND THE LEVEL OF ACCESSIBILITY
 MUST BE MAINTAINED. A 30 INCH WIDE MINIMUM BY 48 INCH
 DEEP MINIMUM CLEAR FLOOR SPACE MUST BE PROVIDED
 ADJACENT TO THE SHOWER AND BEGINNING FLUSH WITH THE
 CONTROL WALL OF THE SHOWER. SHOW THE REQUIRED CLEAR
 FLOOR SPACE ON BOTH DRAWINGS. NO PLUMBING FIXTURES MAY
 ENCROACH INTO THIS CLEAR FLOOR SPACE.
 2) THE EXISTING BACKING FOR FUTURE GRAB BARS SHALL NOT
 BE REMOVED.
 3) SUBMIT MANUFACTURER'S SPCEIFICATIONS FOR THE FIRE
 CAULKING TO BE USED. WPB AMEND. TO FBC SEC. 107.2.1.
 4) SUBMIT DETAILS AS TO HOW THE ACRYLIC WALL SYSTEM
 WILL BE SECURED TO THE EXISTING TILE WALL.WPB AMEND. TO
 FBC SEC. 107.2.1. IF AN ADHESIVE IS TO BE USED, SUBMIT
 SPECIFICATIONS.WPB AMEND. TO FBC SEC. 107.2.1.
 5) SUBMIT MANUFACTURER'S SPECIFICATIONS FOR THE
 PREFABRICATED SHOWER BASE AND WALL SYSTEM. THE UNIT
 SHALL COMPLY WITH 2017 FBC-PLUMBING SEC.417.1 AND ASME
 A112.19/CSA B45.1 OR CSA B45.5/IAPMO Z 124.
 6) THE NEW SHOWER VALVE SHALL BE BALANCED PRESSURE,
 THERMOSTATIC, OR COMBINATION
 BALANCED-PRESSURE/THERMOSTATIC AND COMPLY WITH ASSE
 1016/ASME A112.1016/CSA B125. 16 OR ASME A112.18.1/CSA
 B125.1 PER 2017 FBC PLUMBING SEC.424.3.
  
 TIM LARGE
 CHIEF PLUMBING INSPECTOR
 PLUMBING PLAN REVIEW
 561-805-6692
 [email protected]
  
  
  
  


Account Summary | Usage Policy | Privacy Policy