Plan Review Details - Permit 18110411
Plan Review Stops For Permit 18110411
Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status P Date 2018-12-08 Cont ID  
Sent By shill Date 2018-12-08 Time 15:31 Rev Time 0.00
Received By shill Date 2018-12-08 Time 15:31 Sent To  
Notes
***NONE***

Review Stop E ELECTRICAL
Rev No 1 Status P Date 2018-11-30 Cont ID  
Sent By jpearson Date 2018-11-30 Time 14:33 Rev Time 0.00
Received By jpearson Date 2018-11-30 Time 13:23 Sent To  
Notes
***NONE***

Review Stop FIRE FIRE DEPARTMENT
Rev No 1 Status P Date 2018-11-15 Cont ID  
Sent By scaldero Date 2018-11-15 Time 13:04 Rev Time 0.00
Received By scaldero Date 2018-11-15 Time 13:04 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2018-12-13 Cont ID  
Sent By jesmith Date 2018-12-13 Time 15:16 Rev Time 0.00
Received By jesmith Date 2018-12-13 Time 15:16 Sent To  
Notes
2018-12-08 15:33:2712/8 REMOVED FROM BOARD AND ROUTED TO JES DESK / S.HILL
  
  
2018-11-13 13:49:37B33

Review Stop M MECHANICAL (A/C)
Rev No 1 Status P Date 2018-12-03 Cont ID  
Sent By ccole Date 2018-11-30 Time 11:15 Rev Time 0.00
Received By ccole Date 2018-11-30 Time 11:15 Sent To  
Notes
***NONE***

Review Stop P PLUMBING
Rev No 1 Status P Date 2018-12-13 Cont ID  
Sent By jesmith Date 2018-12-13 Time 15:16 Rev Time 0.00
Received By jesmith Date 2018-12-13 Time 15:16 Sent To  
Notes
2018-12-13 15:16:28APPROVED
 PLUMBING PROVISO
  
 1. ALL WORK PER CITY CODES SUBJECT TO FIELD INSPECTOR'S
 APPROVAL
  
 JERALD SMITH
 PLUMBING PLANS EXAMINER
 CITY OF WEST PALM BEACH
 EMAIL [email protected]
 PHONE 561-805-6715
  


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved