Review Stop B BUILDING (STRUCTURAL)
Rev No 3 Status P Date 2018-12-14 Cont ID  
Sent By jgomez Date 2018-12-14 Time 14:26 Rev Time 0.00
Received By jgomez Date 2018-12-14 Time 14:22 Sent To  
Notes
***NONE***

Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status F Date 2018-12-06 Cont ID  
Sent By jgomez Date 2018-12-06 Time 11:25 Rev Time 0.00
Received By jgomez Date 2018-12-06 Time 09:52 Sent To  
Notes
2018-12-06 10:03:47RESIDENTIAL (R3) SECOND BUILDING REVIEW CHECKLIST.
 CODE: FBC 6TH EDITION (2017) AND CITY AMENDMENTS.
  
 ORIGINAL COMMENT:
 1- PROVIDE SHUTTERS COMPLETE INSTALLATION SCHEDULE AS
 REQUIRED BY CITY IMPLEMENTATION STANDARD FOR WIND-BORNE
 DEBRIS IMPACT PROTECTION FOR THE FLORIDA BUILDING CODE.
 SEE CITY SAMPLE. ALL THE COLUMNS NEED TO BE COMPLETED.
 ALTERNATIVELY, YOU MAY PROVIDE COMPLETE INSTALLATION
 SCHEDULE IN ANY OTHER FORMAT AS LONG AS ALL THE
 REQUIRED INFORMATION IS PROVIDED.
 NOTE: IT LOOKS LIKE THE PROPOSED ACCORDION SHUTTERS ARE
 GOING TO BE INSTALLED ON THE SECOND FLOOR. I BELIEVE
 THE SECOND FLOOR OF THESE HOUSES ARE WOOD FRAMED.
 (CONTRACTOR TO VERIFY) TAKE THIS INTO CONSIDERATION
 WHEN COMPLETING THE INSTALLATION SCHEDULE TO AVOID
 CONFLICTS/DELAYS. PROPOSED INSTALLATION WILL BE
 REVIEWED WHEN COMPLETE SHUTTERS INSTALLATION SCHEDULE
 IS PROVIDED.
  
 RESPONSE:
 REVISE SHUTTERS INSTALLATION SCHEDULE SUBMITTED:
 A) THE DESIGN PRESSURES DON'T MATCH DESIGN PRESSURES
 MARKED ON THE ENGINEERED DESIGN PRESSURES SUBMITTED.
 REVISE AS REQUIRED TO MATCH. AND, REVISE ANCHOR SPACING
 (TOP AND BOTTOM) ACCORDINGLY. SEC. R301.1
 FBC-RESIDENTIAL.
 NOTE: COORDINATE WITH ITEM #2 BELOW. BASED ON THE KEY
 PLAN SUBMITTED OPENINGS #1, 2 AND 5 ARE LOCATED IN
 LOCATION ZONE 5. (FIGURE R301.2(7) OF FBC-RESIDENTIAL
 ALL OPENINGS WITHIN 4 FEET OF END OF WALL ARE
 CONSIDERED ZONE 5).
  
 B) GLASS SEPARATION OF 2-3/4" REQUIRES ONE LOCK AND TWO
 LOCKING RODS OR TWO LOCKS. SEE SEPARATION TO GLASS
 REQUIREMENTS ON SHEET 11 OF 20 OF SHUTTER DRAWINGS
 SUBMITTED. CLARIFY IF USING ONE LOCK AND TWO LOCKING
 RODS OR TWO LOCKS ( CONTRACTOR ONLY HIGHLIGHTED THE HV
 LOCK ON SHEET 3 OF 20). SEC. 107.2.1 CITY AMENDMENTS.
  
 C) CLARIFY SHUTTER SPAN DIMENSION SHOWN ON COLUMN SIX
 OF INSTALLATION SCHEDULE SUBMITTED. SEE TYPICAL BLADE
 SHUTTER ELEVATION ON SHEET 5 OF 20 OF SHUTTERS DRAWINGS
 SUBMITTED FOR CORRECT WAY OF DIMENSIONING THE SHUTTER
 SPAN AND REVISE AS REQUIRED. SEC. 107.2.1 CITY
 AMENDMENTS.
  
  
 ORIGINAL COMMENT:
 2- ACCORDING TO KEY PLAN SUBMITTED, IT LOOKS LIKE SOME
 OPENINGS ARE LOCATED IN THE END ZONE #5. USE THE
 CORRESPONDING DESIGN PRESSURES WHEN COMPLETING THE
 INSTALLATION SCHEDULE. SEC. R301.1 FBC-RESIDENTIAL.
  
 RESPONSE:
 COORDINATE WITH ITEM #1(A) ABOVE.
  
 IF YOU HAVE ANY QUESTIONS, PLEASE CONTACT
 JULIO GOMEZ
 COMMERCIAL COMBINATION PLANS EXAMINER
 DEVELOPMENT SERVICES DEPARTMENT
 BUILDING DIVISION
 (561)805-6712
 [email protected]
  

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status F Date 2018-09-25 Cont ID  
Sent By jgomez Date 2018-09-25 Time 14:38 Rev Time 0.00
Received By jgomez Date 2018-09-25 Time 14:06 Sent To  
Notes
2018-09-25 14:52:05RESIDENTIAL (R3) BUILDING REVIEW COMMENTS
 CODE: FBC 6TH EDITION (2017) AND CITY AMENDMENTS.
  
 1- PROVIDE SHUTTERS COMPLETE INSTALLATION SCHEDULE AS
 REQUIRED BY CITY IMPLEMENTATION STANDARD FOR WIND-BORNE
 DEBRIS IMPACT PROTECTION FOR THE FLORIDA BUILDING CODE.
 SEE CITY SAMPLE. ALL THE COLUMNS NEED TO BE COMPLETED.
 ALTERNATIVELY, YOU MAY PROVIDE COMPLETE INSTALLATION
 SCHEDULE IN ANY OTHER FORMAT AS LONG AS ALL THE
 REQUIRED INFORMATION IS PROVIDED.
 NOTE: IT LOOKS LIKE THE PROPOSED ACCORDION SHUTTERS ARE
 GOING TO BE INSTALLED ON THE SECOND FLOOR. I BELIEVE
 THE SECOND FLOOR OF THESE HOUSES ARE WOOD FRAMED. TAKE
 THIS INTO CONSIDERATION WHEN COMPLETING THE
 INSTALLATION SCHEDULE TO AVOID CONFLICTS/DELAYS.
 PROPOSED INSTALLATION WILL BE REVIEWED WHEN COMPLETE
 SHUTTERS INSTALLATION SCHEDULE IS PROVIDED.
  
 2- ACCORDING TO KEY PLAN SUBMITTED, IT LOOKS LIKE SOME
 OPENINGS ARE LOCATED IN THE END ZONE #5. USE THE
 CORRESPONDING DESIGN PRESSURES WHEN COMPLETING THE
 INSTALLATION SCHEDULE. SEC. R301.1 FBC-RESIDENTIAL.
  
 IF YOU HAVE ANY QUESTIONS, PLEASE CONTACT
 JULIO GOMEZ
 COMMERCIAL COMBINATION PLANS EXAMINER
 DEVELOPMENT SERVICES DEPARTMENT
 BUILDING DIVISION
 (561)805-6712
 [email protected]
  

Review Stop I INCOMING/PROCESSING
Rev No 3 Status N Date 2018-12-14 Cont ID  
Sent By jgomez Date 2018-12-14 Time 14:27 Rev Time 0.00
Received By jgomez Date 2018-12-14 Time 14:21 Sent To  
Notes
2018-12-14 14:21:55MET W/ CONTRACTOR TO GO OVER COMMENTS. JG.

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2018-12-06 Cont ID  
Sent By jgomez Date 2018-12-06 Time 11:25 Rev Time 0.00
Received By jgomez Date 2018-11-27 Time 12:34 Sent To I
Notes
2018-11-29 12:34:11RESUB ROUTED TO JGOMEZ

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2018-09-25 Cont ID  
Sent By jgomez Date 2018-09-25 Time 14:52 Rev Time 0.00
Received By jgomez Date 2018-09-21 Time 14:42 Sent To I
Notes
2018-09-24 14:42:25BLDG <5K