Plan Review Details - Permit 18090918
Plan Review Stops For Permit 18090918
Review Stop B BUILDING (STRUCTURAL)
Rev No 3 Status P Date 2018-11-16 Cont ID  
Sent By pvalenti Date 2018-11-16 Time 07:41 Rev Time 0.00
Received By pvalenti Date 2018-11-16 Time 07:41 Sent To  
Notes
2018-11-16 07:53:42PETER E VALENTI
 BUILDING PLANS EXAMINER
 [email protected]
 561-805-6673
  
 FBC = FLORIDA BUILDING CODE, 6TH EDITION (2017)
 FBC B = FBC BUILDING
 FBC EB = FBC EXISTING BUILDING
 FBC A = FBC ACCESSIBILITY
 FBC EC = FBC ENERGY CONSERVATION
 FBC R = FBC RESIDENTIAL
  
 DEMO. PERMIT APPLICATION APPROVED PV
  
 NOTES:
  
 THE PENDING UTILITY RELEASES WERE APPROVED UNDER
 DEMOLITION PERMIT # 06060780.
  
 THE DEMOLITION DEBRIS DISPOSAL FORM AND FEE IS TO BE
 ADDRESSED PRIOR TO PICKING UP PERMIT.

Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status F Date 2018-11-14 Cont ID  
Sent By pvalenti Date 2018-11-14 Time 09:13 Rev Time 0.00
Received By pvalenti Date 2018-11-14 Time 09:13 Sent To  
Notes
2018-11-14 09:48:32****CORRECTIONS****
  
 PETER E. VALENTI
 BUILDING PLANS EXAMINER
 [email protected]
 561-805-6673
  
 PROVIDE EACH OF THE FOLLOWING ITEMS VIA EMAIL AS THEY
 ARE AVAILABLE; SEND TO [email protected], INCLUDE THE
 PERMIT NUMBER IN THE SUBJECT LINE.
  
 PLEASE SEE THE "DEMOLITION PERMIT APPLICATION
 CHECKLIST" WHICH YOU CAN FIND AT THE FOLLOWING WEBSITE:
  
 HTTP://WPB.ORG/DEPARTMENTS/DEVELOPMENT-SERVICES/FORMS/B
 UILDING-PERMIT-FORMS
  
 THE FOLLOWING ITEMS ARE REQUIRED PRIOR TO ISSUANCE OF A
 DEMO PERMIT:
  
 1. UTILITY RELEASE - FLORIDA POWER & LIGHT (ELECTRIC)
 RELEASE OF SERVICE CONFIRMATION
  
 2. UTILITY RELEASE - FLORIDA PUBLIC UTILITIES (GAS)
 RELEASE OF SERVICE CONFIRMATION
  
 3. UTILITY RELEASE - CITY OF WEST PALM BEACH WATER
 DEPARTMENT, REQUEST FOR METER PULL, ON THEIR FORM
 "DEMOLITION APPLICATION"
  
 HTTP://WPB.ORG/DEPARTMENTS/DEVELOPMENT-SERVICES/FORMS/B
 UILDING-PERMIT-FORMS
  
 FAX THE COMPLETED "DEMOLITION APPLICATION" FORM TO
 561-822-2183. AFTER THEY FAX THE RELEASE TO YOU, SEND A
 COPY VIA EMAIL TO [email protected] WITH THE PERMIT
 NUMBER IN THE SUBJECT LINE.
  
 4. COMPLETE THE DEMO DEBRIS FORM AND PAY THE FEES,
 "DEMOLITION DEBRIS DISPOSAL FEE":
  
 HTTP://WPB.ORG/DEPARTMENTS/DEVELOPMENT-SERVICES/FORMS/B
 UILDING-PERMIT-FORMS
  
 AFTER THE FORM IS SENT TO [email protected], THE FEES
 WILL BE ADDED TO YOUR PERMIT. YOU CAN THEN PAY THE FEES
 ONLINE PRIOR TO PERMIT ISSUANCE.
  
  
 NOTES:
  
 IN THE EVENT THAT SOME OF THE ITEMS LISTED ABOVE ARE
 NOT APPLICABLE AT THIS TIME , PLEASE EXPLAIN.
  
 THE SUBMITTED SITE DEMO PLAN (SHEET 3) IS OK PER
 PROVISO REQUIRING ENGINEERING PERMIT FOR SIDEWALK
 REMOVAL
 THE SIDEWALK REMOVAL OUTSIDE OF THE PROPERTY IS IN
 PROGRESS OF PERMIT APPLICATION, AS PER M. GONZALEZ FROM
 ENGINEERING.
  
  
  
  

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status F Date 2018-10-14 Cont ID  
Sent By pvalenti Date 2018-10-14 Time 11:32 Rev Time 0.00
Received By pvalenti Date 2018-10-14 Time 11:32 Sent To  
Notes
2018-10-14 11:35:56****CORRECTIONS****
  
 PETER E VALENTI
 BUILDING PLANS EXAMINER
 [email protected]
 561-805-6673
  
 FBC = FLORIDA BUILDING CODE, 6TH EDITION (2017)
 FBC B = FBC BUILDING
 FBC EB = FBC EXISTING BUILDING
 FBC A = FBC ACCESSIBILITY
 FBC EC = FBC ENERGY CONSERVATION
 FBC R = FBC RESIDENTIAL
  
 PLEASE ADDRESS ENGINEERING/ZONING NOTES AND SUBMIT.

Review Stop ENG ENGINEERING CSD
Rev No 2 Status P Date 2018-11-13 Cont ID  
Sent By Mgonzale Date 2018-11-13 Time   Rev Time 1.00
Received By mgonzale Date 2018-11-13 Time   Sent To B
Notes
2018-11-13 10:09:55PERMIT 18090918 IS INCLUSIVE OF THE PAVING REMOVAL AND
 FOUNDATION FOOTPRINT LAYOUT. TREE DISPOSITION AND TREE
 MITIGATION WILL BE REQUIRED
 FOR THE PILING PHASE.
  
 POLLUTION PREVENTION PLAN MUST BE IN EFFECT AT ALL
 TIMES. ENGINEERING WILL INSPECT THE SITE WITHOUT NOTICE
 A MINIMUM OF THREE TIMES FOR COMPLIANCE.
 OUR DEPARTMENT WILL USE THE FOLLOWING TEMPLATES FOR
 PERFORMING INSPECTIONS AS PART NPDES MS4
 RESPONSABILITIES.
 HTTP://PBCO-NPDES.ORG/WRITTENPROCEDURES.ASP
  
 MANNY GONZALEZ
 SENIOR ENGINEERING PROJECT COORDINATOR
 PUBLIC WORKS DEPARTMENT
 401 CLEMATIS STREET, 4TH FLOOR
 WEST PALM BEACH, FL 33401
 (MAILING ADDRESS: P.O. BOX 3366, ZIP 33402)
 MAIN PHONE: (561) 822-1200
 DIRECT: (561) 494-1085
 FAX: (561) 494-1116
 EMAIL: [email protected]
 HTTP://WWW.WPB.ORG/DEPARTMENTS/ENGINEERING-PUBLIC-WORKS
 /FORMS,-PERMITS-APPLICATIONS
  
  
  

Review Stop ENG ENGINEERING CSD
Rev No 1 Status F Date 2018-10-05 Cont ID  
Sent By Mgonzale Date 2018-10-05 Time   Rev Time 1.00
Received By mgonzale Date 2018-10-05 Time   Sent To B
Notes
2018-10-05 15:09:20CONTACT ENGINEERING DEPT AND PROVIDE THE FOLLOWING:
  
 #1 PROVIDE A DEMOLOTION PLAN, PLAN SHOULD INCLUDE
 DEMOLITION, STORM WATER POLLUTION PREVENTION, AND TREE
 SURVEY. CAPPING OF SERVICES,
 WATER SOURCE (SERVICE) TO BE UTILIZED FOR DEMO. IT
 SHOULD DETAIL TREE PROTECTION AND/OR REMOVAL, GROUND
 COVER, SILT FENCE.
 #2 PROVIDE ENGINEER'S OPINION OF COST FOR RESTORING THE
 DISTURBED AREAS SHOULD THE PROJECT FAIL BEFORE A
 VERTICAL INSPECTION IS PERFORMED.
 #3 ENGINEERING SERVICES EROSION CONTROL & LAND
 STABILIZATION BOND (ORD. 4060-07) FOR 110% OF THE VALUE
 OF THE OPINION OF COST.
 YOU ARE WELSOME TO UTILIZE OUR PERFORMANCE BOND
 DOCUMENT AND COST ESTIMATE DOC AT THE INTERNET ADDRESS
 BELOW.
 HTTP://WPBFL.US/DEPARTMENTS/ENGINEERING-PUBLIC-WORKS/FO
 RMS,-PERMITS-APPLICATIONS.
 #4 BOND WILL BE RETURNED UPON SUCCESSFULLY PASSING THE
 VERTICAL INSPECTION.
 THANK YOU!
  
 MANNY GONZALEZ
 SENIOR ENGINEERING PROJECT COORDINATOR
 PUBLIC WORKS DEPARTMENT
 401 CLEMATIS STREET, 4TH FLOOR
 WEST PALM BEACH, FL 33401
 (MAILING ADDRESS: P.O. BOX 3366, ZIP 33402)
 MAIN PHONE: (561) 822-1200
 DIRECT: (561) 818-1322
 FAX: (561) 494-1116
 EMAIL: [email protected]
 HTTP://WWW.WPB.ORG/DEPARTMENTS/ENGINEERING-PUBLIC-WORKS
 /FORMS,-PERMITS-APPLICATIONS
  
 IMPORTANT MESSAGE: AS OF DECEMBER 20, 2015 THE CITY OF
 WEST PALM BEACH
 CROSS-CONNECTION CONTROL MANUAL HAS BEEN REVISED,
 MAKING KNOWN THAT "ALL BACKFLOW DEVICES MUST BE LEAD
 FREE."
 FOR MORE INFORMATION REFER TO THE LINK BELOW:
 HTTP://WPB.ORG/DEPARTMENTS/PUBLIC-UTILITIES/FORMS-PUBLI
 CATIONS/BACKFLOW-CROSS-CONNECTION-CONTROL-MANUAL
  

Review Stop I INCOMING/PROCESSING
Rev No 3 Status N Date 2018-11-16 Cont ID  
Sent By pvalenti Date 2018-11-16 Time 07:54 Rev Time 0.00
Received By pvalenti Date   Time   Sent To I
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2018-11-14 Cont ID  
Sent By pvalenti Date 2018-11-14 Time 10:16 Rev Time 0.00
Received By pvalenti Date 2018-10-25 Time 13:08 Sent To I
Notes
2018-11-07 15:55:45ROUTED FROM ZONING TO LM 11/8/18
2018-10-26 13:08:31RESUB ROUTED TO ZONING INBOX

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2018-10-14 Cont ID  
Sent By pvalenti Date 2018-10-14 Time 11:36 Rev Time 0.00
Received By pvalenti Date 2018-09-20 Time 12:52 Sent To I
Notes
2018-10-04 14:22:48ROUTED FROM ZONING TO LM 10/3/18
2018-09-21 12:52:51ROUTED TO ZONING INBOX

Review Stop Z ZONING
Rev No 2 Status P Date 2018-11-07 Cont ID  
Sent By elevesqu Date 2018-11-07 Time 15:55 Rev Time 0.00
Received By elevesqu Date 2018-11-07 Time 15:55 Sent To ENG
Notes
***NONE***

Review Stop Z ZONING
Rev No 1 Status F Date 2018-10-04 Cont ID  
Sent By elevesqu Date 2018-10-04 Time 14:18 Rev Time 0.00
Received By elevesqu Date 2018-10-04 Time 14:18 Sent To ENG
Notes
2018-10-04 14:22:31PLEASE MAKE NOTE, THE SUBMITTED BUILDING FOOTPRINT MAY
 NOT MATCH THE LATEST APPROVED SITE PLAN. THE LATES
 APPROVED SITE PLAN IS DATED APRIL 28, 2016. PLEASE
 SUBMIT A SITE PLAN FOR PROPOSAL.
  
 PLEASE ADDRESS ENGINEERING COMMENTS.
  
 LIZ LEVESQUE, 561 822 1426


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved