| 2018-09-28 16:42:51 | 09/28/2018 1ST POOL PLUMBING REVIEW**DENIED** WITH |
| | COMMENTS |
| | |
| | NOTE - A COMPREHENSIVE REVIEW COULD NOT BE DONE AT THIS |
| | TIME AND ADDITIONAL PLAN REVIEW COMMENTS MAY BE |
| | GENERATED UPON THE RE-REVIEW OF SUBMITTED CORRECTIONS. |
| | |
| | 1. SUBMIT MANUFACTURER'S SPECIFICATIONS FOR THE MAIN |
| | DRAIN, PUMP AND HEAT PUMP. WPB AMENDMENTS TO FBC SEC. |
| | 107.2.1. |
| | |
| | 2. SUBMIT SPECIFICATIONS FOR THE CARTRIDGE FILTER. WPB |
| | AMEND. TO FBC SEC. 107.2.1. |
| | |
| | 3. HEAT PUMP POOL HEATERS SHALL HAVE A MINIMUM COP OF |
| | 4.0 WHEN TESTED IN ACCORDANCE WITH AHRI 1160, TABLE 2, |
| | STANDARD RATING CONDITIONS ? LOW AIR TEMPERATURE. A |
| | TEST REPORT FROM AN INDEPENDENT LABORATORY IS REQUIRED |
| | TO VERIFY PROCEDURE COMPLIANCE. 2017 FBC-ENERGY ? SEC. |
| | R 403.10.5. |
| | |
| | 4. SUBMIT TWO LEGIBLE COPIES OF THE POOL PUMP CURVE. |
| | IDENTIFY ON THE PUMP CURVE WHICH CURVE KEY IS SPECIFIC |
| | TO THE PUMP BEING INSTALLED ON THIS POOL. THIS IS |
| | NEEDED TO CONFIRM THE MAXIMUM SYSTEM FLOW FROM THE TDH |
| | CALCULATIONS. WPB AMENDMENTS TO THE FBC SEC. 107.2.1 |
| | INFORMATION ON CONSTRUCTION DOCUMENTS. (USING THE |
| | MANUFACTURER?S PERFORMANCE CURVE FOR THE EXISTING PUMP, |
| | FIND THE FLOW THAT CORRESPONDS TO THE TOTAL DYNAMIC |
| | HEAD. THIS IS THE ACTUAL FLOW AT WHICH THE PUMP IS |
| | CURRENTLY OPERATING, WHICH MAY OR MAY NOT MEET TURNOVER |
| | RATE AND WATER VELOCITY REQUIREMENTS. VERIFY THE ACTUAL |
| | FLOW RATE IS BETWEEN THE MINIMUM FLOW BASED ON THE |
| | TURNOVER RATE AND THE MAXIMUM FLOW BASED ON THE WATER |
| | VELOCITY.) |
| | |
| | 5. THE DYNAMIC HEAD CALCULATIONS FOR THE MAXIMUM SYSTEM |
| | FLOW DOES NOT SHOW ALL FRICTION LOSS THROUGH ALL |
| | COMPONENTS, CHLORINATORS, HEATER, ETC., ON THE HAYWARD |
| | CALCULATOR CHART. ASSUME THE TOTAL FRICTION LOSS WOULD |
| | INCLUDE THE PIPE, FITTINGS (90-DEGREE FITTINGS, 45'S, |
| | TEES) AND ALSO VALVES AND FILTER. WPB AMENDMENTS TO THE |
| | FBC SEC. 107.2.1 INFORMATION ON CONSTRUCTION DOCUMENTS. |
| | |
| | 6. THE SUCTION OUTLET SAFETY COMPLIANCE THAT THE SYSTEM |
| | FLOW RATE HAS BEEN DETERMINED BY THE MAXIMUM FLOW FROM |
| | THE PUMP CURVE. THIS METHOD IS NO LONGER PERMITTED BY |
| | APSP/ANSI-7 2013 EDITION SEC. 4.4.9. TOTAL DYNAMIC HEAD |
| | CALCULATIONS ARE REQUIRED. |
| | |
| | 7. BACKFLOW PREVENTER REQUIRED PER THE CITY OF WEST |
| | PALM BEACH ORD #2853-95. A PERMIT REQUIRED BY A |
| | LICENSED CONTRACTOR AND MUST BE CERTIFIED BY UTILITIES |
| | PRIOR TO FINAL INSPECTION. A DUAL CHECK VALVE MAY BE |
| | USED IF NO POOL FILL IS INSTALLED AT THE METER AND |
| | INSTALLED BY UTILITIES WHICH DO NOT REQUIRE A PERMIT SO |
| | PLEASE CONTACT CITY OF WPB UTILITIES AT 561-822-2240 |
| | FOR FURTHER DIRECTIONS. |
| | |
| | WHEN RESUBMITTING PLANS PLEASE INDICATE THE REVISION & |
| | REMOVE ANY VOIDED SHEETS & REPLACE ANY PAGES AS |
| | NECESSARY. A TRANSMITTAL LETTER LISTING THE ORIGINAL |
| | REVIEW COMMENT NUMBER, WITH A DESCRIPTION OF THE |
| | REVISION, MADE, IDENTIFYING THE SHEET OR SPECIFICATION |
| | PAGE WHERE THE CHANGES CAN BE FOUND WILL HELP TO |
| | EXPEDITE YOUR PERMIT. THANK YOU FOR YOUR ANTICIPATED |
| | COOPERATION. |
| | |
| | LUIS A. CRESPO |
| | PLUMBING INSPECTOR / |
| | PLUMBING PLAN REVIEW |
| | AVAILABLE FROM 1:00 PM TO 4:00 PM |
| | [email protected] |
| | 561-805-6720 |
| | |