| 2018-09-05 11:03:45 | PERMIT #18081451 |
| | FIRE REVIEW COMMENTS |
| | |
| | FAILED COMMENTS: |
| | |
| | 1) CLARIFICATION NEEDED ON WHAT IS TO BE ANTICIPATED AS |
| | PART OF THE PHASING PLANS. PLEASE PROVIDE A NARRATIVE |
| | EXPLANATION OF PHASING PLAN. PLEASE INCLUDE, AT A |
| | MINIMUM: |
| | A) WHAT, IF ANY, PART OF THE STORE WILL BE OPEN TO THE |
| | PUBLIC AND/OR STORE EMPLOYEES DURING EACH PHASE. |
| | B) HOW WILL CUSTOMERS AND STORE EMPLOYEES BE KEPT OUT |
| | OF CONSTRUCTION AREAS DURING PHASING WORK. |
| | C) ALL REQUIRED FIRE AND LIFE SAFETY SYSTEMS SHALL BE |
| | FULLY OPERATIONAL PRIOR TO OCCUPANCY. |
| | D) WHAT ARE THE ANTICIPATED PHASING DATES/ TIME FRAMES? |
| | E) PHASE 4 APPEARS TO APPLY TO THE MAIN POINT OF ENTRY |
| | AND EGRESS, WILL THIS ACCESS POINT BE OPEN TO THE |
| | PUBLIC DURING CONSTRUCTION OF PHASE 4? IF SO, HOW WILL |
| | CUSTOMERS BE PROTECTED FROM CONSTRUCTION WORK? |
| | F) THE RESTROOMS ARE LOCATED IN PHASE 3, WILL THEY BE |
| | ACCESSIBLE DURING CONSTRUCTION OF THIS PHASE? IF SO, |
| | WHAT KEEPS PATRONS/EMPLOYEES FROM ACCESSING THE |
| | CONSTRUCTION AREA? |
| | |
| | 2) PROVIDE DRAWING NOTE INDICATING, ?FIRE PROTECTION |
| | SYSTEMS SHALL REMAIN ACTIVE DURING DEMOLITION AND |
| | RENOVATION ACTIVITIES. IN THE EVENT A FIRE PROTECTION |
| | SYSTEM IS OUT OF SERVICE FOR MORE THAN 4-HOURS IN A |
| | 24-HOUR PERIOD, THE BUILDING SHALL BE PLACED UNDER A |
| | FIRE WATCH. ALL FIRE WATCH REQUESTS MUST BE SUBMITTED |
| | BY EMAIL ([email protected]) OR IN WRITING (FAX: |
| | 561-804-4774) AND APPROVED BY THE OFFICE OF THE FIRE |
| | MARSHAL LOCATED AT 500 NORTH DIXIE HIGHWAY.? |
| | |
| | SUE ELLEN CALDERON |
| | ASSISTANT FIRE MARSHAL |
| | [email protected] |
| | |