Plan Review Details - Permit 18080815
Plan Review Stops For Permit 18080815
Review Stop B BUILDING (STRUCTURAL)
Rev No 3 Status P Date 2018-10-27 Cont ID  
Sent By pvalenti Date 2018-10-27 Time 09:20 Rev Time 0.00
Received By pvalenti Date 2018-10-27 Time 09:20 Sent To  
Notes
***NONE***

Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status P Date 2018-09-12 Cont ID  
Sent By pvalenti Date 2018-09-12 Time 08:38 Rev Time 0.00
Received By pvalenti Date   Time   Sent To I
Notes
2018-09-12 08:43:36PETER E VALENTI
 BUILDING PLANS EXAMINER
 [email protected]
 561-805-6673
  
 FBC = FLORIDA BUILDING CODE, 6TH EDITION (2017)
 FBC B = FBC BUILDING
 FBC EB = FBC EXISTING BUILDING
 FBC A = FBC ACCESSIBILITY
 FBC EC = FBC ENERGY CONSERVATION
 FBC R = FBC RESIDENTIAL
  
 NOTES: ALL WORK, INCLUDING CONNECTIONS, WILL BE SUBJECT
 TO VERIFICATION BY FIELD INSPECTOR.

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status F Date 2018-09-01 Cont ID  
Sent By hmtribou Date 2018-08-28 Time 11:41 Rev Time  
Received By pvalenti Date   Time   Sent To E
Notes
2018-09-01 17:32:43****CORRECTIONS****
  
 PETER E VALENTI
 BUILDING PLANS EXAMINER
 [email protected]
 561-805-6673
  
 FBC = FLORIDA BUILDING CODE, 6TH EDITION (2017)
 FBC B = FBC BUILDING
 FBC EB = FBC EXISTING BUILDING
 FBC A = FBC ACCESSIBILITY
 FBC EC = FBC ENERGY CONSERVATION
 FBC R = FBC RESIDENTIAL
  
  
 FBC 107.
  
 1. PLEASE CLARIFY THE LOCATION OF PROPOSED SOLAR PANEL
 SYSTEM. THE PLANS APPEAR TO SHOW CONNECTIONS TO AN
 EXISTING ROOF DECK AND/OR A NEW ALUMINUM FRAMING SYSTEM
 DIRECT TO GRADE.
  
  
  
 AWS D1.1 CLAUSE 3.1 / AWS D1.1 CLAUSE 4.15
  
 2. IF FIELD WELDING IS GOING TO TAKE PLACE, THE
 FOLLOWING SPECIFICATIONS WILL BE REQUIRED:
  
 A. A WELD PROCEDURE SPECIFICATION; THIS SPECIFICATION
 IS REQUIRED TO SHOW THE ESSENTIAL VARIABLES USED DURING
 THE WELDING PROCEDURE AS PER THE REQUIREMENTS OF AWS
 D1.1.
 B. A WELDER PERFORMANCE QUALIFICATION TEST RECORD AS
 PER THE REQUIREMENTS OF AWS D1.1.

Review Stop E ELECTRICAL
Rev No 1 Status P Date 2018-09-04 Cont ID  
Sent By jleahy Date 2018-08-24 Time 14:10 Rev Time 0.00
Received By jleahy Date 2018-08-24 Time 14:10 Sent To Z
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 3 Status N Date 2018-10-27 Cont ID  
Sent By pvalenti Date 2018-10-27 Time 09:20 Rev Time 0.00
Received By pvalenti Date 2018-10-24 Time 14:55 Sent To I
Notes
2018-10-25 14:55:23RESUB ROUTED TO ZONING INBOX

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2018-09-12 Cont ID  
Sent By pvalenti Date 2018-09-12 Time 08:44 Rev Time 0.00
Received By pvalenti Date 2018-09-04 Time 13:24 Sent To I
Notes
2018-09-05 13:24:42RESUB ROUTED TO ZONING INBOX

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2018-09-04 Cont ID  
Sent By shill Date 2018-09-04 Time 09:45 Rev Time  
Received By jleahy Date 2018-08-15 Time 13:08 Sent To  
Notes
2018-09-01 17:48:299/1 TO JL DESK
  
  
2018-08-16 13:09:03ROUTED TO JLEAHY

Review Stop Z ZONING
Rev No 3 Status P Date 2018-10-26 Cont ID  
Sent By hmtribou Date 2018-10-26 Time 09:46 Rev Time 0.00
Received By hmtribou Date 2018-10-26 Time 09:46 Sent To B
Notes
***NONE***

Review Stop Z ZONING
Rev No 2 Status P Date 2018-09-06 Cont ID  
Sent By hmtribou Date 2018-09-06 Time 13:23 Rev Time 0.00
Received By hmtribou Date 2018-09-06 Time 13:23 Sent To B
Notes
***NONE***

Review Stop Z ZONING
Rev No 1 Status F Date 2018-08-28 Cont ID  
Sent By jleahy Date 2018-09-04 Time 09:45 Rev Time 0.00
Received By hmtribou Date 2018-08-28 Time 11:41 Sent To B
Notes
2018-08-28 10:56:32LOCATION OF NEW STRUCTURE MUST BE INCLUDED ON SITE PLAN
 TO MEET SETBACK REQUIREMENT AND IF NEEDED SEPERATION
 REQUIREMRNTS.