Plan Review Details - Permit 18080351
Plan Review Stops For Permit 18080351
Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status P Date 2018-08-28 Cont ID  
Sent By rmcdouga Date 2018-08-28 Time 18:58 Rev Time 0.00
Received By rmcdouga Date 2018-08-28 Time 18:50 Sent To E
Notes
***NONE***

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status F Date 2018-08-15 Cont ID  
Sent By rmcdouga Date 2018-08-15 Time 07:51 Rev Time 0.00
Received By rmcdouga Date 2018-08-15 Time 07:41 Sent To I
Notes
2018-08-15 07:51:45PLAN
 REVIEW COMMENTS
  
 1ST REVIEW: FBC SIXTH EDITION (2017)
 ROBERT MCDOUGAL, CBO
 COMMERCIAL COMBINATION PLANS EXAMINER
 (561) 805-6714
 [email protected]
  
 DENIED BY BUILDING
 PLEASE ADDRESS THE ITEMS NOTED BELOW:
  
 1) THE PLANS HAVE SEVERAL REFERENCES TO THE FBC FIFTH
 EDITION (2014). THE FBC SIXTH EDITION (2017) WENT INTO
 EFFECT ON JANUARY 1, 2018. ALL NEW PERMITS APPLIED FOR
 ON OR AFTER THAT DATE ARE REQUIRED TO COMPLY WITH AND
 REFERENCE THE FBC SIXTH EDITION (2017).
 FS CHAPTER 553
  

Review Stop E ELECTRICAL
Rev No 2 Status P Date 2018-08-30 Cont ID  
Sent By jleahy Date 2018-08-30 Time 17:17 Rev Time 0.00
Received By jleahy Date 2018-08-30 Time 17:17 Sent To P
Notes
***NONE***

Review Stop E ELECTRICAL
Rev No 1 Status P Date 2018-08-11 Cont ID  
Sent By jleahy Date 2018-08-11 Time 12:10 Rev Time 0.00
Received By jleahy Date 2018-08-11 Time 12:10 Sent To  
Notes
***NONE***

Review Stop G GAS REVIEW
Rev No 1 Status N Date 2018-08-13 Cont ID  
Sent By lcrespo Date 2018-08-13 Time 18:17 Rev Time 0.00
Received By lcrespo Date 2018-08-13 Time 18:17 Sent To  
Notes
2018-08-13 18:17:30HEATER IS ELECTRIC TYPE

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2018-08-31 Cont ID  
Sent By lcrespo Date 2018-08-31 Time 16:23 Rev Time 0.00
Received By lcrespo Date 2018-08-21 Time 14:19 Sent To  
Notes
2018-08-22 14:19:16RESUB ROUTED TO ZONING INBOX

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2018-08-15 Cont ID  
Sent By rmcdouga Date 2018-08-15 Time 07:52 Rev Time 0.00
Received By rmcdouga Date 2018-08-07 Time 10:58 Sent To  
Notes
2018-08-08 10:58:39ROUTED TO ZONING INBOX

Review Stop P PLUMBING
Rev No 2 Status P Date 2018-08-31 Cont ID  
Sent By lcrespo Date 2018-08-31 Time 16:23 Rev Time 0.00
Received By lcrespo Date 2018-08-31 Time 16:23 Sent To  
Notes
2018-08-31 16:24:2008/31/18 REVIEWED FOR CODE COMPLIANCE (PLUMBING/POOL)
  
 BY REVIEWING THE PLANS / SPECIFICATIONS FOR CODE
 COMPLIANCE DOES NOT RELIEVE THE OWNER, DESIGN
 PROFESSIONAL, CONTRACTORS OR THEIR REPRESENTATIVES FROM
 THE RESPONSIBILITY TO COMPLY WITH ALL LOCAL, STATE AND
 NATIONAL CODES AND STANDARDS IN EFFECT AT THE TIME OF
 PERMIT ISSUANCE. OUR REVIEW IS NOT A CHECK OF EVERY
 ITEM AND DOES NOT PREVENT THIS DEPARTMENT FROM
 REQUIRING CORRECTIONS DURING CONSTRUCTION. ANY CHANGES
 / ALTERATIONS TO APPROVE PLANS SHALL BE APPROVED TO
 AVOID VOIDING OF THE PERMIT.
  
 LUIS A. CRESPO
 PLUMBING PLAN EXAMINER
  

Review Stop P PLUMBING
Rev No 1 Status F Date 2018-08-13 Cont ID  
Sent By lcrespo Date 2018-08-13 Time 18:17 Rev Time 0.00
Received By lcrespo Date 2018-08-13 Time 18:17 Sent To  
Notes
2018-08-13 18:18:2108/13/2018 1ST PLUMBING/POOL REVIEW **DENIED** WITH
 COMMENTS
  
 NOTE - A COMPREHENSIVE REVIEW COULD NOT BE DONE AT THIS
 TIME AND ADDITIONAL PLAN REVIEW COMMENTS MAY BE
 GENERATED UPON THE RE-REVIEW OF SUBMITTED CORRECTIONS.
  
 1. SUBMIT TOTAL DYNAMIC HEAD CALCULATIONS FOR THE
 MAXIMUM SYSTEM FLOW. THE MAXIMUM FLOW OF THE PUMP FROM
 ITS PUMP CURVE IS NO LONGER ALLOWED TO BE USED IN
 DETERMINING THE MAXIMUM SYSTEM FLOW RATE PER
 ANSI/APSP/ICC 7 - 2013 SECS. 4.4.9, 4.4.9.1. THE 2013
 EDITION ADDRESSES FLOW RATE IN GALLONS PER MINUTE
 (GPM). IT REQUIRES THAT MAXIMUM SYSTEM FLOW RATE DOES
 NOT EXCEED THE LISTED MAXIMUM FLOW RATE OF THE SUCTION
 OUTLET FITTING ASSEMBLY (DRAIN COVER).THE TDH
 CALCULATIONS MUST INCLUDE ALL OF THE SYSTEM COMPONENTS
 IN THE PIPING SYSTEM INCLUDING THE FILTER.
  
 WHEN RESUBMITTING PLANS PLEASE INDICATE THE REVISION &
 REMOVE ANY VOIDED SHEETS & REPLACE ANY PAGES AS
 NECESSARY. A TRANSMITTAL LETTER LISTING THE ORIGINAL
 REVIEW COMMENT NUMBER, WITH A DESCRIPTION OF THE
 REVISION, MADE, IDENTIFYING THE SHEET OR SPECIFICATION
 PAGE WHERE THE CHANGES CAN BE FOUND WILL HELP TO
 EXPEDITE YOUR PERMIT. THANK YOU FOR YOUR ANTICIPATED
 COOPERATION.
  
 LUIS A. CRESPO
 PLUMBING INSPECTOR /
 PLUMBING PLAN REVIEW
 AVAILABLE FROM 1:00 PM TO 4:00 PM
 [email protected]
 561-805-6720
  

Review Stop Z ZONING
Rev No 2 Status P Date 2018-08-28 Cont ID  
Sent By mcruz Date 2018-08-28 Time 08:49 Rev Time 0.00
Received By mcruz Date 2018-08-28 Time 08:46 Sent To E
Notes
***NONE***

Review Stop Z ZONING
Rev No 1 Status P Date 2018-08-10 Cont ID  
Sent By mcruz Date 2018-08-10 Time 15:16 Rev Time 0.00
Received By mcruz Date 2018-08-10 Time 15:13 Sent To B
Notes
***NONE***