Plan Review Details - Permit 18080036
Plan Review Stops For Permit 18080036
Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status F Date 2018-09-04 Cont ID  
Sent By rmcdouga Date 2018-09-04 Time 16:34 Rev Time 0.00
Received By rmcdouga Date 2018-08-31 Time 15:24 Sent To  
Notes
2018-09-04 16:42:32CALLED THE CONTRACTOR TO ASK A QUESTION ABOUT THE
 SUBMITTAL AND SPOKE WITH THE QUALIFIER, KIM ABREU. SHE
 INFORMED ME THAT THE OWNER HAD DECIDED NOT TO DO THE
 WORK. THEREFORE, THE CONTRACTOR WISHES TO CANCEL THE
 PERMIT APPLICATION. I INFORMED THE CONTRACTOR TO SUBMIT
 A LETTER REQUESTING THE PERMIT APPLICATION TO BE
 CANCELED.

Review Stop E ELECTRICAL
Rev No 1 Status P Date 2018-08-21 Cont ID  
Sent By jpearson Date 2018-08-21 Time 12:56 Rev Time 0.00
Received By jpearson Date 2018-08-21 Time 12:56 Sent To  
Notes
***NONE***

Review Stop FIRE FIRE DEPARTMENT
Rev No 1 Status P Date 2018-08-06 Cont ID  
Sent By scaldero Date 2018-08-06 Time 11:51 Rev Time 0.00
Received By scaldero Date 2018-08-06 Time 11:48 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2018-09-04 Cont ID  
Sent By rmcdouga Date 2018-09-04 Time 16:34 Rev Time 0.00
Received By rmcdouga Date 2018-08-01 Time 10:41 Sent To  
Notes
2018-08-03 10:41:27B19

Review Stop P PLUMBING
Rev No 1 Status N Date 2018-08-30 Cont ID  
Sent By gjohnson Date 2018-08-30 Time 16:40 Rev Time 0.00
Received By gjohnson Date 2018-08-30 Time 11:43 Sent To  
Notes
2018-08-30 16:41:46NO PLUMBING WORK SHOWN ON THE PLAN SEPARATE PLAN AND
 PERMIT FOR ANY PLUMBING WORK DONE.
  
 GEORGE JOHNSON
 PLUMBING PLANS EXAMINER
 CITY OF WEST PALM BEACH
  561-805-6711
 [email protected]
  


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved