| Plan Review Stops For Permit 18070626 |
| Review Stop |
B |
BUILDING (STRUCTURAL) |
| Rev No |
1 |
Status |
P |
Date |
2018-07-17 |
|
|
Cont ID |
|
| Sent By |
tmoore |
Date |
2018-07-17 |
Time |
13:47 |
Rev Time |
0.00 |
| Received By |
tmoore |
Date |
2018-07-17 |
Time |
13:43 |
Sent To |
ENG |
|
| Notes |
| 2018-07-17 13:47:13 | HAVE ALL NEEDED UTILITY RELEASES. ONLY NEED; | | | | | | 1) ENGINEERING AND HISTORIC'S REVIEW COMMENTS. | | | | | | 2) DEBRIS DISPOSAL FEE PAID. THIS CAN BE DONE AT PERMIT | | | PICK-UP. | | | | | | 3) COPY OF N.O.C. INCLUDED. THIS CAN BE INCLUDED AT | | | PERMIT PICKUP. | | | | | | MOVING THE APPLICATION ON TO ENGINEERING DEPARTMENT FOR | | | THEIR PLAN REVIEW. | | | | | | TOM 561-805-6669 |
|
|
| Review Stop |
ENG |
ENGINEERING CSD |
| Rev No |
1 |
Status |
P |
Date |
2018-07-18 |
|
|
Cont ID |
|
| Sent By |
hhall |
Date |
2018-07-18 |
Time |
13:23 |
Rev Time |
0.00 |
| Received By |
hhall |
Date |
2018-07-18 |
Time |
13:23 |
Sent To |
HIST |
|
| Notes |
|
|
| Review Stop |
HIST |
HISTORICAL |
| Rev No |
1 |
Status |
P |
Date |
2018-07-19 |
|
|
Cont ID |
|
| Sent By |
fmittner |
Date |
2018-07-19 |
Time |
10:15 |
Rev Time |
0.00 |
| Received By |
fmittner |
Date |
2018-07-19 |
Time |
10:15 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
1 |
Status |
N |
Date |
2018-07-19 |
|
|
Cont ID |
|
| Sent By |
lmarchan |
Date |
2018-07-19 |
Time |
11:58 |
Rev Time |
0.00 |
| Received By |
lmarchan |
Date |
2018-07-13 |
Time |
14:49 |
Sent To |
|
|
| Notes |
| 2018-07-16 14:49:51 | ROUTED TO TMOORE'S DESK |
|
|
|