| 2018-06-29 14:52:10 | 06/29/2018 1ST PLUMBING/GAS REVIEW **DENIED** WITH |
| | COMMENTS. |
| | |
| | NOTE - A COMPREHENSIVE REVIEW COULD NOT BE DONE AT THIS |
| | TIME AND ADDITIONAL PLAN REVIEW COMMENTS MAY BE |
| | GENERATED UPON THE RE-REVIEW OF SUBMITTED CORRECTIONS. |
| | |
| | 1. SUBMIT MANUFACTURES SPECIFICATIONS FOR THE GENERATOR |
| | AND MANUFACTURER'S SPECIFICATIONS FOR THE GENERATOR |
| | SHALL BE ONSITE FOR FINAL GAS INSPECTION. THE GENERATOR |
| | SHALL BE LISTED AND APPROVED. NFPA 58 SEC. 5.20.1. THE |
| | GENERATOR SHALL MEET THE REQUIREMENTS OF UL 2200. 2017 |
| | FBC FUEL GAS SEC.305.1. |
| | 2. IS THE EXISTING STEAM GENERATOR THE ONLY APPLIANCE |
| | ON THIS SYSTEM? WPB AMENDMENTS TO FBC SEC.107.2.1. |
| | INFORMATION ON CONSTRUCTION DOCUMENTS. |
| | 3. A SET OF PLANS HAS BEEN SUBMITTED THAT IS DRAWN IN |
| | PENCIL. PLANS DONE IN PENCIL ARE UNACCEPTABLE AS THE |
| | DRAWING CAN BE MODIFIED/CHANGED. I HAVE VOIDED IT AND |
| | MADE A COPY AND PUT IT WITH THE OTHER SET. WPB |
| | AMENDMENTS TO THE FBC SEC. 107.2.1.4 QUALITY OF |
| | BUILDING PLANS. |
| | 4. SUBMIT MANUFACTURER?S SPECIFICATIONS FOR THE |
| | PRESSURE REGULATORS. REGULATORS INSTALLED ON THE |
| | EXTERIOR OF THE BUILDING SHALL BE APPROVED FOR OUTDOOR |
| | INSTALLATION. IF INSIDE THE GENERATOR PLEASE CLARIFY. |
| | 2017 FBC FUEL GAS SEC.410.1. |
| | 5. SUBMIT TWO COPIES OF THE SIZING TABLE AFTER PE THAT |
| | IS USED IN THE DESIGN FOR THE GAS SYSTEM OR PLACE A |
| | NOTE ON BOTH SETS OF PLANS LISTING THE SIZING TABLES |
| | FROM GAS CODES OR ANOTHER STANDARD THAT WERE USED IN |
| | THE DESIGN OF THIS SYSTEM, 2017 FBC FUEL GAS SEC. |
| | 402.3. |
| | 6. SHOW SHUTOFF VALVE SHALL BE INSTALLED IMMEDIATELY |
| | AHEAD OF EACH MP REGULATOR AND GENERATOR, PLEASE SHOW |
| | ON LAYOUT DESIGN, 2017 FBC FUEL GAS SEC. 409.4. |
| | 7. IS THE NEW GENERATOR GOING TO THE EXISTING LOCATION |
| | AND WILL IT COMPLY WITH NFPA 37, SECTION 4.1.4, ENGINES |
| | LOCATED OUTDOORS OR MANUFACTURES SPECIFICATION, PLEASE |
| | SHOW ON DRAWINGS IF APPLICABLE? |
| | 8. THE IS AN APPLICATION FOR A 75 KW AND THE PLANS LIST |
| | AN 80 KW, I ALSO SAW A TOWER GENERATOR UNDER THIS |
| | ADDRESS, PLEASE CLARIFY. WPB AMENDMENTS TO THE FBC SEC. |
| | 107.2.1 INFORMATION ON CONSTRUCTION DOCUMENTS. |
| | |
| | LUIS A. CRESPO |
| | PLUMBING INSPECTOR / |
| | PLUMBING PLAN REVIEW |
| | AVAILABLE FROM 1:00 PM TO 4:00 PM |
| | [email protected] |
| | 561-805-6720 |
| | |