Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2018-07-11 Cont ID  
Sent By thunt Date 2018-07-11 Time 14:48 Rev Time 0.00
Received By thunt Date 2018-07-03 Time 15:33 Sent To  
Notes
2018-07-05 15:33:53RESUB ROUTED TO THUNT

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2018-06-27 Cont ID  
Sent By thunt Date 2018-06-27 Time 19:24 Rev Time 0.00
Received By thunt Date 2018-06-15 Time 13:48 Sent To I
Notes
2018-06-18 13:48:42ROUTED TO PLUMBING INBOX

Review Stop P PLUMBING
Rev No 2 Status P Date 2018-07-11 Cont ID  
Sent By thunt Date 2018-07-11 Time 14:47 Rev Time 0.00
Received By thunt Date 2018-07-11 Time 14:47 Sent To  
Notes
***NONE***

Review Stop P PLUMBING
Rev No 1 Status F Date 2018-06-27 Cont ID  
Sent By thunt Date 2018-06-27 Time 19:19 Rev Time 0.00
Received By thunt Date 2018-06-27 Time 19:19 Sent To  
Notes
2018-06-27 19:24:2306/27/2018 1ST PLUMBING REVIEW**DENIED**
  
 1) VALUE OF SCOPE OF WORK APPEARS TOO LOW. PROVIDE A
 SIGNED BONA FIDE CONTRACT.109.3 BUILDING PERMIT
 VALUATIONS. IF, IN THE OPINION OF THE BUILDING
 OFFICIAL, THE CLAIMED VALUATION OF
 BUILDING, ALTERATION, STRUCTURE, ELECTRICAL, GAS,
 MECHANICAL OR PLUMBING SYSTEMS APPEARS TO BE
 UNDERESTIMATED ON THE APPLICATION, THE PERMIT SHALL BE
 DENIED, UNLESS THE APPLICANT CAN SHOW
 DETAILED, QUANTITY ESTIMATES, AND/OR BONA FIDE SIGNED
 CONTRACTS (EXCLUDING LAND VALUE) TO MEET THE
 APPROVAL OF THE BUILDING OFFICIAL. FOR PERMITTING
 PURPOSES, VALUATION OF BUILDINGS AND SYSTEMS SHALL
 BE TOTAL REPLACEMENT VALUE TO INCLUDE STRUCTURAL,
 ELECTRIC, PLUMBING, MECHANICAL, INTERIOR FINISH,
 RELATIVE SITE WORK, ARCHITECTURAL AND DESIGN FEES,
 MARKETING COSTS, OVERHEAD AND PROFIT; EXCLUDING
 ONLY LAND VALUE. VALUATION REFERENCES MAY INCLUDE THE
 LATEST PUBLISHED DATA OF NATIONAL CONSTRUCTION
 COST ANALYSIS SERVICES (MARSHALL-SWIFT, MEANS, ETC.),
 AS PUBLISHED BY INTERNATIONAL CODE CONGRESS.
 FINAL BUILDING PERMIT VALUATION SHALL BE SET BY THE
 BUILDING OFFICIAL.
  
 2) NEARLY ALL SHEETS REFER TO CONNECTING TO AN EXISTING
 MAIN LINE. WHERE DOES THE SOURCE OF THIS WATER COME
 FROM? FBC 107.2.1
  
 3) SHOW BOTH PIPE SIZES AND SLEEVE SIZES ON PLAN. FBC
 107.2.5 MINIMUM PLAN REVIEW CRITERIA
  
 4) ADD NOTE THAT THE POINT OF CONNECTION ONTO THE CITY
 WATER SUPPLY SYSTEM WILL REQUIRE A MIN RPZ BACKFLOW
 DEVICE WITH A SEPERATE PLUMBING PERMIT BY A LICENSED
 PLUMBING CONTRACTOR. FBC 107.2.1
  
  
 TIM HUNT
 PLUMBING INSPECTOR / PLUMBING PLAN REVIEWER
 CITY OF WEST PALM BEACH DEVELOPMENT SERVICES DEPARTMENT
 BUILDING DIVISION
 561-805-6695
 [email protected]
  


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved