Plan Review Details - Permit 18050056
| Plan Review Stops For Permit 18050056 |
| Review Stop |
B |
BUILDING (STRUCTURAL) |
| Rev No |
5 |
Status |
P |
Date |
2019-06-11 |
|
|
Cont ID |
|
| Sent By |
cthroop |
Date |
2019-06-11 |
Time |
08:36 |
Rev Time |
0.00 |
| Received By |
cthroop |
Date |
2019-06-11 |
Time |
08:36 |
Sent To |
|
|
| Notes |
| 2019-06-11 08:36:58 | REVISIONS TO PLAN PAGES A201 & A208. CT | | | |
|
|
| Review Stop |
B |
BUILDING (STRUCTURAL) |
| Rev No |
4 |
Status |
P |
Date |
2019-06-05 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2019-06-05 |
Time |
15:43 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2019-06-04 |
Time |
16:12 |
Sent To |
|
|
| Notes |
| 2019-06-05 15:43:00 | BUILDING PROVISO | | | APPROVED WITH THE FOLLOWING EXCEPTIONS: | | | | | | 1) SUBMIT REVISED LIFE SAFETY PLANS THAT SHOW THE BATH | | | EXHAUST CHASES, THE DRYER EXHAUST CHASE AND THE | | | REFRIGERANT LINE CHASE AS TWO HOUR FIRE RATED SHAFTS | | | PER 713.4. | | | | | | 2) DEFERRED SUBMITTALS. FBC 107.3.4.1 SUBMIT THREE SETS | | | OF PRODUCT APPROVALS FOR THOSE PRODUCTS WHICH ARE | | | REGULATED BY FAC 61G20-3.001 PER FLORIDA STATUTE | | | 553.842 (5) THAT HAVE BEEN REVIEWED AND APPROVED IN | | | WRITING BY THE DESIGNER OF RECORD. PROVIDE TWO COMPLETE | | | PRODUCT APPROVALS WITH FL OR NOA NUMBERS INCLUDING | | | INSTALLATION INSTRUCTIONS AND MAXIMUM DESIGN PRESSURES | | | FOR EACH OF THE DIFFERENT ROOFING MATERIALS, WINDOW | | | (GLASS TYPES), STRUCTURAL MULLIONS, EXTERIOR DOORS, | | | EXTERIOR LOUVERS, AC STANDS, ROOF VENTALATORS AND ROOF | | | HATCHES. | | | | | | 3) DEFERRED SUBMITTALS. FBC 107.3.4 SUBMIT THREE SETS | | | OF DOCUMENTS FROM DELEGATE ENGINEERS THAT HAVE BEEN | | | REVIEWED AND APPROVED IN WRITING BY THE DESIGNER OF | | | RECORD FOR THE GLASS GUARDS, THE METAL GUARDS AND | | | HANDRAILS. | | | | | | 4) THIS PROJECT IS LOCATED IN A SPECIAL FLOOD HAZARD | | | AREA. IN ADDITION TO THE PRE-CONSTRUCTION ELEVATION | | | CERTIFICATE, YOU ARE REQUIRED TO SUBMIT A CONSTRUCTION | | | IN PROGRESS ELEVATION CERTIFICATE WHEN THE GROUND FLOOR | | | SLAB IS TO BE POURED AND A FINAL ELEVATION CERTIFICATE | | | WHEN THE BUILDING IS COMPLETE AND ALL OF THE EQUIPMENT | | | IS IN PLACE. YOU WILL NOT BE ABLE TO GET A CERTIFICATE | | | OF OCCUPANCY UNTIL THE FINAL ELEVATION CERTIFICATE HAS | | | BEEN SUBMITTED AND APPROVED BY THIS OFFICE. |
|
|
| Review Stop |
B |
BUILDING (STRUCTURAL) |
| Rev No |
3 |
Status |
F |
Date |
2019-05-13 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2019-05-13 |
Time |
18:55 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2019-05-08 |
Time |
07:25 |
Sent To |
|
|
| Notes |
| 2019-05-13 11:10:59 | PLAN | | | REVIEW COMMENTS | | | | | | 3RD REVIEW: FBC FIFTH EDITION (2014) | | | ROBERT MCDOUGAL, CBO | | | COMMERCIAL COMBINATION PLANS EXAMINER | | | (561) 805-6714 | | | [email protected] | | | | | | DENIED BY BUILDING | | | PLEASE ADDRESS THE ITEMS NOTED BELOW: | | | | | | 1) COMPLIED. THE PLANS HAVE SEVERAL REFERENCES TO THE | | | FBC SIXTH EDITION (2017) WHICH WENT INTO EFFECT ON | | | JANUARY 1, 2018. ALL NEW PERMITS APPLIED FOR ON OR | | | AFTER THAT DATE ARE REQUIRED TO COMPLY WITH AND | | | REFERENCE THE FBC SIXTH EDITION (2017). THE FOUNDATION | | | PERMIT FOR THIS PROJECT (#17111142) WAS APPLIED FOR ON | | | 11/30/2017, THEREFORE THIS PROJECT IS UNDER THE FBC | | | FIFTH EDITION (2014). REVISE PLANS TO ONLY REFERENCE | | | THE FBC FIFTH EDITION (2014) FS CHAPTER 553 | | | | | | 2) COMPLIED. SPECIFY THE TYPE OF OCCUPANCY AND | | | CONSTRUCTION TYPE FOR THE BUILDING ON THE PLANS. FBC | | | 302.1 AND 602.1 | | | | | | 3) NOT ADDRESSED. A PRE-CONSTRUCTION ELEVATION | | | CERTIFICATE IS REQUIRED TO BE SUBMITTED. THIS PROJECT | | | IS LOCATED IN A SPECIAL FLOOD HAZARD AREA. THE FLOOD | | | ZONE IS AE THE BASE FLOOD ELEVATION FOR THE BUILDING IS | | | 7' NAVD 88 PLUS THE 2' FREEBOARD REQUIRED BY THE CITY | | | OF WEST PALM BEACH'S FLOOD ORDINANCE. THE LOWEST FLOOR | | | OF THE BUILDING AND THE EQUIPMENT SERVICING THE | | | BUILDING IS REQUIRED TO BE AT OR ABOVE 9'-0" NAVD 88. | | | ELEVATION CERTIFICATES FROM A FLORIDA LICENSED SURVEYOR | | | WILL BE REQUIRED AT VARIOUS STAGES OF CONSTRUCTION. A | | | PRE-CONSTRUCTION ELEVATION CERTIFICATED BASED ON THE | | | PROPOSED PLANS IS REQUIRED AT THIS TIME. | | | | | | 4) COMPLIED. THERE ARE SEVERAL NOTES ON THE PLAN THAT | | | CITE THE FBC RESIDENTIAL, THESE NOTES DO NOT APPLY TO | | | THIS PROJECT. THIS BUILDING CONTAINS MULTIPLE | | | RESIDENTIAL UNITS THAT ARE SPECIFIED AS CONDOMINIUMS | | | AND AS SUCH ARE CONSIDERED R-2 OCCUPANCY TYPES AND ARE | | | SUBJECT TO THE FBC BUILDING SCOPING REQUIREMENTS. FBC | | | 101.2 | | | | | | 5) PARTIALLY COMPLIED. THE CODE SECTION FOR GUARD | | | HEIGHT IS INCORRECTLY SPECIFIED AS FBC 1015.3 ON THE | | | PLANS. REVISE THE STAIR INFORMATION ON SHEET A201 TO | | | 2014 FBC SECTION 1607.8 FOR LOADS AND SECTION 1013.3 | | | FOR REQUIRED 42" GUARD HEIGHT, EXCEPT WITHIN INDIVIDUAL | | | DWELLING UNITS OF R-2 OCCUPANCIES. | | | | | | 6) PARTIALLY COMPLIED. THE CODE SECTION FOR THE GUARD | | | OPENINGS IS INCORRECTLY SPECIFIED AS FBC 1015.4 ON THE | | | PLANS. SHOW COMPLIANCE WITH FBC 1013.4 FOR GUARD | | | OPENING LIMITATIONS. | | | | | | 7) NOT ADDRESSED. A SCHEMATIC FIRE SPRINKLER PLAN IS | | | REQUIRED TO BE SUBMITTED BY FBC 107.3.5.1. PROVIDE A | | | FIRE SPRINKLER PLAN. FBC 903.2.11.3 ( SEE FIRE REVIEW | | | COMMENTS) | | | | | | 8) PARTIALLY COMPLIED. THE LIFE SAFETY PLAN THAT WAS | | | SUBMITTED HAS SOME ERRORS AND OMISSIONS. SHEET LS-1 | | | SHOWS THE EGRESS PATH OF TRAVEL FROM THE FIRE PUMP ROOM | | | THROUGH WALLS AND THE ADJACENT UNIT. INDICATE THE FIRE | | | RATED WALLS AT THE SHAFTS, ELEVATOR HOISTWAY, EXIT | | | STAIRWAYS, ETC. ON THE LIFE SAFETY FLOOR PLANS BY USING | | | DIFFERENT COMBINATIONS OF DOTS AND DASHES ALONG WITH A | | | CORRESPONDING SCHEDULE. SHOW THE OVERALL DIAGONAL | | | DISTANCE OF THE AREA SERVED AND THE EXIT STAIR | | | SEPARATION DISTANCE ON THE LIFE SAFETY FLOOR PLANS. | | | SHOW THE OCCUPANT LOADS FOR EACH AREA ON THE LS FLOOR | | | PLANS. SHOW THE EGRESS DOOR SIZES AND OCCUPANT CAPACITY | | | ON THE LS FLOOR PLANS. THE EXIT ACCESS TRAVEL DISTANCE | | | IS MEASURED FROM THE MOST REMOTE POINT WITHIN A STORY | | | TO AN EXIT AND INCLUDES THE COMMON PATH OF TRAVEL PER | | | 2014 FBC 1016.3. THE MOST REMOTE POINT ON THE BALCONIES | | | NEEDS TO BE INCLUDED IN THE TRAVEL DISTANCE. PLEASE PUT | | | THE TRAVEL DISTANCES ON THE TRAVEL PATHS SHOWN ON THE | | | LS FLOOR PLANS. THE FIRE RATINGS OF THE DOORS ARE NOT | | | SPECIFIED IN THE DOOR SCHEDULE. PROVIDE A LIFE SAFETY | | | PLAN, SHOWING OCCUPANT LOADS, TRAVEL DISTANCES, ETC. | | | FBC 1001.4 ( SEE FIRE REVIEW COMMENTS) | | | | | | 9) NOT ADDRESSED. THE EQUIPMENT IS NOT SHOWN ON THE | | | PLANS. SHOW COMPLIANCE WITH FBC 901.8. FIRE PUMP AND | | | AUTOMATIC SPRINKLER SYSTEM RISER ROOMS SHALL BE | | | DESIGNED WITH ADEQUATE SPACE FOR ALL EQUIPMENT | | | NECESSARY FOR THE INSTALLATION, AS DEFINED BY THE | | | MANUFACTURER, WITH SUFFICIENT WORKING ROOM AROUND THE | | | STATIONARY EQUIPMENT. CLEARANCES AROUND EQUIPMENT TO | | | ELEMENTS OF PERMANENT CONSTRUCTION, INCLUDING OTHER | | | INSTALLED EQUIPMENT AND APPLIANCES, SHALL BE SUFFICIENT | | | TO ALLOW INSPECTION, SERVICE, REPAIR OR REPLACEMENT | | | WITHOUT REMOVING SUCH ELEMENTS OF PERMANENT | | | CONSTRUCTION OR DISABLING THE FUNCTION OF A REQUIRED | | | FIRE-RESISTANCE-RATED ASSEMBLY. FIRE PUMP AND AUTOMATIC | | | SPRINKLER SYSTEM RISER ROOMS SHALL BE PROVIDED WITH A | | | DOOR(S) AND UNOBSTRUCTED PASSAGEWAY LARGE ENOUGH TO | | | ALLOW REMOVAL OF THE LARGEST PIECE OF EQUIPMENT. | | | | | | 10) COMPLIED. | | | | | | 11) COMPLIED. | | | | | | 12) COMPLIED. | | | | | | 13) PARTIALLY COMPLIED. THE BATHROOM ON THE GROUND | | | FLOOR IS REQUIRED TO BE A SPECIFICATION B BATHROOM. THE | | | 2'-8" DOOR (D11) AT THE GROUND FLOOR BATHROOM DOES NOT | | | PROVIDE A 32" NOMINAL CLEAR OPENING AS REQUIRED BY FAIR | | | HOUSING FOR A USABLE BATHROOM. THERE IS NO DOOR ID TAG | | | FOR THE POCKET DOOR AT THE GROUND FLOOR BATHROOM. THE | | | POCKET DOOR AT THE STUDY BATHROOM IS MISTAKENLY TAGGED | | | D3, WHICH IS A 2'-8" LOUVERED DOOR. THE GLASS WALL AND | | | DOOR AT THE SPEC. B BATHROOM IS NOT ALLOWED TO BE IN | | | THE CLEAR FLOOR SPACE FOR THE TOILET. SPECIFY THE | | | REQUIRED DIMENSIONS AT THE CLEAR FLOOR SPACE AREAS ON | | | THE ACCESSIBLE ROUTE FLOOR PLANS. NOTE: THIS PROJECT IS | | | FOR A PRIVATE MULTI-FAMILY RESIDENCE AND NO FEDERAL | | | FUNDING IS BEING USED, THEREFORE IT IS NOT REQUIRED TO | | | COMPLY WITH THE ADA, HOWEVER, IT IS REQUIRED TO COMPLY | | | WITH FAIR HOUSING. SHOW COMPLIANCE WITH FAIR HOUSING | | | REQUIREMENTS FOR SCHEDULE A OR B BATHROOM REQUIREMENTS | | | AS SPECIFIED IN THE FAIR HOUSING ACT DESIGN MANUAL. FBC | | | ACCESSIBILITY - FAIR HOUSING GUIDELINES (SEE PLUMBING | | | REVIEW COMMENTS.) | | | | | | 14) COMPLIED. | | | | | | 15) NOT ADDRESSED. THE ACTUAL TEST REPORTS FOR THE | | | SOUND PROOFING MATERIALS ARE REQUIRED TO BE SUBMITTED | | | FOR REVIEW. THESE DOCUMENTS CAN BE DEFERRED IF LISTED | | | IF LISTED IN THE CONSTRUCTION DOCUMENTS. SEE COMMENT | | | #16. SHOW COMPLIANCE WITH THE FOLLOWING: FBC 1207.2 | | | AIR-BORNE SOUND. WALLS, PARTITIONS AND FLOOR/CEILING | | | ASSEMBLIES SEPARATING DWELLING UNITS FROM EACH OTHER OR | | | FROM PUBLIC OR SERVICE AREAS SHALL HAVE A SOUND | | | TRANSMISSION CLASS (STC) OF NOT LESS THAN 50 (45 IF | | | FIELD TESTED) FOR AIR-BORNE NOISE WHEN TESTED IN | | | ACCORDANCE WITH ASTM E 90. PENETRATIONS OR OPENINGS IN | | | CONSTRUCTION ASSEMBLIES FOR PIPING; ELECTRICAL DEVICES; | | | RECESSED CABINETS; BATHTUBS; SOFFITS; OR HEATING, | | | VENTILATING OR EXHAUST DUCTS SHALL BE SEALED, LINED, | | | INSULATED OR OTHERWISE TREATED TO MAINTAIN THE REQUIRED | | | RATINGS. THIS REQUIREMENT SHALL NOT APPLY TO DWELLING | | | UNIT ENTRANCE DOORS; HOWEVER, SUCH DOORS SHALL BE TIGHT | | | FITTING TO THE FRAME AND SILL. | | | 1207.3 STRUCTURE-BORNE SOUND. | | | FLOOR/CEILING ASSEMBLIES BETWEEN DWELLING UNITS OR | | | BETWEEN A DWELLING UNIT AND A PUBLIC OR SERVICE AREA | | | WITHIN THE STRUCTURE SHALL HAVE AN IMPACT INSULATION | | | CLASS (IIC) RATING OF NOT LESS THAN 50 (45 IF FIELD | | | TESTED) WHEN TESTED IN ACCORDANCE WITH ASTM E 492. | | | TESTING REPORTS FOR SOUND PROOFING INSULATION FOR TILE | | | FLOORING OR OTHER HARD SURFACE FLOORING MATERIAL IS | | | REQUIRED TO BE SUBMITTED. THIS CAN BE A DEFERRED | | | SUBMITTAL. | | | | | | 16) NOT ADDRESSED. FBC 107.3.4 - PROVIDE TWO SETS OF | | | PRODUCT APPROVALS FOR THOSE PRODUCTS WHICH ARE | | | REGULATED BY FAC 61G20-3.001 PER FLORIDA STATUTE | | | 553.842 (5) THAT HAVE BEEN REVIEWED AND APPROVED IN | | | WRITING BY THE DESIGNER OF RECORD. PROVIDE TWO COMPLETE | | | PRODUCT APPROVALS WITH FL OR NOA NUMBERS INCLUDING | | | INSTALLATION INSTRUCTIONS AND MAXIMUM DESIGN PRESSURES | | | FOR EACH OF THE DIFFERENT ROOFING MATERIALS, | | | WINDOW/GLASS TYPES, STRUCTURAL MULLIONS, ROOF HATCHES | | | AND EXTERIOR DOOR TYPES. YOU MAY REQUEST THAT THESE | | | ITEMS BE DEFERRED TO A LATER DATE. SEE BELOW. | | | 107.3.4.2 DEFERRED SUBMITTALS. FOR THE PURPOSES OF THIS | | | SECTION, DEFERRED SUBMITTALS ARE DEFINED AS THOSE | | | PORTIONS OF THE DESIGN THAT ARE NOT SUBMITTED AT THE | | | TIME OF THE APPLICATION AND THAT ARE TO BE SUBMITTED TO | | | THE BUILDING OFFICIAL WITHIN A SPECIFIED PERIOD. | | | DEFERRAL OF ANY SUBMITTAL ITEMS SHALL HAVE THE PRIOR | | | APPROVAL OF THE BUILDING OFFICIAL. THE REGISTERED | | | DESIGN PROFESSIONAL IN RESPONSIBLE CHARGE SHALL LIST | | | THE DEFERRED SUBMITTALS ON THE CONSTRUCTION DOCUMENTS | | | FOR REVIEW BY THE BUILDING OFFICIAL. DOCUMENTS FOR | | | DEFERRED SUBMITTAL ITEMS SHALL BE SUBMITTED TO THE | | | REGISTERED DESIGN PROFESSIONAL IN RESPONSIBLE CHARGE | | | WHO SHALL REVIEW THEM AND FORWARD THEM TO THE BUILDING | | | OFFICIAL WITH A NOTATION INDICATING THAT THE DEFERRED | | | SUBMITTAL DOCUMENTS HAVE BEEN REVIEWED AND FOUND TO BE | | | IN GENERAL CONFORMANCE TO THE DESIGN OF THE BUILDING. | | | THE DEFERRED SUBMITTAL ITEMS SHALL NOT BE INSTALLED | | | UNTIL THE DEFERRED SUBMITTAL DOCUMENTS HAVE BEEN | | | APPROVED BY THE BUILDING OFFICIAL. | | | | | | 17) PARTIALLY ADDRESSED. THERE IS A PORTION OF THE | | | PARAPET WALL LOCATED WITHIN 10 FEET OF THE ROOF HATCH | | | THAT IS ONLY 24" ABOVE THE ROOF DECK. SEE SHEETS A701 | | | AND A403. THE ROOF HATCH SHOWN ON THE PLANS DOES NOT | | | COMPLY WITH THE REQUIREMENTS FOR SIZE AND GUARDS. ON | | | SHEET A502 THE STAIR SECTIONS ARE NOT IDENTIFIED AS | | | STAIR #1 AND STAIR #2. THERE IS A DOOR SHOWN AT THE | | | GROUND LEVEL ON THE SECTION FOR STAIR #1, WHERE THERE | | | IS NO DOOR SHOWN ON THE FLOOR PLANS. SEE A502 AND A503. | | | THE HANDRAILS FOR THE EXIT STAIRS DO NOT HAVE | | | EXTENSIONS AT THE TOP AND BOTTOM AS REQUIRED BY FAIR | | | HOUSING AND ANSI117.1. THE HANDRAIL IS REQUIRED TO | | | EXTEND HORIZONTALLY AT THE TOP FOR 12" AND FOLLOW THE | | | SLOPE OF THE STAIRS FOR A DISTANCE OF AT LEAST ONE | | | TREAD DEPTH. SOME OF THE STAIRS SHOWN ON SHEET1009.16 | | | STAIRWAY TO ROOF. IN BUILDINGS FOUR OR MORE STORIES | | | ABOVE GRADE PLANE, ONE STAIRWAY SHALL EXTEND TO THE | | | ROOF SURFACE, UNLESS THE ROOF HAS A SLOPE STEEPER THAN | | | FOUR UNITS VERTICAL IN 12 UNITS HORIZONTAL (33-PERCENT | | | SLOPE). IN BUILDINGS WITHOUT AN OCCUPIED ROOF, ACCESS | | | TO THE ROOF FROM THE TOP STORY SHALL BE PERMITTED TO BE | | | BY AN ALTERNATING TREAD DEVICE. | | | 1009.16.1 ROOF ACCESS. WHERE A STAIRWAY IS PROVIDED TO | | | A ROOF, ACCESS TO THE ROOF SHALL BE PROVIDED THROUGH A | | | PENTHOUSE COMPLYING WITH SECTION 1509.2. | | | EXCEPTION: IN BUILDINGS WITHOUT AN OCCUPIED ROOF, | | | ACCESS TO THE ROOF SHALL BE PERMITTED TO BE A ROOF | | | HATCH OR TRAP DOOR NOT LESS THAN 16 SQUARE FEET (1.5 | | | M2) IN AREA AND HAVING A MINIMUM DIMENSION OF 2 FEET | | | (610 MM). | | | 1009.16.2 PROTECTION AT ROOF HATCH OPENINGS. WHERE THE | | | ROOF HATCH OPENING PROVIDING THE REQUIRED ACCESS IS | | | LOCATED WITHIN 10 FEET (3049 MM) OF THE ROOF EDGE, SUCH | | | ROOF ACCESS OR ROOF EDGE SHALL BE PROTECTED BY GUARDS | | | INSTALLED IN ACCORDANCE WITH THE PROVISIONS OF SECTION | | | 1013. | | | | | | 18) COMPLIED. | | | | | | 19) COMPLIED. | | | | | | 20) COMPLIED. | | | | | | 21) COMPLIED. | | | | | | 22) COMPLIED. | | | | | | 23) COMPLIED. | | | | | | 24) PARTIALLY COMPLIED. THE BUILDING CODE ANALYSIS ON | | | LS-1 HAS A 4 HOUR FIRE RATING FOR THE STAIRS AND | | | ELEVATOR SHAFT. SHEET LS-4 HAS A 2 HOUR RATING IN | | | DETAIL 10. SHOW COMPLIANCE WITH FBC 3002.1 HOISTWAY | | | ENCLOSURE PROTECTION. ELEVATOR, DUMBWAITER AND OTHER | | | HOISTWAY ENCLOSURES SHALL BE SHAFT ENCLOSURES COMPLYING | | | WITH SECTION 713. FBC 713.4 FIRE-RESISTANCE RATING. | | | SHAFT ENCLOSURES SHALL HAVE A FIRE-RESISTANCE RATING OF | | | NOT LESS THAN 2 HOURS WHERE CONNECTING FOUR STORIES OR | | | MORE, AND NOT LESS THAN 1 HOUR WHERE CONNECTING LESS | | | THAN FOUR STORIES. THE NUMBER OF STORIES CONNECTED BY | | | THE SHAFT ENCLOSURE SHALL INCLUDE ANY BASEMENTS BUT NOT | | | ANY MEZZANINES. SHAFT ENCLOSURES SHALL HAVE A | | | FIRE-RESISTANCE RATING NOT LESS THAN THE FLOOR ASSEMBLY | | | PENETRATED, BUT NEED NOT EXCEED 2 HOURS. SHAFT | | | ENCLOSURES SHALL MEET THE REQUIREMENTS OF SECTION | | | 703.2.1. | | | | | | 25) COMPLIED. | | | | | | 26) COMPLIED. | | | | | | 27) COMPLIED. | | | | | | 28) SEE COMMENTS FOR ITEM #8. IDENTIFY THE FIRE RATED | | | WALLS ON THE PLANS. FBC 107.2.1 | | | | | | 29) IN ORDER TO REDUCE PLAN REVIEW TIME, PLEASE SUBMIT | | | A RESPONSE LETTER INDICATING HOW EACH OF THE REVIEW | | | COMMENTS HAS BEEN ADDRESSED. | | | WHEN RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE | | | LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY | | | RE-SUBMITTAL FORM. ADDITIONALLY, PLEASE INSERT | | | CORRECTED PLAN SHEETS INTO THE SETS, REMOVE THE | | | PREVIOUSLY REVIEWED SHEETS AND MARK VOID ON THEM, AND | | | KEEP THEM WITH THE SUBMITTALS. | | | | | | | | | | | | | | | | | | | | | |
|
|
| Review Stop |
B |
BUILDING (STRUCTURAL) |
| Rev No |
2 |
Status |
F |
Date |
2019-03-29 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2019-03-29 |
Time |
18:24 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2019-03-28 |
Time |
18:43 |
Sent To |
|
|
| Notes |
| 2019-03-28 18:45:33 | PLAN | | | REVIEW COMMENTS | | | | | | 2ND REVIEW: FBC FIFTH EDITION (2014) | | | ROBERT MCDOUGAL, CBO | | | COMMERCIAL COMBINATION PLANS EXAMINER | | | (561) 805-6714 | | | [email protected] | | | | | | DENIED BY BUILDING (COMMENTS FROM THE FIRST REVIEW HAVE | | | NOT BEEN ADDRESSED.) | | | PLEASE ADDRESS THE ITEMS NOTED BELOW: | | | | | | 1) THE PLANS HAVE SEVERAL REFERENCES TO THE FBC SIXTH | | | EDITION (2017) WHICH WENT INTO EFFECT ON JANUARY 1, | | | 2018. ALL NEW PERMITS APPLIED FOR ON OR AFTER THAT DATE | | | ARE REQUIRED TO COMPLY WITH AND REFERENCE THE FBC SIXTH | | | EDITION (2017). THE FOUNDATION PERMIT FOR THIS PROJECT | | | (#17111142) WAS APPLIED FOR ON 11/30/2017, THEREFORE | | | THIS PROJECT IS UNDER THE FBC FIFTH EDITION (2014). | | | REVISE PLANS TO ONLY REFERENCE THE FBC FIFTH EDITION | | | (2014) FS CHAPTER 553 | | | | | | 2) SPECIFY THE TYPE OF OCCUPANCY AND CONSTRUCTION TYPE | | | FOR THE BUILDING ON THE PLANS. FBC 302.1 AND 602.1 | | | | | | 3) THIS PROJECT IS LOCATED IN A SPECIAL FLOOD HAZARD | | | AREA. THE FLOOD ZONE IS AE THE BASE FLOOD ELEVATION FOR | | | THE BUILDING IS 7' NAVD 88 PLUS THE 2' FREEBOARD | | | REQUIRED BY THE CITY OF WEST PALM BEACH'S FLOOD | | | ORDINANCE. THE LOWEST FLOOR OF THE BUILDING AND THE | | | EQUIPMENT SERVICING THE BUILDING IS REQUIRED TO BE AT | | | OR ABOVE 9'-0" NAVD 88. ELEVATION CERTIFICATES FROM A | | | FLORIDA LICENSED SURVEYOR WILL BE REQUIRED AT VARIOUS | | | STAGES OF CONSTRUCTION. A PRE-CONSTRUCTION ELEVATION | | | CERTIFICATED BASED ON THE PROPOSED PLANS IS REQUIRED AT | | | THIS TIME. | | | | | | 4) THERE ARE SEVERAL NOTES ON THE PLAN THAT CITE THE | | | FBC RESIDENTIAL, THESE NOTES DO NOT APPLY TO THIS | | | PROJECT. THIS BUILDING CONTAINS MULTIPLE RESIDENTIAL | | | UNITS THAT ARE SPECIFIED AS CONDOMINIUMS AND AS SUCH | | | ARE CONSIDERED R-2 OCCUPANCY TYPES AND ARE SUBJECT TO | | | THE FBC BUILDING SCOPING REQUIREMENTS. FBC 101.2 | | | | | | 5) REVISE THE STAIR INFORMATION ON SHEET A201 TO 2014 | | | FBC SECTION 1607.8 FOR LOADS AND SECTION 1013.3 FOR | | | REQUIRED 42" GUARD HEIGHT, EXCEPT WITHIN INDIVIDUAL | | | DWELLING UNITS OF R-2 OCCUPANCIES. | | | | | | 6) SHOW COMPLIANCE WITH FBC 1013.4 FOR GUARD OPENING | | | LIMITATIONS. | | | | | | 7) PROVIDE A FIRE SPRINKLER PLAN. FBC 903.2.11.3 ( SEE | | | FIRE REVIEW COMMENTS) | | | | | | 8) PROVIDE A LIFE SAFETY PLAN, SHOWING OCCUPANT LOADS, | | | TRAVEL DISTANCES, ETC. FBC 1001.4 ( SEE FIRE REVIEW | | | COMMENTS) | | | | | | 9) SHOW COMPLIANCE WITH FBC 901.8. FIRE PUMP AND | | | AUTOMATIC SPRINKLER SYSTEM RISER ROOMS SHALL BE | | | DESIGNED WITH ADEQUATE SPACE FOR ALL EQUIPMENT | | | NECESSARY FOR THE INSTALLATION, AS DEFINED BY THE | | | MANUFACTURER, WITH SUFFICIENT WORKING ROOM AROUND THE | | | STATIONARY EQUIPMENT. CLEARANCES AROUND EQUIPMENT TO | | | ELEMENTS OF PERMANENT CONSTRUCTION, INCLUDING OTHER | | | INSTALLED EQUIPMENT AND APPLIANCES, SHALL BE SUFFICIENT | | | TO ALLOW INSPECTION, SERVICE, REPAIR OR REPLACEMENT | | | WITHOUT REMOVING SUCH ELEMENTS OF PERMANENT | | | CONSTRUCTION OR DISABLING THE FUNCTION OF A REQUIRED | | | FIRE-RESISTANCE-RATED ASSEMBLY. FIRE PUMP AND AUTOMATIC | | | SPRINKLER SYSTEM RISER ROOMS SHALL BE PROVIDED WITH A | | | DOOR(S) AND UNOBSTRUCTED PASSAGEWAY LARGE ENOUGH TO | | | ALLOW REMOVAL OF THE LARGEST PIECE OF EQUIPMENT. | | | | | | 10) THERE IS A CONFLICT IN THE FINISH FLOOR ELEVATIONS | | | BETWEEN SHEET C-1 AND SHEET A201. SHEET C-1 HAS THE | | | ELEVATIONS IN NAVD 88 AND A201 IS IN NGVD 29. ALL OF | | | THE ELEVATIONS ARE TO USE THE CURRENT VERTICAL DATA | | | USED BY FEMA, WHICH IS NAVD 88. | | | | | | 11) ON SHEET A207, THE FLOOR PLAN FOR THE SEVENTH FLOOR | | | IS INCORRECTLY LABELED AS THE SECOND FLOOR. FBC 107.2.1 | | | | | | 12) ON SHEET A301 THE GROUND FLOOR CEILING PLAN DOES | | | NOT SHOW THE OPENING FOR THE STAIRWAY TO THE SECOND | | | FLOOR. FBC 107.2.1 | | | | | | 13) NOTE: THIS PROJECT IS FOR A PRIVATE MULTI-FAMILY | | | RESIDENCE AND NO FEDERAL FUNDING IS BEING USED, | | | THEREFORE IT IS NOT REQUIRED TO COMPLY WITH THE ADA, | | | HOWEVER, IT IS REQUIRED TO COMPLY WITH FAIR HOUSING. | | | SHOW COMPLIANCE WITH FAIR HOUSING REQUIREMENTS FOR | | | SCHEDULE A OR B BATHROOM REQUIREMENTS AS SPECIFIED IN | | | THE FAIR HOUSING ACT DESIGN MANUAL. FBC ACCESSIBILITY - | | | FAIR HOUSING GUIDELINES (SEE PLUMBING REVIEW COMMENTS.) | | | | | | 14) THE COMPONENT AND CLADDING PRESSURES FOR THE | | | EXTERIOR DOORS AND WINDOWS HAVE NOT BEEN PROVIDED IN | | | THE SCHEDULES ON SHEET A601. THE STRUCTURAL SHEETS HAVE | | | BEEN REMOVED AND ARE UNDER ANOTHER PERMIT. FBC 107.2.1 | | | | | | 15) SHOW COMPLIANCE WITH THE FOLLOWING: FBC 1207.2 | | | AIR-BORNE SOUND. WALLS, PARTITIONS AND FLOOR/CEILING | | | ASSEMBLIES SEPARATING DWELLING UNITS FROM EACH OTHER OR | | | FROM PUBLIC OR SERVICE AREAS SHALL HAVE A SOUND | | | TRANSMISSION CLASS (STC) OF NOT LESS THAN 50 (45 IF | | | FIELD TESTED) FOR AIR-BORNE NOISE WHEN TESTED IN | | | ACCORDANCE WITH ASTM E 90. PENETRATIONS OR OPENINGS IN | | | CONSTRUCTION ASSEMBLIES FOR PIPING; ELECTRICAL DEVICES; | | | RECESSED CABINETS; BATHTUBS; SOFFITS; OR HEATING, | | | VENTILATING OR EXHAUST DUCTS SHALL BE SEALED, LINED, | | | INSULATED OR OTHERWISE TREATED TO MAINTAIN THE REQUIRED | | | RATINGS. THIS REQUIREMENT SHALL NOT APPLY TO DWELLING | | | UNIT ENTRANCE DOORS; HOWEVER, SUCH DOORS SHALL BE TIGHT | | | FITTING TO THE FRAME AND SILL. | | | 1207.3 STRUCTURE-BORNE SOUND. | | | FLOOR/CEILING ASSEMBLIES BETWEEN DWELLING UNITS OR | | | BETWEEN A DWELLING UNIT AND A PUBLIC OR SERVICE AREA | | | WITHIN THE STRUCTURE SHALL HAVE AN IMPACT INSULATION | | | CLASS (IIC) RATING OF NOT LESS THAN 50 (45 IF FIELD | | | TESTED) WHEN TESTED IN ACCORDANCE WITH ASTM E 492. | | | TESTING REPORTS FOR SOUND PROOFING INSULATION FOR TILE | | | FLOORING OR OTHER HARD SURFACE FLOORING MATERIAL IS | | | REQUIRED TO BE SUBMITTED. THIS CAN BE A DEFERRED | | | SUBMITTAL. | | | | | | 16) FBC 107.3.4 - PROVIDE TWO SETS OF PRODUCT APPROVALS | | | FOR THOSE PRODUCTS WHICH ARE REGULATED BY FAC | | | 61G20-3.001 PER FLORIDA STATUTE 553.842 (5) THAT HAVE | | | BEEN REVIEWED AND APPROVED IN WRITING BY THE DESIGNER | | | OF RECORD. PROVIDE TWO COMPLETE PRODUCT APPROVALS WITH | | | FL OR NOA NUMBERS INCLUDING INSTALLATION INSTRUCTIONS | | | AND MAXIMUM DESIGN PRESSURES FOR EACH OF THE DIFFERENT | | | ROOFING MATERIALS, WINDOW/GLASS TYPES, STRUCTURAL | | | MULLIONS, ROOF HATCHES AND EXTERIOR DOOR TYPES. YOU MAY | | | REQUEST THAT THESE ITEMS BE DEFERRED TO A LATER DATE. | | | SEE BELOW. | | | 107.3.4.2 DEFERRED SUBMITTALS. FOR THE PURPOSES OF THIS | | | SECTION, DEFERRED SUBMITTALS ARE DEFINED AS THOSE | | | PORTIONS OF THE DESIGN THAT ARE NOT SUBMITTED AT THE | | | TIME OF THE APPLICATION AND THAT ARE TO BE SUBMITTED TO | | | THE BUILDING OFFICIAL WITHIN A SPECIFIED PERIOD. | | | DEFERRAL OF ANY SUBMITTAL ITEMS SHALL HAVE THE PRIOR | | | APPROVAL OF THE BUILDING OFFICIAL. THE REGISTERED | | | DESIGN PROFESSIONAL IN RESPONSIBLE CHARGE SHALL LIST | | | THE DEFERRED SUBMITTALS ON THE CONSTRUCTION DOCUMENTS | | | FOR REVIEW BY THE BUILDING OFFICIAL. DOCUMENTS FOR | | | DEFERRED SUBMITTAL ITEMS SHALL BE SUBMITTED TO THE | | | REGISTERED DESIGN PROFESSIONAL IN RESPONSIBLE CHARGE | | | WHO SHALL REVIEW THEM AND FORWARD THEM TO THE BUILDING | | | OFFICIAL WITH A NOTATION INDICATING THAT THE DEFERRED | | | SUBMITTAL DOCUMENTS HAVE BEEN REVIEWED AND FOUND TO BE | | | IN GENERAL CONFORMANCE TO THE DESIGN OF THE BUILDING. | | | THE DEFERRED SUBMITTAL ITEMS SHALL NOT BE INSTALLED | | | UNTIL THE DEFERRED SUBMITTAL DOCUMENTS HAVE BEEN | | | APPROVED BY THE BUILDING OFFICIAL. | | | | | | 17) THE ROOF HATCH SHOWN ON THE PLANS DOES NOT COMPLY | | | WITH THE REQUIREMENTS FOR SIZE AND GUARDS. 1009.16 | | | STAIRWAY TO ROOF. IN BUILDINGS FOUR OR MORE STORIES | | | ABOVE GRADE PLANE, ONE STAIRWAY SHALL EXTEND TO THE | | | ROOF SURFACE, UNLESS THE ROOF HAS A SLOPE STEEPER THAN | | | FOUR UNITS VERTICAL IN 12 UNITS HORIZONTAL (33-PERCENT | | | SLOPE). IN BUILDINGS WITHOUT AN OCCUPIED ROOF, ACCESS | | | TO THE ROOF FROM THE TOP STORY SHALL BE PERMITTED TO BE | | | BY AN ALTERNATING TREAD DEVICE. | | | 1009.16.1 ROOF ACCESS. WHERE A STAIRWAY IS PROVIDED TO | | | A ROOF, ACCESS TO THE ROOF SHALL BE PROVIDED THROUGH A | | | PENTHOUSE COMPLYING WITH SECTION 1509.2. | | | EXCEPTION: IN BUILDINGS WITHOUT AN OCCUPIED ROOF, | | | ACCESS TO THE ROOF SHALL BE PERMITTED TO BE A ROOF | | | HATCH OR TRAP DOOR NOT LESS THAN 16 SQUARE FEET (1.5 | | | M2) IN AREA AND HAVING A MINIMUM DIMENSION OF 2 FEET | | | (610 MM). | | | 1009.16.2 PROTECTION AT ROOF HATCH OPENINGS. WHERE THE | | | ROOF HATCH OPENING PROVIDING THE REQUIRED ACCESS IS | | | LOCATED WITHIN 10 FEET (3049 MM) OF THE ROOF EDGE, SUCH | | | ROOF ACCESS OR ROOF EDGE SHALL BE PROTECTED BY GUARDS | | | INSTALLED IN ACCORDANCE WITH THE PROVISIONS OF SECTION | | | 1013. | | | | | | 18) ON SHEET A602, #4 THE ENLARGED STAIR PLAN FOR THE | | | SEVENTH FLOOR, THE ELEVATOR EQUIPMENT IS NOT LABELED | | | AND SOME OF THE DIMENSIONS OF THE ROOM AND IT'S STAIR | | | LANDING ARE MISSING. FBC 107.2.1 | | | | | | 19) THE STAIR PLANS ON SHEET A602 HAVE ARE SPECIFIED AS | | | BEING 1/4" SCALE AND THEY ARE ACTUALLY 3/8" SCALE. FBC | | | 107.2.1 | | | | | | 20) THE PLANS SHOW A SHIPS LADDER FOR ACCESS TO THE | | | ELEVATOR EQUIPMENT ROOM. THE ROOM FOR ELEVATOR | | | EQUIPMENT THAT MUST BE ACCESSED FOR MAINTENANCE IS | | | REQUIRED TO BE ACCESSED BY A STAIRWAY. FBC 1009.17 | | | | | | 21) SHOW COMPLIANCE WITH FBC 1009.3.1.4 OPENINGS. | | | OPENINGS IN AN EXIT ACCESS STAIRWAY ENCLOSURE SHALL BE | | | PROTECTED IN ACCORDANCE WITH SECTION 716 AS REQUIRED | | | FOR FIRE BARRIERS. DOORS SHALL BE SELF- OR | | | AUTOMATIC-CLOSING BY SMOKE DETECTION IN ACCORDANCE WITH | | | SECTION 716.5.9.3. | | | 1009.3.1.4.1 PROHIBITED OPENINGS. OPENINGS OTHER THAN | | | THOSE NECESSARY FOR THE PURPOSE OF THE EXIT ACCESS | | | STAIRWAY ENCLOSURE SHALL NOT BE PERMITTED IN EXIT | | | ACCESS STAIRWAY ENCLOSURES. THE ELEVATOR EQUIPMENT ROOM | | | IS NOT ALLOWED TO OPEN INTO THE EXIT ACCESS STAIRWAY AS | | | SHOWN ON THE PLANS. | | | | | | 22) SHOW COMPLIANCE WITH FBC 1009.3.1.2 FIRE-RESISTANCE | | | RATING. EXIT ACCESS STAIRWAY ENCLOSURES SHALL HAVE A | | | FIRE-RESISTANCE RATING OF NOT LESS THAN 2 HOURS WHERE | | | CONNECTING FOUR STORIES OR MORE. | | | | | | 23) SHOW COMPLIANCE WITH FBC 1022.5 PENETRATIONS. | | | PENETRATIONS INTO AND OPENINGS THROUGH INTERIOR EXIT | | | STAIRWAYS AND RAMPS ARE PROHIBITED EXCEPT FOR REQUIRED | | | EXIT DOORS, EQUIPMENT AND DUCTWORK NECESSARY FOR | | | INDEPENDENT VENTILATION OR PRESSURIZATION, SPRINKLER | | | PIPING, STANDPIPES, ELECTRICAL RACEWAY FOR FIRE | | | DEPARTMENT COMMUNICATION SYSTEMS AND ELECTRICAL RACEWAY | | | SERVING THE INTERIOR EXIT STAIRWAY AND RAMP AND | | | TERMINATING AT A STEEL BOX NOT EXCEEDING 16 SQUARE | | | INCHES (0.010 M2). SUCH PENETRATIONS SHALL BE PROTECTED | | | IN ACCORDANCE WITH SECTION 714. THERE SHALL BE NO | | | PENETRATIONS OR COMMUNICATING OPENINGS, WHETHER | | | PROTECTED OR NOT, BETWEEN ADJACENT INTERIOR EXIT | | | STAIRWAYS AND RAMPS. | | | | | | 24) SHOW COMPLIANCE WITH FBC 3002.1 HOISTWAY ENCLOSURE | | | PROTECTION. ELEVATOR, DUMBWAITER AND OTHER HOISTWAY | | | ENCLOSURES SHALL BE SHAFT ENCLOSURES COMPLYING WITH | | | SECTION 713. FBC 713.4 FIRE-RESISTANCE RATING. SHAFT | | | ENCLOSURES SHALL HAVE A FIRE-RESISTANCE RATING OF NOT | | | LESS THAN 2 HOURS WHERE CONNECTING FOUR STORIES OR | | | MORE, AND NOT LESS THAN 1 HOUR WHERE CONNECTING LESS | | | THAN FOUR STORIES. THE NUMBER OF STORIES CONNECTED BY | | | THE SHAFT ENCLOSURE SHALL INCLUDE ANY BASEMENTS BUT NOT | | | ANY MEZZANINES. SHAFT ENCLOSURES SHALL HAVE A | | | FIRE-RESISTANCE RATING NOT LESS THAN THE FLOOR ASSEMBLY | | | PENETRATED, BUT NEED NOT EXCEED 2 HOURS. SHAFT | | | ENCLOSURES SHALL MEET THE REQUIREMENTS OF SECTION | | | 703.2.1. | | | | | | 25) SHOW COMPLIANCE WITH FBC 3002.4 ELEVATOR CAR TO | | | ACCOMMODATE AMBULANCE STRETCHER. ANY BUILDING THAT IS | | | MORE THAN THREE STORIES HIGH OR IN WHICH THE VERTICAL | | | DISTANCE BETWEEN THE BOTTOM TERMINAL LANDING AND THE | | | TOP TERMINAL LANDING EXCEEDS 25 FEET (7620 MM), MUST BE | | | CONSTRUCTED TO CONTAIN AT LEAST ONE PASSENGER ELEVATOR | | | THAT IS OPERATIONAL FOR BUILDING OCCUPANTS AND FIRE | | | DEPARTMENT EMERGENCY ACCESS TO ALL FLOORS. THE ELEVATOR | | | CAR SHALL BE OF SUCH A SIZE AND ARRANGEMENT TO | | | ACCOMMODATE AN AMBULANCE STRETCHER 24 INCHES BY 76 | | | INCHES (610 MM BY 2134 MM) WITH NOT LESS THAN 5-INCH | | | (127 MM) RADIUS CORNERS, IN THE HORIZONTAL, OPEN | | | POSITION AND SHALL BE IDENTIFIED BY THE INTERNATIONAL | | | SYMBOL FOR EMERGENCY MEDICAL SERVICES (STAR OF LIFE). | | | THE SYMBOL SHALL NOT BE LESS THAN 3 INCHES (76 MM) IN | | | HEIGHT AND SHALL BE PLACED INSIDE ON BOTH SIDES OF THE | | | HOISTWAY DOOR FRAME. | | | | | | 26) 3006.4 MACHINE ROOMS AND MACHINERY SPACES. ELEVATOR | | | MACHINE ROOMS AND MACHINERY SPACES SHALL BE ENCLOSED | | | WITH FIRE BARRIERS CONSTRUCTED IN ACCORDANCE WITH | | | SECTION 707 OR HORIZONTAL ASSEMBLIES CONSTRUCTED IN | | | ACCORDANCE WITH SECTION 711, OR BOTH. THE | | | FIRE-RESISTANCE RATING SHALL BE NOT LESS THAN THE | | | REQUIRED RATING OF THE HOISTWAY ENCLOSURE SERVED BY THE | | | MACHINERY. OPENINGS IN THE FIRE BARRIERS SHALL BE | | | PROTECTED WITH ASSEMBLIES HAVING A FIRE PROTECTION | | | RATING NOT LESS THAN THAT REQUIRED FOR THE HOISTWAY | | | ENCLOSURE DOORS. | | | EXCEPTIONS: 1. WHERE MACHINE ROOMS AND MACHINERY SPACES | | | DO NOT ABUT AND HAVE NO OPENINGS TO THE HOISTWAY | | | ENCLOSURE THEY SERVE THE FIRE BARRIERS CONSTRUCTED IN | | | ACCORDANCE WITH SECTION 707 OR HORIZONTAL ASSEMBLIES | | | CONSTRUCTED IN ACCORDANCE WITH SECTION 711, OR BOTH, | | | SHALL BE PERMITTED TO BE REDUCED TO A 1-HOUR | | | FIRE-RESISTANCE RATING. | | | | | | 27) F] 913.2 PROTECTION AGAINST INTERRUPTION OF | | | SERVICE. THE FIRE PUMP, DRIVER AND CONTROLLER SHALL BE | | | PROTECTED IN ACCORDANCE WITH NFPA 20 AGAINST POSSIBLE | | | INTERRUPTION OF SERVICE THROUGH DAMAGE CAUSED BY | | | EXPLOSION, FIRE, FLOOD, EARTHQUAKE, RODENTS, INSECTS, | | | WINDSTORM, FREEZING, VANDALISM AND OTHER ADVERSE | | | CONDITIONS. | | | 913.2.1 PROTECTION OF FIRE PUMP ROOMS. FIRE PUMPS SHALL | | | BE LOCATED IN ROOMS THAT ARE SEPARATED FROM ALL OTHER | | | AREAS OF THE BUILDING BY 2-HOUR FIRE BARRIERS | | | CONSTRUCTED IN ACCORDANCE WITH SECTION 707 OR 2-HOUR | | | HORIZONTAL ASSEMBLIES CONSTRUCTED IN ACCORDANCE WITH | | | SECTION 711, OR BOTH. | | | EXCEPTIONS: | | | 1. IN OTHER THAN HIGH-RISE BUILDINGS, SEPARATION BY | | | 1-HOUR FIRE BARRIERS CONSTRUCTED IN ACCORDANCE WITH | | | SECTION 707 OR 1-HOUR HORIZONTAL ASSEMBLIES CONSTRUCTED | | | IN ACCORDANCE WITH SECTION 711, OR BOTH, SHALL BE | | | PERMITTED IN BUILDINGS EQUIPPED THROUGHOUT WITH AN | | | AUTOMATIC SPRINKLER SYSTEM IN ACCORDANCE WITH SECTION | | | 903.3.1.1 OR 903.3.1.2. | | | | | | 2. SEPARATION IS NOT REQUIRED FOR FIRE PUMPS PHYSICALLY | | | SEPARATED IN ACCORDANCE WITH NFPA 20. | | | | | | 28) IDENTIFY THE FIRE RATED WALLS ON THE PLANS. FBC | | | 107.2.1 | | | | | | 29) IN ORDER TO REDUCE PLAN REVIEW TIME, PLEASE SUBMIT | | | A RESPONSE LETTER INDICATING HOW EACH OF THE REVIEW | | | COMMENTS HAS BEEN ADDRESSED. | | | WHEN RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE | | | LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY | | | RE-SUBMITTAL FORM. ADDITIONALLY, PLEASE INSERT | | | CORRECTED PLAN SHEETS INTO THE SETS, REMOVE THE | | | PREVIOUSLY REVIEWED SHEETS AND MARK VOID ON THEM, AND | | | KEEP THEM WITH THE SUBMITTALS. | | | | | | | | | | | | | | | | | | | | | |
|
|
| Review Stop |
B |
BUILDING (STRUCTURAL) |
| Rev No |
1 |
Status |
F |
Date |
2018-07-10 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2018-07-10 |
Time |
11:25 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2018-06-25 |
Time |
10:22 |
Sent To |
I |
|
| Notes |
| 2018-07-06 15:27:13 | PLAN | | | REVIEW COMMENTS | | | | | | 1ST REVIEW: FBC FIFTH EDITION (2014) | | | ROBERT MCDOUGAL, CBO | | | COMMERCIAL COMBINATION PLANS EXAMINER | | | (561) 805-6714 | | | [email protected] | | | | | | DENIED BY BUILDING | | | PLEASE ADDRESS THE ITEMS NOTED BELOW: | | | | | | 1) THE PLANS HAVE SEVERAL REFERENCES TO THE FBC SIXTH | | | EDITION (2017) WHICH WENT INTO EFFECT ON JANUARY 1, | | | 2018. ALL NEW PERMITS APPLIED FOR ON OR AFTER THAT DATE | | | ARE REQUIRED TO COMPLY WITH AND REFERENCE THE FBC SIXTH | | | EDITION (2017). THE FOUNDATION PERMIT FOR THIS PROJECT | | | (#17111142) WAS APPLIED FOR ON 11/30/2017, THEREFORE | | | THIS PROJECT IS UNDER THE FBC FIFTH EDITION (2014). | | | REVISE PLANS TO ONLY REFERENCE THE FBC FIFTH EDITION | | | (2014) FS CHAPTER 553 | | | | | | 2) SPECIFY THE TYPE OF OCCUPANCY AND CONSTRUCTION TYPE | | | FOR THE BUILDING ON THE PLANS. FBC 302.1 AND 602.1 | | | | | | 3) THIS PROJECT IS LOCATED IN A SPECIAL FLOOD HAZARD | | | AREA. THE FLOOD ZONE IS AE THE BASE FLOOD ELEVATION FOR | | | THE BUILDING IS 7' NAVD 88 PLUS THE 2' FREEBOARD | | | REQUIRED BY THE CITY OF WEST PALM BEACH'S FLOOD | | | ORDINANCE. THE LOWEST FLOOR OF THE BUILDING AND THE | | | EQUIPMENT SERVICING THE BUILDING IS REQUIRED TO BE AT | | | OR ABOVE 9'-0" NAVD 88. ELEVATION CERTIFICATES FROM A | | | FLORIDA LICENSED SURVEYOR WILL BE REQUIRED AT VARIOUS | | | STAGES OF CONSTRUCTION. A PRE-CONSTRUCTION ELEVATION | | | CERTIFICATED BASED ON THE PROPOSED PLANS IS REQUIRED AT | | | THIS TIME. | | | | | | 4) THERE ARE SEVERAL NOTES ON THE PLAN THAT CITE THE | | | FBC RESIDENTIAL, THESE NOTES DO NOT APPLY TO THIS | | | PROJECT. THIS BUILDING CONTAINS MULTIPLE RESIDENTIAL | | | UNITS THAT ARE SPECIFIED AS CONDOMINIUMS AND AS SUCH | | | ARE CONSIDERED R-2 OCCUPANCY TYPES AND ARE SUBJECT TO | | | THE FBC BUILDING SCOPING REQUIREMENTS. FBC 101.2 | | | | | | 5) REVISE THE STAIR INFORMATION ON SHEET A201 TO 2014 | | | FBC SECTION 1607.8 FOR LOADS AND SECTION 1013.3 FOR | | | REQUIRED 42" GUARD HEIGHT, EXCEPT WITHIN INDIVIDUAL | | | DWELLING UNITS OF R-2 OCCUPANCIES. | | | | | | 6) SHOW COMPLIANCE WITH FBC 1013.4 FOR GUARD OPENING | | | LIMITATIONS. | | | | | | 7) PROVIDE A FIRE SPRINKLER PLAN. FBC 903.2.11.3 ( SEE | | | FIRE REVIEW COMMENTS) | | | | | | 8) PROVIDE A LIFE SAFETY PLAN, SHOWING OCCUPANT LOADS, | | | TRAVEL DISTANCES, ETC. FBC 1001.4 ( SEE FIRE REVIEW | | | COMMENTS) | | | | | | 9) SHOW COMPLIANCE WITH FBC 901.8. FIRE PUMP AND | | | AUTOMATIC SPRINKLER SYSTEM RISER ROOMS SHALL BE | | | DESIGNED WITH ADEQUATE SPACE FOR ALL EQUIPMENT | | | NECESSARY FOR THE INSTALLATION, AS DEFINED BY THE | | | MANUFACTURER, WITH SUFFICIENT WORKING ROOM AROUND THE | | | STATIONARY EQUIPMENT. CLEARANCES AROUND EQUIPMENT TO | | | ELEMENTS OF PERMANENT CONSTRUCTION, INCLUDING OTHER | | | INSTALLED EQUIPMENT AND APPLIANCES, SHALL BE SUFFICIENT | | | TO ALLOW INSPECTION, SERVICE, REPAIR OR REPLACEMENT | | | WITHOUT REMOVING SUCH ELEMENTS OF PERMANENT | | | CONSTRUCTION OR DISABLING THE FUNCTION OF A REQUIRED | | | FIRE-RESISTANCE-RATED ASSEMBLY. FIRE PUMP AND AUTOMATIC | | | SPRINKLER SYSTEM RISER ROOMS SHALL BE PROVIDED WITH A | | | DOOR(S) AND UNOBSTRUCTED PASSAGEWAY LARGE ENOUGH TO | | | ALLOW REMOVAL OF THE LARGEST PIECE OF EQUIPMENT. | | | | | | 10) THERE IS A CONFLICT IN THE FINISH FLOOR ELEVATIONS | | | BETWEEN SHEET C-1 AND SHEET A201. SHEET C-1 HAS THE | | | ELEVATIONS IN NAVD 88 AND A201 IS IN NGVD 29. ALL OF | | | THE ELEVATIONS ARE TO USE THE CURRENT VERTICAL DATA | | | USED BY FEMA, WHICH IS NAVD 88. | | | | | | 11) ON SHEET A207, THE FLOOR PLAN FOR THE SEVENTH FLOOR | | | IS INCORRECTLY LABELED AS THE SECOND FLOOR. FBC 107.2.1 | | | | | | 12) ON SHEET A301 THE GROUND FLOOR CEILING PLAN DOES | | | NOT SHOW THE OPENING FOR THE STAIRWAY TO THE SECOND | | | FLOOR. FBC 107.2.1 | | | | | | 13) NOTE: THIS PROJECT IS FOR A PRIVATE MULTI-FAMILY | | | RESIDENCE AND NO FEDERAL FUNDING IS BEING USED, | | | THEREFORE IT IS NOT REQUIRED TO COMPLY WITH THE ADA, | | | HOWEVER, IT IS REQUIRED TO COMPLY WITH FAIR HOUSING. | | | SHOW COMPLIANCE WITH FAIR HOUSING REQUIREMENTS FOR | | | SCHEDULE A OR B BATHROOM REQUIREMENTS AS SPECIFIED IN | | | THE FAIR HOUSING ACT DESIGN MANUAL. FBC ACCESSIBILITY - | | | FAIR HOUSING GUIDELINES (SEE PLUMBING REVIEW COMMENTS.) | | | | | | 14) THE COMPONENT AND CLADDING PRESSURES FOR THE | | | EXTERIOR DOORS AND WINDOWS HAVE NOT BEEN PROVIDED IN | | | THE SCHEDULES ON SHEET A601. THE STRUCTURAL SHEETS HAVE | | | BEEN REMOVED AND ARE UNDER ANOTHER PERMIT. FBC 107.2.1 | | | | | | 15) SHOW COMPLIANCE WITH THE FOLLOWING: FBC 1207.2 | | | AIR-BORNE SOUND. WALLS, PARTITIONS AND FLOOR/CEILING | | | ASSEMBLIES SEPARATING DWELLING UNITS FROM EACH OTHER OR | | | FROM PUBLIC OR SERVICE AREAS SHALL HAVE A SOUND | | | TRANSMISSION CLASS (STC) OF NOT LESS THAN 50 (45 IF | | | FIELD TESTED) FOR AIR-BORNE NOISE WHEN TESTED IN | | | ACCORDANCE WITH ASTM E 90. PENETRATIONS OR OPENINGS IN | | | CONSTRUCTION ASSEMBLIES FOR PIPING; ELECTRICAL DEVICES; | | | RECESSED CABINETS; BATHTUBS; SOFFITS; OR HEATING, | | | VENTILATING OR EXHAUST DUCTS SHALL BE SEALED, LINED, | | | INSULATED OR OTHERWISE TREATED TO MAINTAIN THE REQUIRED | | | RATINGS. THIS REQUIREMENT SHALL NOT APPLY TO DWELLING | | | UNIT ENTRANCE DOORS; HOWEVER, SUCH DOORS SHALL BE TIGHT | | | FITTING TO THE FRAME AND SILL. | | | 1207.3 STRUCTURE-BORNE SOUND. | | | FLOOR/CEILING ASSEMBLIES BETWEEN DWELLING UNITS OR | | | BETWEEN A DWELLING UNIT AND A PUBLIC OR SERVICE AREA | | | WITHIN THE STRUCTURE SHALL HAVE AN IMPACT INSULATION | | | CLASS (IIC) RATING OF NOT LESS THAN 50 (45 IF FIELD | | | TESTED) WHEN TESTED IN ACCORDANCE WITH ASTM E 492. | | | TESTING REPORTS FOR SOUND PROOFING INSULATION FOR TILE | | | FLOORING OR OTHER HARD SURFACE FLOORING MATERIAL IS | | | REQUIRED TO BE SUBMITTED. THIS CAN BE A DEFERRED | | | SUBMITTAL. | | | | | | 16) FBC 107.3.4 - PROVIDE TWO SETS OF PRODUCT APPROVALS | | | FOR THOSE PRODUCTS WHICH ARE REGULATED BY FAC | | | 61G20-3.001 PER FLORIDA STATUTE 553.842 (5) THAT HAVE | | | BEEN REVIEWED AND APPROVED IN WRITING BY THE DESIGNER | | | OF RECORD. PROVIDE TWO COMPLETE PRODUCT APPROVALS WITH | | | FL OR NOA NUMBERS INCLUDING INSTALLATION INSTRUCTIONS | | | AND MAXIMUM DESIGN PRESSURES FOR EACH OF THE DIFFERENT | | | ROOFING MATERIALS, WINDOW/GLASS TYPES, STRUCTURAL | | | MULLIONS, ROOF HATCHES AND EXTERIOR DOOR TYPES. YOU MAY | | | REQUEST THAT THESE ITEMS BE DEFERRED TO A LATER DATE. | | | SEE BELOW. | | | 107.3.4.2 DEFERRED SUBMITTALS. FOR THE PURPOSES OF THIS | | | SECTION, DEFERRED SUBMITTALS ARE DEFINED AS THOSE | | | PORTIONS OF THE DESIGN THAT ARE NOT SUBMITTED AT THE | | | TIME OF THE APPLICATION AND THAT ARE TO BE SUBMITTED TO | | | THE BUILDING OFFICIAL WITHIN A SPECIFIED PERIOD. | | | DEFERRAL OF ANY SUBMITTAL ITEMS SHALL HAVE THE PRIOR | | | APPROVAL OF THE BUILDING OFFICIAL. THE REGISTERED | | | DESIGN PROFESSIONAL IN RESPONSIBLE CHARGE SHALL LIST | | | THE DEFERRED SUBMITTALS ON THE CONSTRUCTION DOCUMENTS | | | FOR REVIEW BY THE BUILDING OFFICIAL. DOCUMENTS FOR | | | DEFERRED SUBMITTAL ITEMS SHALL BE SUBMITTED TO THE | | | REGISTERED DESIGN PROFESSIONAL IN RESPONSIBLE CHARGE | | | WHO SHALL REVIEW THEM AND FORWARD THEM TO THE BUILDING | | | OFFICIAL WITH A NOTATION INDICATING THAT THE DEFERRED | | | SUBMITTAL DOCUMENTS HAVE BEEN REVIEWED AND FOUND TO BE | | | IN GENERAL CONFORMANCE TO THE DESIGN OF THE BUILDING. | | | THE DEFERRED SUBMITTAL ITEMS SHALL NOT BE INSTALLED | | | UNTIL THE DEFERRED SUBMITTAL DOCUMENTS HAVE BEEN | | | APPROVED BY THE BUILDING OFFICIAL. | | | | | | 17) THE ROOF HATCH SHOWN ON THE PLANS DOES NOT COMPLY | | | WITH THE REQUIREMENTS FOR SIZE AND GUARDS. 1009.16 | | | STAIRWAY TO ROOF. IN BUILDINGS FOUR OR MORE STORIES | | | ABOVE GRADE PLANE, ONE STAIRWAY SHALL EXTEND TO THE | | | ROOF SURFACE, UNLESS THE ROOF HAS A SLOPE STEEPER THAN | | | FOUR UNITS VERTICAL IN 12 UNITS HORIZONTAL (33-PERCENT | | | SLOPE). IN BUILDINGS WITHOUT AN OCCUPIED ROOF, ACCESS | | | TO THE ROOF FROM THE TOP STORY SHALL BE PERMITTED TO BE | | | BY AN ALTERNATING TREAD DEVICE. | | | 1009.16.1 ROOF ACCESS. WHERE A STAIRWAY IS PROVIDED TO | | | A ROOF, ACCESS TO THE ROOF SHALL BE PROVIDED THROUGH A | | | PENTHOUSE COMPLYING WITH SECTION 1509.2. | | | EXCEPTION: IN BUILDINGS WITHOUT AN OCCUPIED ROOF, | | | ACCESS TO THE ROOF SHALL BE PERMITTED TO BE A ROOF | | | HATCH OR TRAP DOOR NOT LESS THAN 16 SQUARE FEET (1.5 | | | M2) IN AREA AND HAVING A MINIMUM DIMENSION OF 2 FEET | | | (610 MM). | | | 1009.16.2 PROTECTION AT ROOF HATCH OPENINGS. WHERE THE | | | ROOF HATCH OPENING PROVIDING THE REQUIRED ACCESS IS | | | LOCATED WITHIN 10 FEET (3049 MM) OF THE ROOF EDGE, SUCH | | | ROOF ACCESS OR ROOF EDGE SHALL BE PROTECTED BY GUARDS | | | INSTALLED IN ACCORDANCE WITH THE PROVISIONS OF SECTION | | | 1013. | | | | | | 18) ON SHEET A602, #4 THE ENLARGED STAIR PLAN FOR THE | | | SEVENTH FLOOR, THE ELEVATOR EQUIPMENT IS NOT LABELED | | | AND SOME OF THE DIMENSIONS OF THE ROOM AND IT'S STAIR | | | LANDING ARE MISSING. FBC 107.2.1 | | | | | | 19) THE STAIR PLANS ON SHEET A602 HAVE ARE SPECIFIED AS | | | BEING 1/4" SCALE AND THEY ARE ACTUALLY 3/8" SCALE. FBC | | | 107.2.1 | | | | | | 20) THE PLANS SHOW A SHIPS LADDER FOR ACCESS TO THE | | | ELEVATOR EQUIPMENT ROOM. THE ROOM FOR ELEVATOR | | | EQUIPMENT THAT MUST BE ACCESSED FOR MAINTENANCE IS | | | REQUIRED TO BE ACCESSED BY A STAIRWAY. FBC 1009.17 | | | | | | 21) SHOW COMPLIANCE WITH FBC 1009.3.1.4 OPENINGS. | | | OPENINGS IN AN EXIT ACCESS STAIRWAY ENCLOSURE SHALL BE | | | PROTECTED IN ACCORDANCE WITH SECTION 716 AS REQUIRED | | | FOR FIRE BARRIERS. DOORS SHALL BE SELF- OR | | | AUTOMATIC-CLOSING BY SMOKE DETECTION IN ACCORDANCE WITH | | | SECTION 716.5.9.3. | | | 1009.3.1.4.1 PROHIBITED OPENINGS. OPENINGS OTHER THAN | | | THOSE NECESSARY FOR THE PURPOSE OF THE EXIT ACCESS | | | STAIRWAY ENCLOSURE SHALL NOT BE PERMITTED IN EXIT | | | ACCESS STAIRWAY ENCLOSURES. THE ELEVATOR EQUIPMENT ROOM | | | IS NOT ALLOWED TO OPEN INTO THE EXIT ACCESS STAIRWAY AS | | | SHOWN ON THE PLANS. | | | | | | 22) SHOW COMPLIANCE WITH FBC 1009.3.1.2 FIRE-RESISTANCE | | | RATING. EXIT ACCESS STAIRWAY ENCLOSURES SHALL HAVE A | | | FIRE-RESISTANCE RATING OF NOT LESS THAN 2 HOURS WHERE | | | CONNECTING FOUR STORIES OR MORE. | | | | | | 23) SHOW COMPLIANCE WITH FBC 1022.5 PENETRATIONS. | | | PENETRATIONS INTO AND OPENINGS THROUGH INTERIOR EXIT | | | STAIRWAYS AND RAMPS ARE PROHIBITED EXCEPT FOR REQUIRED | | | EXIT DOORS, EQUIPMENT AND DUCTWORK NECESSARY FOR | | | INDEPENDENT VENTILATION OR PRESSURIZATION, SPRINKLER | | | PIPING, STANDPIPES, ELECTRICAL RACEWAY FOR FIRE | | | DEPARTMENT COMMUNICATION SYSTEMS AND ELECTRICAL RACEWAY | | | SERVING THE INTERIOR EXIT STAIRWAY AND RAMP AND | | | TERMINATING AT A STEEL BOX NOT EXCEEDING 16 SQUARE | | | INCHES (0.010 M2). SUCH PENETRATIONS SHALL BE PROTECTED | | | IN ACCORDANCE WITH SECTION 714. THERE SHALL BE NO | | | PENETRATIONS OR COMMUNICATING OPENINGS, WHETHER | | | PROTECTED OR NOT, BETWEEN ADJACENT INTERIOR EXIT | | | STAIRWAYS AND RAMPS. | | | | | | 24) SHOW COMPLIANCE WITH FBC 3002.1 HOISTWAY ENCLOSURE | | | PROTECTION. ELEVATOR, DUMBWAITER AND OTHER HOISTWAY | | | ENCLOSURES SHALL BE SHAFT ENCLOSURES COMPLYING WITH | | | SECTION 713. FBC 713.4 FIRE-RESISTANCE RATING. SHAFT | | | ENCLOSURES SHALL HAVE A FIRE-RESISTANCE RATING OF NOT | | | LESS THAN 2 HOURS WHERE CONNECTING FOUR STORIES OR | | | MORE, AND NOT LESS THAN 1 HOUR WHERE CONNECTING LESS | | | THAN FOUR STORIES. THE NUMBER OF STORIES CONNECTED BY | | | THE SHAFT ENCLOSURE SHALL INCLUDE ANY BASEMENTS BUT NOT | | | ANY MEZZANINES. SHAFT ENCLOSURES SHALL HAVE A | | | FIRE-RESISTANCE RATING NOT LESS THAN THE FLOOR ASSEMBLY | | | PENETRATED, BUT NEED NOT EXCEED 2 HOURS. SHAFT | | | ENCLOSURES SHALL MEET THE REQUIREMENTS OF SECTION | | | 703.2.1. | | | | | | 25) SHOW COMPLIANCE WITH FBC 3002.4 ELEVATOR CAR TO | | | ACCOMMODATE AMBULANCE STRETCHER. ANY BUILDING THAT IS | | | MORE THAN THREE STORIES HIGH OR IN WHICH THE VERTICAL | | | DISTANCE BETWEEN THE BOTTOM TERMINAL LANDING AND THE | | | TOP TERMINAL LANDING EXCEEDS 25 FEET (7620 MM), MUST BE | | | CONSTRUCTED TO CONTAIN AT LEAST ONE PASSENGER ELEVATOR | | | THAT IS OPERATIONAL FOR BUILDING OCCUPANTS AND FIRE | | | DEPARTMENT EMERGENCY ACCESS TO ALL FLOORS. THE ELEVATOR | | | CAR SHALL BE OF SUCH A SIZE AND ARRANGEMENT TO | | | ACCOMMODATE AN AMBULANCE STRETCHER 24 INCHES BY 76 | | | INCHES (610 MM BY 2134 MM) WITH NOT LESS THAN 5-INCH | | | (127 MM) RADIUS CORNERS, IN THE HORIZONTAL, OPEN | | | POSITION AND SHALL BE IDENTIFIED BY THE INTERNATIONAL | | | SYMBOL FOR EMERGENCY MEDICAL SERVICES (STAR OF LIFE). | | | THE SYMBOL SHALL NOT BE LESS THAN 3 INCHES (76 MM) IN | | | HEIGHT AND SHALL BE PLACED INSIDE ON BOTH SIDES OF THE | | | HOISTWAY DOOR FRAME. | | | | | | 26) 3006.4 MACHINE ROOMS AND MACHINERY SPACES. ELEVATOR | | | MACHINE ROOMS AND MACHINERY SPACES SHALL BE ENCLOSED | | | WITH FIRE BARRIERS CONSTRUCTED IN ACCORDANCE WITH | | | SECTION 707 OR HORIZONTAL ASSEMBLIES CONSTRUCTED IN | | | ACCORDANCE WITH SECTION 711, OR BOTH. THE | | | FIRE-RESISTANCE RATING SHALL BE NOT LESS THAN THE | | | REQUIRED RATING OF THE HOISTWAY ENCLOSURE SERVED BY THE | | | MACHINERY. OPENINGS IN THE FIRE BARRIERS SHALL BE | | | PROTECTED WITH ASSEMBLIES HAVING A FIRE PROTECTION | | | RATING NOT LESS THAN THAT REQUIRED FOR THE HOISTWAY | | | ENCLOSURE DOORS. | | | EXCEPTIONS: 1. WHERE MACHINE ROOMS AND MACHINERY SPACES | | | DO NOT ABUT AND HAVE NO OPENINGS TO THE HOISTWAY | | | ENCLOSURE THEY SERVE THE FIRE BARRIERS CONSTRUCTED IN | | | ACCORDANCE WITH SECTION 707 OR HORIZONTAL ASSEMBLIES | | | CONSTRUCTED IN ACCORDANCE WITH SECTION 711, OR BOTH, | | | SHALL BE PERMITTED TO BE REDUCED TO A 1-HOUR | | | FIRE-RESISTANCE RATING. | | | | | | 27) F] 913.2 PROTECTION AGAINST INTERRUPTION OF | | | SERVICE. THE FIRE PUMP, DRIVER AND CONTROLLER SHALL BE | | | PROTECTED IN ACCORDANCE WITH NFPA 20 AGAINST POSSIBLE | | | INTERRUPTION OF SERVICE THROUGH DAMAGE CAUSED BY | | | EXPLOSION, FIRE, FLOOD, EARTHQUAKE, RODENTS, INSECTS, | | | WINDSTORM, FREEZING, VANDALISM AND OTHER ADVERSE | | | CONDITIONS. | | | 913.2.1 PROTECTION OF FIRE PUMP ROOMS. FIRE PUMPS SHALL | | | BE LOCATED IN ROOMS THAT ARE SEPARATED FROM ALL OTHER | | | AREAS OF THE BUILDING BY 2-HOUR FIRE BARRIERS | | | CONSTRUCTED IN ACCORDANCE WITH SECTION 707 OR 2-HOUR | | | HORIZONTAL ASSEMBLIES CONSTRUCTED IN ACCORDANCE WITH | | | SECTION 711, OR BOTH. | | | EXCEPTIONS: | | | 1. IN OTHER THAN HIGH-RISE BUILDINGS, SEPARATION BY | | | 1-HOUR FIRE BARRIERS CONSTRUCTED IN ACCORDANCE WITH | | | SECTION 707 OR 1-HOUR HORIZONTAL ASSEMBLIES CONSTRUCTED | | | IN ACCORDANCE WITH SECTION 711, OR BOTH, SHALL BE | | | PERMITTED IN BUILDINGS EQUIPPED THROUGHOUT WITH AN | | | AUTOMATIC SPRINKLER SYSTEM IN ACCORDANCE WITH SECTION | | | 903.3.1.1 OR 903.3.1.2. | | | | | | 2. SEPARATION IS NOT REQUIRED FOR FIRE PUMPS PHYSICALLY | | | SEPARATED IN ACCORDANCE WITH NFPA 20. | | | | | | 28) IDENTIFY THE FIRE RATED WALLS ON THE PLANS. FBC | | | 107.2.1 | | | | | | 29) IN ORDER TO REDUCE PLAN REVIEW TIME, PLEASE SUBMIT | | | A RESPONSE LETTER INDICATING HOW EACH OF THE REVIEW | | | COMMENTS HAS BEEN ADDRESSED. | | | | | | | | | | | | | | | |
|
|
| Review Stop |
E |
ELECTRICAL |
| Rev No |
3 |
Status |
P |
Date |
2019-05-02 |
|
|
Cont ID |
|
| Sent By |
jpearson |
Date |
2019-05-02 |
Time |
15:10 |
Rev Time |
0.00 |
| Received By |
jpearson |
Date |
2019-05-02 |
Time |
13:50 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
E |
ELECTRICAL |
| Rev No |
2 |
Status |
F |
Date |
2019-04-11 |
|
|
Cont ID |
|
| Sent By |
jpearson |
Date |
2019-04-11 |
Time |
10:53 |
Rev Time |
0.00 |
| Received By |
jpearson |
Date |
2019-04-10 |
Time |
10:09 |
Sent To |
I |
|
| Notes |
| 2019-04-11 10:53:12 | CODES IN EFFECT: | | | FBC = FLORIDA BUILDING CODE 2017 6TH EDITION | | | WPB FBC = WEST PALM BEACH AMENDMENTS TO THE FBC 2017 | | | 6TH ED, CHAPTER 1. | | | FBC EC = FLORIDA BUILDING CODE ENERGY CONSERVATION 2017 | | | 6TH EDITION | | | FBC RE = FLORIDA RESIDENTIAL CODE 2017 6TH EDITION | | | NEC = NFPA 70 2014 EDITION, NATIONAL ELECTRICAL CODE | | | FS = FLORIDA STATUTES | | | | | | ELECTRICAL REVIEW STATUS: DENIED, SEE COMMENTS BELOW. | | | | | | PREVIOUS COMMENTS THAT HAVE BEEN ADDRESSED | | | SATISFACTORILY ARE MARKED AS CORRECTED. PREVIOUS | | | COMMENTS THAT HAVE NOT BEEN ADDRESSED SATISFACTORILY | | | HAVE ADDITIONAL COMMENTS IN PARENTHESES. ANY NEW | | | COMMENTS WILL BE LISTED AFTER PREVIOUS COMMENTS. | | | | | | 1. CORRECTED. | | | 2. CORRECTED. | | | 3. CORRECTED. | | | 4. SMOKE ALARMS MUST BE INSTALLED AT LEAST THREE FEET | | | FROM BATHROOM DOOR, THREE FEET FROM CEILING FANS, AND | | | THREE FEET FROM ANY MECHANICAL DUCT. PROVIDE | | | CORRECTIONS. NFPA 72:29.8.3.4 (FIRST FLLOR STILL SHOWS | | | SMOKE ALARMS TOO CLOSE TO BATHROOM AND TO FAN IN GUEST | | | BEDROOM.) | | | 5. CORRECTED. | | | 7. ALL RECEPTACLE OUTLETS IN LAUNDRY REQUIRE GFCI | | | PROTECTION. PROVIDE CORRECTION. NEC 210.8 (COMMENT | | | STATES "ALL" RECEPTACLES IN LAUNDRY. SOME HAVE NOT BEEN | | | CORRECTED TO GFCI PROTECTED.) | | | 8. CORRECTED. | | | 9. CORRECTED. | | | 10. CORRECTED. | | | 11. CORRECTED. | | | 12. CORRECTED. | | | 13. CORRECTED. | | | 14. CORRECTED. | | | 15. CORRECTED. | | | 16. CORRECTED. | | | 17. CORRECTED. | | | 18. CORRECTED. | | | | | | NEW COMMENTS: | | | | | | 19. WALK IN CLOSETS SHOW A RECEPTACLE "ABOVE CEILING". | | | PROVIDE CLARIFICATION. HOW WILL THIS RECEPTACLE BE | | | ACCESSED IF IT IS ABOVE THE CEILING? WHAT IS PURPOSE OF | | | THIS RECEPTACLE? WPB FBC 107.2.1 | | | 20. REVISED RISER DIAGRAM SHOWS THE JOCKEY PUMP IN THE | | | FIRE PUMP ROOM BEING FED FROM THE FIRE PUMP CONTROLLER. | | | THIS IS NOT PERMITTED PER CODE. PROVIDE CORRECTION. NEC | | | 695.6(E), 695.6(I)(6) | | | 21. FEED FROM THE 200 AMP METER TO THE FIRE PUMP | | | CONTROLLER SHOULD NOT INCLUDE AND EQUIPMENT GROUNDING | | | CONDUCTOR. HOWEVER, THIS SERVICE SHOULD BE TIED TO THE | | | GROUNDING ELECTRODE SYSTEM. PROVIDE CORRECTION. NEC | | | 250.6, 250.50 | | | | | | END OF COMMENTS. | | | | | | PLEASE NOTE: SUBMITTAL OF ADDITIONAL AND/OR REVISED | | | MATERIALS MAY RESULT IN NEW PLAN REVIEW COMMENTS. WHEN | | | RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE | | | LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY | | | RESUBMITTAL FORM. ADDITIONALLY, INSERT CORRECTED PAGES | | | INTO THE ORIGINAL SUBMITTAL AND REMOVE OR VOID THE | | | PREVIOUSLY REVIEWED SHEETS. | | | | | | SINCERELY, | | | | | | JOHN PEARSON | | | ELECTRICAL PLANS EXAMINER | | | 561-805-6746 | | | [email protected] | | | | | | |
|
|
| Review Stop |
E |
ELECTRICAL |
| Rev No |
1 |
Status |
F |
Date |
2018-06-13 |
|
|
Cont ID |
|
| Sent By |
jpearson |
Date |
2018-06-13 |
Time |
15:56 |
Rev Time |
0.00 |
| Received By |
jpearson |
Date |
2018-06-13 |
Time |
08:04 |
Sent To |
|
|
| Notes |
| 2018-06-13 15:56:30 | CODES IN EFFECT: | | | FBC = FLORIDA BUILDING CODE 2017 6TH EDITION | | | WPB FBC = WEST PALM BEACH AMENDMENTS TO THE FBC 2017 | | | 6TH ED, CHAPTER 1. | | | FBC EC = FLORIDA BUILDING CODE ENERGY CONSERVATION 2017 | | | 6TH EDITION | | | FBC RE = FLORIDA RESIDENTIAL CODE 2017 6TH EDITION | | | NEC = NFPA 70 2014 EDITION, NATIONAL ELECTRICAL CODE | | | FS = FLORIDA STATUTES | | | | | | ELECTRICAL REVIEW STATUS: DENIED, SEE COMMENTS BELOW. | | | | | | 1. PLAN SHOWS A PENDANT LIGHT OVER TUB IN MASTER BATH. | | | NO PARTS OF CORD-CONNECTED LUMINAIRES, CHAIN-, CABLE-, | | | OR CORD-SUSPENDED LUMINAIRES, LIGHTING TRACK, PENDANTS, | | | OR CEILING-SUSPENDED (PADDLE) FANS SHALL BE LOCATED | | | WITHIN A ZONE MEASURED 3 FEET HORIZONTALLY AND 8 FEET | | | VERTICALLY FROM THE TOP OF THE BATHTUB RIM OR SHOWER | | | STALL THRESHOLD. PROVIDE CORRECTION. NEC 410.10(D) | | | 2. PLAN SHOWS PENDANT LIGHTS IN CLOTHES CLOSETS. PER | | | CODE: LIGHTING WITH OPEN OR PARTIALLY ENCLOSED LAMPS | | | AND PENDANT LUMINAIRES OR LAMPHOLDERS SHALL NOT BE | | | PERMITTED IN CLOTHES CLOSETS. PROVIDE CORRECTION. NEC | | | 410.16 | | | 3. SEVERAL AREAS DO NOT COMPLY WITH THE WALL SPACING | | | REQUIREMENTS FOR OUTLETS. RECEPTACLES SHALL BE | | | INSTALLED SO THAT NO POINT MEASURED HORIZONTALLY ALONG | | | THE FLOOR LINE OF ANY WALL SPACE IS MORE THAN 6 FEET | | | FROM A RECEPTACLE OUTLET. THE WALL SPACING REQUIREMENTS | | | FOR KITCHEN COUNTER SPACE STATE THAT RECEPTACLE OUTLETS | | | SHALL BE INSTALLED SO THAT NO POINT ALONG THE WALL LINE | | | IS MORE THAN 24 INCHES MEASURED HORIZONTALLY FROM A | | | RECEPTACLE OUTLET IN THAT SPACE. THE PLAN PROVIDED DOES | | | NOT MEET THIS CODE IN SOME AREAS. EXAMPLES INCLUDE THE | | | CONVERTIBLE STUDY ROOM, THE WALL FOR STAIRWELL FROM | | | FLOOR 1 TO 2, THE KITCHEN COUNTER ADJACENT TO PANTRY, | | | ETC. PROVIDE CORRECTIONS. NEC 210.52 | | | 4. SMOKE ALARMS MUST BE INSTALLED AT LEAST THREE FEET | | | FROM BATHROOM DOOR, THREE FEET FROM CEILING FANS, AND | | | THREE FEET FROM ANY MECHANICAL DUCT. PROVIDE | | | CORRECTIONS. NFPA 72:29.8.3.4 | | | 5. BE ADVISED THAT FIRE ALARM, LOW VOLTAGE SYSTEMS, | | | DAS, LIGHTNING PROTECTION, GENERATORS, COMMERCIAL HOOD | | | SYSTEMS, WALK IN COOLERS, SIGNS, SITE LIGHTING, AND | | | SWIMMING POOLS (WHERE APPLICABLE) ARE NOT INCLUDED IN | | | THE SCOPE OF THIS PLAN REVIEW. PROVIDE A BLOCK NOTE | | | INDICATING THE REQUIRED SEPARATE PERMITS AND PLAN | | | SUBMITTALS FOR ANY OF THESE SYSTEMS PRESENT. WPB FBC | | | 105.1, 107.2.1 | | | 6. PROVIDE GFCI PROTECTED RECEPTACLE OUTLETS ON EACH | | | BALCONY. NEC 210.52(E)(3) | | | 7. ALL RECEPTACLE OUTLETS IN LAUNDRY REQUIRE GFCI | | | PROTECTION. PROVIDE CORRECTION. NEC 210.8 | | | 8. ALL RECEPTACLE OUTLETS IN BATHROOMS REQUIRE GFCI | | | PROTECTION. PROVIDE CORRECTION. NEC 210.8 | | | 9. PROVIDE GFCI PROTECTION FOR DISHWASHERS. NEC | | | 210.8(D) | | | 10. ALL BRANCH CIRCUITS THAT SUPPLY 120-VOLT, | | | SINGLE-PHASE, 15- AND 20-AMPERE OUTLETS INSTALLED IN | | | KITCHENS, FAMILY ROOMS, DINING ROOMS, LIVING ROOMS, | | | PARLORS, LIBRARIES, DENS, BEDROOMS, SUN-ROOMS, | | | RECREATIONS ROOMS, CLOSETS, HALLWAYS, LAUNDRY AREAS AND | | | SIMILAR ROOMS OR AREAS SHALL BE AFCI PROTECTED. PROVIDE | | | CORRECTION. NEC 210.12 | | | 11. BREAKER FOR POOL PUMP REQUIRED TO BE GFCI | | | PROTECTED. PROVIDE CORRECTION. NEC 680.21(C) | | | 12. BREAKER FOR HOT TUB REQUIRED TO BE GFCI PROTECTED. | | | PROVIDE CORRECTION. NEC 680.43 | | | 13. PROVIDE TAMPER RESISTANT RECEPTACLES PER CODE. A | | | NOTE WILL SUFFICE. NEC 406.12 | | | 14. PROVIDE COMPLIANCE: A MINIMUM OF 75 PERCENT OF THE | | | LAMPS IN PERMANENTLY INSTALLED LIGHTING FIXTURES SHALL | | | BE HIGH-EFFICACY LAMPS OR A MINIMUM OF 75 PERCENT OF | | | THE PERMANENTLY INSTALLED LIGHTING FIXTURES SHALL | | | CONTAIN ONLY HIGH EFFICACY LAMPS. A NOTE WILL SUFFICE. | | | FBC EC C405.1, R404.1 | | | 15. PROVIDE NOTES TO INDICATE THE REQUIRED MARKING OF | | | SERVICE EQUIPMENT FOR AVAILABLE FAULT CURRENT PER CODE. | | | NEC 110.24 | | | 16. PROVIDE THE REQUIRED SERVICE AREA RECEPTACLE PER | | | CODE. NEC 210.64 | | | 17. PROVIDE INTERSYSTEM BONDING TERMINATION POINT AT | | | SERVICE. SHOW ON PLAN. NEC 250.94 | | | 18. PLAN IS NOT STAPLED TOGETHER CORRECTLY AND SHEETS | | | ARE FALLING OUT, PLEASE MAKE SURE THAT EACH SET IS | | | BOUND PROPERLY FOR RESUBMITTAL. WPB FBC 107.2.1.3 | | | | | | END OF COMMENTS. | | | | | | PLEASE NOTE: SUBMITTAL OF ADDITIONAL AND/OR REVISED | | | MATERIALS MAY RESULT IN NEW PLAN REVIEW COMMENTS. WHEN | | | RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE | | | LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY | | | RESUBMITTAL FORM. ADDITIONALLY, INSERT CORRECTED PAGES | | | INTO THE ORIGINAL SUBMITTAL AND REMOVE OR VOID THE | | | PREVIOUSLY REVIEWED SHEETS. | | | | | | SINCERELY, | | | | | | JOHN PEARSON | | | ELECTRICAL PLANS EXAMINER | | | 561-805-6746 | | | [email protected] | | | | | | |
|
|
| Review Stop |
E-LOWVOLT |
ELECTRICAL LOW VOLTAGE |
| Rev No |
1 |
Status |
P |
Date |
2019-05-02 |
|
|
Cont ID |
|
| Sent By |
jpearson |
Date |
2019-05-02 |
Time |
14:04 |
Rev Time |
0.00 |
| Received By |
jpearson |
Date |
2019-05-02 |
Time |
14:04 |
Sent To |
|
|
| Notes |
| 2019-05-02 14:04:51 | SEPARATE PERMITS REQUIRED FOR LOW VOLTAGE SYSTEMS. |
|
|
| Review Stop |
ENG |
ENGINEERING CSD |
| Rev No |
2 |
Status |
N |
Date |
2019-05-02 |
|
|
Cont ID |
|
| Sent By |
rrossano |
Date |
2019-05-02 |
Time |
|
Rev Time |
0.00 |
| Received By |
rrossano |
Date |
2019-05-02 |
Time |
|
Sent To |
I |
|
| Notes |
| 2019-05-02 15:39:25 | PROJECT HAS BEEN REVIEWED AND APPROVED THROUGH FORMAL | | | SITE DEVELOPMENT SUBMITTAL. |
|
|
| Review Stop |
ENG |
ENGINEERING CSD |
| Rev No |
1 |
Status |
F |
Date |
2018-06-15 |
|
|
Cont ID |
|
| Sent By |
shill |
Date |
2018-06-15 |
Time |
10:08 |
Rev Time |
0.00 |
| Received By |
shill |
Date |
2018-06-15 |
Time |
10:08 |
Sent To |
|
|
| Notes |
| 2018-06-15 10:08:18 | CONTACT ENGINEERING DEPARTMENT DIRECTLY AND SUBMIT | | | APPLICATION IF REQUIRED | | | HTTP://WWW.WPB.ORG/DEPARTMENTS/ENGINEERING-PUBLIC-WORKS | | | /FORMS,-PERMITS-APPLICATIONS | | | | | | ENGINEERING APPROVAL REQUIRED PRIOR TO PERMIT ISSUANCE | | | | | | MAIN PHONE: (561) 822-1200 | | | | | | |
|
|
| Review Stop |
FIRE |
FIRE DEPARTMENT |
| Rev No |
4 |
Status |
P |
Date |
2019-06-06 |
|
|
Cont ID |
|
| Sent By |
pleduc |
Date |
2019-06-06 |
Time |
|
Rev Time |
0.00 |
| Received By |
pleduc |
Date |
2019-06-06 |
Time |
15:53 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
FIRE |
FIRE DEPARTMENT |
| Rev No |
3 |
Status |
F |
Date |
2019-05-14 |
|
|
Cont ID |
|
| Sent By |
pleduc |
Date |
2019-05-14 |
Time |
|
Rev Time |
0.00 |
| Received By |
pleduc |
Date |
2019-05-14 |
Time |
13:36 |
Sent To |
|
|
| Notes |
| 2019-05-14 13:56:31 | THIS PLAN WAS REVIEWED AND FAILED BY PETER LEDUC, FIRE | | | MARSHAL, WITH THE FOLLOWING COMMENTS: | | | | | | | | | | | | | | | PREVIOUS COMMENT: | | | | | | 4) THERE IS NO INDICATION OF ELEVATORS BEING EQUIPPED | | | WITH A REGION 7 KEYWAY. | | | | | | CHAPTER 399 FLORIDA STATUTES. SECTION 399.15, SECTION | | | 17: | | | REGIONAL EMERGENCY ELEVATOR ACCESS ? | | | (1) IN ORDER TO PROVIDE EMERGENCY ACCESS TO ELEVATORS: | | | (A) FOR EACH BUILDING IN THIS STATE WHICH IS SIX OR | | | MORE STORIES IN HEIGHT, INCLUDING, BUT NOT LIMITED TO, | | | HOTELS AND CONDOMINIUMS, ON WHICH A BUILDING PERMIT IS | | | ISSUED AFTER SEPTEMBER 30, 2006, ALL OF THE KEYS FOR | | | ELEVATORS THAT ALLOW PUBLIC ACCESS, INCLUDING, BUT NOT | | | LIMITED TO, SERVICE AND FREIGHT ELEVATORS, MUST BE | | | KEYED SO AS TO ALLOW ALL ELEVATORS WITHIN EACH OF THE | | | SEVEN STATE EMERGENCY RESPONSE REGIONS TO OPERATE IN | | | FIRE EMERGENCY SITUATIONS WITH ONE MASTER ELEVATOR KEY. | | | | | | | | | PLEASE PROVIDE AN APPLICABLE NOTE OF ACKNOWLEDGEMENT | | | AND COMPLIANCE. | | | | | | | | | | | | | | | NEW COMMENT: | | | | | | | | | 1) PLEASE CLARIFY THE 4 HR FIRE RATING INDICATED FOR | | | THE ELEVATOR AND STAIRWELL SHAFTS ON THE LIFE SAFETY | | | SHEETS 1- 3, AND THE CALLOUT LISTING ON LS 4 INDICATING | | | 2 HR. | | | | | | WHICH IS CORRECT AND CORRECT. | | | | | | | | | | | | WHEN RESUBMITTING, PLEASE PROVIDE PLAN SHEET REVISION | | | CLOUDS OR NUMBERED NARRATIVE RESPONSES TO THE ABOVE. | | | | | | | | | ADDITIONAL COMMENTS MAY BE PROVIDED ON THE RE-SUBMITTAL | | | OF THE ABOVE. | | | | | | | | | PETER LEDUC | | | FIRE MARSHAL | | | 561-804-4709 | | | [email protected] | | | |
|
|
| Review Stop |
FIRE |
FIRE DEPARTMENT |
| Rev No |
2 |
Status |
F |
Date |
2019-03-27 |
|
|
Cont ID |
|
| Sent By |
pleduc |
Date |
2019-03-27 |
Time |
|
Rev Time |
0.00 |
| Received By |
pleduc |
Date |
2019-03-27 |
Time |
12:58 |
Sent To |
|
|
| Notes |
| 2019-03-27 13:18:43 | THIS PLAN WAS REVIEWED AND FAILED BY PETER LEDUC, FIRE | | | MARSHAL, WITH THE FOLLOWING COMMENTS: | | | | | | | | | | | | 1) THERE ARE CLEAR INDICATIONS THAT THE COMMENTS FROM | | | FIRE HAVE NOT BEEN ADDRESSED. | | | | | | ON REVIEW OF FIRE COMMENTS NO DISCERNABLE DIFFERENCES | | | CAN BE MADE TO THE PLAN SHEETS. | | | | | | | | | 2) PLEASE ADDRESS EACH FIRE COMMENT INDICIDUALLY AS | | | NUMBER WITH AN APPLICABLE REPONSE AND PAGE CHANGES IN | | | CLOUDED FORM. | | | | | | IF NO CHANGES WERE MADE PLESE PROVIDE A NARRATIVE AND | | | APPLICABLE CODE REFERNCES. | | | | | | | | | 3) WHEN RESUBMITTING, PLEASE PROVIDE PLAN SHEET | | | REVISION CLOUDS OR NUMBERED NARRATIVE RESPONSES TO THE | | | ABOVE. | | | | | | | | | | | | 4) ADDITIONAL COMMENTS MAY BE PROVIDED ON THE | | | RE-SUBMITTAL OF THE ABOVE. | | | | | | | | | | | | PETER LEDUC | | | FIRE MARSHAL | | | 561-804-4709 | | | [email protected] | | | |
|
|
| Review Stop |
FIRE |
FIRE DEPARTMENT |
| Rev No |
1 |
Status |
F |
Date |
2018-05-14 |
|
|
Cont ID |
|
| Sent By |
pleduc |
Date |
2018-05-14 |
Time |
|
Rev Time |
0.00 |
| Received By |
pleduc |
Date |
2018-05-07 |
Time |
16:55 |
Sent To |
|
|
| Notes |
| 2018-05-07 17:02:04 | THIS PLAN WAS REVIEWED AND APPROVED BY PETER LEDUC, | | | FIRE MARSHAL, WITH THE FOLLOWING COMMENTS: | | | | | | | | | | | | 1) SHEET CVR - THERE IS NOT INDICATION OF COMPLIANCE | | | WITH ANY FIRE CODE. | | | | | | THE PROPOSED PROJECT SHALL MEET THE REQUIREMENTS OF THE | | | 6TH EDITION OF FLORIDA FIRE PREVENTION CODE INCLUDING | | | THE 2015 EDITION OF NFPA 1 AND NFPA 101 AND ALL OTHER | | | APPLICABLE CODES OR STANDARDS. | | | FIRE SPRINKLER WORK SHALL COMPLY WITH THE REQUIREMENTS | | | OF NFPA 13, 2013 EDITION. | | | FIRE ALARM WORK SHALL COMPLY WITH THE REQUIREMENTS OF | | | NFPA 72, 2013 EDITION. | | | CONSTRUCTION WORK SHALL COMPLY WITH THE REQUIREMENTS OF | | | NFPA 241, 2013 EDITION. | | | FIRE EXTINGUISHERS SHALL COMPLY WITH THE REQUIREMENTS | | | OF NFPA 10, 2013 EDITION. | | | ELECTRIC WORK SHALL COMPLY WITH NFPA 70, 2014 EDITION. | | | | | | PLEASE REVIEW, ENSURE COMPLIANCE AND PROVIDE AN | | | APPLICABLE REVISION NOTE. | | | | | | | | | | | | 2) THERE IS NO SHEET INDICATING THE LIFE SAFETY PLAN. | | | | | | PER NFPA 1 | | | | | | 1.7.12 PLANS AND SPECIFICATIONS. | | | 1.7.12.1 THE AHJ SHALL HAVE THE AUTHORITY TO REQUIRE | | | PLANS AND | | | SPECIFICATIONS TO ENSURE COMPLIANCE WITH APPLICABLE | | | CODES AND | | | STANDARDS. | | | | | | | | | PLEASE PROVIDE A CCOMPLETE LIFE SAFETY PLAN THAT | | | ILLUSTRATE OCCUPANT LOADS, TRAVEL DISTANCES, COMMON | | | PATHS OF TRAVEL, DEAD-END CORRIDORS, EXIT SIGNS, | | | EMERGENCY LIGHTING, EXITS LEADING TO A PUBLIC WAY, FIRE | | | EXTINGUISHER LOCATIONS, AND ALL FIRE SAFETY FEATURES | | | AND EQUIPMENT. | | | | | | | | | | | | | | | 3) THERE IS NO INFORMATION REGARDING THE ELEVATORS. | | | | | | 30.5.3 ELEVATORS, ESCALATORS, AND CONVEYORS. ELEVATORS, | | | ESCALATORS, AND CONVEYORS SHALL COMPLY WITH THE | | | PROVISIONS OF | | | SECTION 9.4. | | | | | | 9.4.2.3 ELEVATORS IN ACCORDANCE WITH ASME A17.7/CSA | | | B44.7, | | | PERFORMANCE-BASED SAFETY CODE FOR ELEVATORS AND | | | ESCALATORS, | | | SHALL BE DEEMED TO COMPLY WITH ASME A17.1/CSA B44, | | | SAFETY | | | CODE FOR ELEVATORS AND ESCALATORS, OR ASME A17.3, | | | SAFETY CODE | | | FOR EXISTING ELEVATORS AND ESCALATORS. | | | | | | 9.4.3 FIRE FIGHTERS? EMERGENCY OPERATIONS. | | | 9.4.3.1 ALL NEW ELEVATORS SHALL CONFORM TO THE FIRE | | | FIGHTERS? | | | EMERGENCY OPERATIONS REQUIREMENTS OF ASME A17.1/CSA | | | B44, | | | SAFETY CODE FOR ELEVATORS AND ESCALATORS. | | | | | | ANY BUILDING THAT IS MORE THAN THREE STORIES HIGH OR IN | | | WHICH THE VERTICAL DISTANCE BETWEEN THE BOTTOM TERMINAL | | | LANDING AND THE TOP TERMINAL LANDING EXCEEDS 25 FEET | | | MUST BE CONSTRUCTED TO CONTAIN AT LEAST ONE PASSENGER | | | ELEVATOR THAT IS OPERATIONAL AND WILL ACCOMMODATE AN | | | AMBULANCE STRETCHER 76 INCHES LONG AND 24 INCHES WIDE | | | IN THE HORIZONTAL POSITION. | | | | | | | | | | | | | | | 4) THERE IS NO INDICATION OF ELEVATORS BEING EQUIPPED | | | WITH A REGION 7 KEYWAY. | | | | | | CHAPTER 399 FLORIDA STATUTES. SECTION 399.15, SECTION | | | 17: | | | REGIONAL EMERGENCY ELEVATOR ACCESS ? | | | (1) IN ORDER TO PROVIDE EMERGENCY ACCESS TO ELEVATORS: | | | (A) FOR EACH BUILDING IN THIS STATE WHICH IS SIX OR | | | MORE STORIES IN HEIGHT, INCLUDING, BUT NOT LIMITED TO, | | | HOTELS AND CONDOMINIUMS, ON WHICH A BUILDING PERMIT IS | | | ISSUED AFTER SEPTEMBER 30, 2006, ALL OF THE KEYS FOR | | | ELEVATORS THAT ALLOW PUBLIC ACCESS, INCLUDING, BUT NOT | | | LIMITED TO, SERVICE AND FREIGHT ELEVATORS, MUST BE | | | KEYED SO AS TO ALLOW ALL ELEVATORS WITHIN EACH OF THE | | | SEVEN STATE EMERGENCY RESPONSE REGIONS TO OPERATE IN | | | FIRE EMERGENCY SITUATIONS WITH ONE MASTER ELEVATOR KEY. | | | | | | | | | PLEASE PROVIDE AN APPLICABLE NOTE OF ACKNOWLEDGEMENT | | | AND COMPLIANCE. | | | | | | | | | | | | 5) THERE IS NO INDICATION OF THE TRAVEL DISTANCE FROM | | | THE ROOF TOP OBSERVATION DECK TO THE NEAREST EXIT. | | | | | | PER NFPA 101, CHAPTER 30, NEW APARTMENT BUILDINGS | | | | | | 30.2.4 NUMBER OF MEANS OF EGRESS. | | | 30.2.4.1 THE NUMBER OF MEANS OF EGRESS SHALL COMPLY | | | WITH 7.4. | | | | | | | | | 7.4* NUMBER OF MEANS OF EGRESS. | | | 7.4.1 GENERAL. | | | 7.4.1.1 THE NUMBER OF MEANS OF EGRESS FROM ANY BALCONY, | | | MEZZANINE, STORY, OR PORTION THEREOF SHALL BE NOT LESS | | | THAN TWO, | | | EXCEPT UNDER ONE OF THE FOLLOWING CONDITIONS: | | | (1) A SINGLE MEANS OF EGRESS SHALL BE PERMITTED WHERE | | | PERMITTED | | | IN CHAPTERS 11 THROUGH 43. | | | (2) A SINGLE MEANS OF EGRESS SHALL BE PERMITTED FOR A | | | MEZZANINE | | | OR BALCONY WHERE THE COMMON PATH OF TRAVEL LIMITATIONS | | | OF | | | CHAPTERS 11 THROUGH 43 ARE MET. | | | | | | 30.2.6.3.1 THE TRAVEL DISTANCE FROM A DWELLING UNIT | | | (APARTMENT) | | | ENTRANCE DOOR TO THE NEAREST EXIT SHALL NOT EXCEED 100 | | | FT (30 M). | | | | | | PLEASE PROVIDE THE ACTUAL DIMENSION OF THE TRAVEL | | | DISTANCE FROM THE REMOTE CORNER OF THE OBSERVATION DECK | | | TO THE NEAREST EXIT INDICATING COMPLIANCE WITH THE | | | ABOVE CODE. | | | | | | | | | | | | | | | 6) SHEET 602, 603, 701 - THERE IS AN INDICATION OF A | | | SPIRAL STAIR LEADING DOWN FROM THE OBSERVATION DECK. | | | THIS APPEARS TO BE THE ONLY EXIT FROM THIS OCCUPIABLE | | | FLOOR. | | | | | | SHOULD THE TRAVEL DISTANCE MEET THE REQUIRMENT ABOVE, | | | THERE IS NO INDICATION THAT THE SPIRAL STAIRS MEET THE | | | CODE. | | | | | | 30.2.2.3 STAIRS. | | | 30.2.2.3.1 STAIRS COMPLYING WITH 7.2.2 SHALL BE | | | PERMITTED. | | | 30.2.2.3.2 RESERVED. | | | 30.2.2.3.3 SPIRAL STAIRS COMPLYING WITH 7.2.2.2.3 SHALL | | | BE | | | PERMITTED WITHIN EACH DWELLING UNIT. | | | 30.2.2.3.4 WINDERS COMPLYING WITH 7.2.2.2.4 SHALL BE | | | PERMITTED | | | WITHIN EACH DWELLING UNIT. | | | | | | 7.2.2.2.3 SPIRAL STAIRS. | | | 7.2.2.2.3.1 WHERE SPECIFICALLY PERMITTED FOR INDIVIDUAL | | | OCCUPANCIES BY | | | CHAPTERS 11 THROUGH 43, SPIRAL STAIRS SHALL BE | | | PERMITTED AS A COMPONENT | | | IN A MEANS OF EGRESS IN ACCORDANCE WITH 7.2.2.2.3.2 | | | THROUGH 7.2.2.2.3.4. | | | 7.2.2.2.3.2 SPIRAL STAIRS SHALL BE PERMITTED, PROVIDED | | | THAT ALL OF THE | | | FOLLOWING CRITERIA ARE MET: | | | (1) RISER HEIGHTS SHALL NOT EXCEED 7 IN. (180 MM). | | | (2) THE STAIRWAY SHALL HAVE A TREAD DEPTH OF NOT LESS | | | THAN 11 IN. (280 | | | MM) FOR A PORTION OF THE STAIRWAY WIDTH SUFFICIENT TO | | | PROVIDE | | | EGRESS CAPACITY FOR THE OCCUPANT LOAD SERVED IN | | | ACCORDANCE WITH | | | 7.3.3.1. | | | (3) AT THE OUTER SIDE OF THE STAIRWAY, AN ADDITIONAL | | | 10? IN. (265 MM) | | | OF WIDTH SHALL BE PROVIDED CLEAR TO THE OTHER HANDRAIL, | | | AND THIS | | | WIDTH SHALL NOT BE INCLUDED AS PART OF THE REQUIRED | | | EGRESS CAPACITY. | | | (4) HANDRAILS COMPLYING WITH 7.2.2.4 SHALL BE PROVIDED | | | ON BOTH SIDES | | | OF THE SPIRAL STAIRWAY. | | | (5) THE INNER HANDRAIL SHALL BE LOCATED WITHIN 24 IN. | | | (610 MM), | | | MEASURED HORIZONTALLY, OF THE POINT WHERE A TREAD DEPTH | | | OF NOT LESS | | | THAN 11 IN. (280 MM) IS PROVIDED. | | | (6) THE TURN OF THE STAIRWAY SHALL BE SUCH THAT THE | | | OUTER HANDRAIL IS AT | | | THE RIGHT SIDE OF DESCENDING USERS. | | | | | | PLEASE PROVIDE DETAILS. | | | | | | | | | | | | 7) A SHEETS - THERE IS NO INDICATION OF THE EXIT | | | STAIRWELLS BEING 1 HOUR FIRE RATED. | | | | | | PER NFPA 101, CHAPTER 30 | | | | | | 30.2.2 MEANS OF EGRESS COMPONENTS. | | | 30.2.2.1 GENERAL. | | | 30.2.2.1.1 COMPONENTS OF MEANS OF EGRESS SHALL BE | | | LIMITED TO THE | | | TYPES DESCRIBED IN 30.2.2.2 THROUGH 30.2.2.12. | | | 30.2.2.1.2 IN BUILDINGS PROTECTED THROUGHOUT BY AN | | | APPROVED, | | | SUPERVISED AUTOMATIC SPRINKLER SYSTEM IN ACCORDANCE | | | WITH 30.3.5, | | | EXIT ENCLOSURES SHALL HAVE A MINIMUM 1-HOUR FIRE | | | RESISTANCE RATING, | | | AND DOORS SHALL HAVE A MINIMUM 1-HOUR FIRE PROTECTION | | | RATING. | | | | | | PLEASE PROVIDE DETAILS AND INDICATIONS | | | | | | | | | | | | 8) SHEET A 601 - THERE ARE NO INDICATIONS THAT THE DOOS | | | OF THE STAIRWELLS ARE 1 HOUR FIRE RATED IN THE DOOR | | | SCHEDULE. | | | | | | 30.2.2 MEANS OF EGRESS COMPONENTS. | | | 30.2.2.1 GENERAL. | | | 30.2.2.1.1 COMPONENTS OF MEANS OF EGRESS SHALL BE | | | LIMITED TO THE | | | TYPES DESCRIBED IN 30.2.2.2 THROUGH 30.2.2.12. | | | 30.2.2.1.2 IN BUILDINGS PROTECTED THROUGHOUT BY AN | | | APPROVED, | | | SUPERVISED AUTOMATIC SPRINKLER SYSTEM IN ACCORDANCE | | | WITH 30.3.5, | | | EXIT ENCLOSURES SHALL HAVE A MINIMUM 1-HOUR FIRE | | | RESISTANCE RATING, | | | AND DOORS SHALL HAVE A MINIMUM 1-HOUR FIRE PROTECTION | | | RATING. | | | | | | PLEASE PROVIDE DETAILS | | | | | | | | | | | | 9) SHEET A 601 - THERE ARE NO INDICATION OF ANY DOOR | | | HARDWARE IN THE DOOR SCHEDULE. | | | | | | 7.2.1.5.3 LOCKS, IF PROVIDED, SHALL NOT REQUIRE THE USE | | | OF A KEY, A | | | TOOL, OR SPECIAL KNOWLEDGE OR EFFORT FOR OPERATION FROM | | | THE EGRESS | | | SIDE. | | | | | | 7.2.1.7 PANIC HARDWARE AND FIRE EXIT HARDWARE. | | | 7.2.1.7.1 WHERE A DOOR ASSEMBLY IS REQUIRED TO BE | | | EQUIPPED WITH | | | PANIC OR FIRE EXIT HARDWARE, SUCH HARDWARE SHALL MEET | | | ALL OF THE | | | FOLLOWING CRITERIA: | | | (1) IT SHALL CONSIST OF A CROSS BAR OR A PUSH PAD, THE | | | ACTUATING | | | PORTION OF WHICH EXTENDS ACROSS NOT LESS THAN ONE-HALF | | | OF THE | | | WIDTH OF THE DOOR LEAF. | | | (2) IT SHALL BE MOUNTED AS FOLLOWS: | | | (A) NEW INSTALLATIONS SHALL BE NOT LESS THAN 34 IN. | | | (865 MM), | | | AND NOT MORE THAN 48 IN. (1220 MM), ABOVE THE FLOOR. | | | (B) EXISTING INSTALLATIONS SHALL BE NOT LESS THAN 30 | | | IN. (760 MM), | | | AND NOT MORE THAN 48 IN. (1220 MM), ABOVE THE FLOOR. | | | (3) IT SHALL BE CONSTRUCTED SO THAT A HORIZONTAL FORCE | | | NOT TO EXCEED | | | 15 LBF (66 N) ACTUATES THE CROSS BAR OR PUSH PAD AND | | | LATCHES. | | | 7.2.1.7.2* ONLY APPROVED FIRE EXIT HARDWARE SHALL BE | | | USED ON FIRE | | | PROTECTION-RATED DOOR ASSEMBLIES. NEW PANIC HARDWARE | | | AND NEW | | | FIRE EXIT HARDWARE SHALL COMPLY WITH ANSI/UL 305, | | | STANDARD FOR | | | SAFETY PANIC HARDWARE, AND ANSI/BHMA A156.3, EXIT | | | DEVICES. | | | | | | 7.2.1.8 SELF-CLOSING DEVICES. | | | 7.2.1.8.1* A DOOR LEAF NORMALLY REQUIRED TO BE KEPT | | | CLOSED SHALL | | | NOT BE SECURED IN THE OPEN POSITION AT ANY TIME AND | | | SHALL BE SELFCLOSING | | | OR AUTOMATIC-CLOSING IN ACCORDANCE WITH 7.2.1.8.2, | | | UNLESS | | | OTHERWISE PERMITTED BY 7.2.1.8.3. | | | | | | PLEASE PROVIDE FOR THE APPLICABLE HARDWARE OF EACH TYPE | | | OF DOOR. | | | | | | | | | | | | | | | 10) THERE ARE NO INDICATION OF ANY 61G DOCUMENTS FOR | | | FIRE SPRINKLERS. | | | | | | PER FLORIDA ADMINISTRATIVE CODE SECTION 61G15-32.004, | | | FIRE PROTECTION ENGINEERING DOCUMENTS SHALL INCLUDE THE | | | POINT OF SERVICE FOR THE WATER SUPPLY, A LIST OF | | | APPLICABLE NFPA STANDARDS APPLICABLE TO THE PROJECT, | | | CLASSIFICATION OF HAZARD OCCUPANCY FOR EACH ROOM OR | | | AREA, SUPPRESSION SYSTEM TYPE, DESIGN DENSITIES, WATER | | | SUPPLY DATA (FIRE PUMP DATA, HYDRANT FLOW TEST DATA) | | | AND ANY PERFORMANCE BASED INFORMATION SUCH AS | | | PRE-ENGINEERED SYSTEMS. | | | | | | 61G15-32.003 COMMON REQUIREMENTS TO ALL FIRE PROTECTION | | | ENGINEERING | | | DOCUMENTS. | | | (1) THE FIRE PROTECTION SYSTEM ENGINEERING DOCUMENTS | | | SHALL PROVIDE THE ENGINEERING REQUIREMENTS TO BE USED | | | IN THE PREPARATION OF THE FIRE PROTECTION SYSTEM LAYOUT | | | DOCUMENTS AND TO INDICATE THE NATURE AND SCOPE OF THE | | | WORK, AND TO DESCRIBE, DETAIL, DIMENSION, LABEL AND | | | DEFINE THE FIRE PROTECTION COMPONENTS, SYSTEM(S), | | | MATERIALS, ASSEMBLIES, EQUIPMENT AND ITS STRUCTURAL AND | | | UTILITY SUPPORT SYSTEM(S), INSOFAR AS THEY INVOLVE THE | | | SAFEGUARDING OF LIFE, HEALTH OR PROPERTY. | | | (2) THE FIRE PROTECTION SYSTEM ENGINEERING DOCUMENTS | | | SHALL SPECIFY THE APPLICABLE REQUIREMENTS FOR THE | | | ACCEPTANCE TESTING OF THE FIRE PROTECTION SYSTEM AND | | | COMPONENTS, WHICH SHALL BE BASED UPON APPLICABLE CODES | | | AND STANDARDS, WHERE AVAILABLE. | | | (3) THE OCCUPANCY OF THE AREA OR DESCRIPTION OF A | | | SPECIFIC HAZARD BEING PROTECTED BY THE FIRE PROTECTION | | | SYSTEM(S) SHALL BE SHOWN ON THE FIRE PROTECTION SYSTEM | | | ENGINEERING DOCUMENTS. | | | (4) THE APPLICABLE CODE AND STANDARD TO BE USED IN THE | | | PREPARATION OF THE FIRE PROTECTION SYSTEM LAYOUT | | | DOCUMENTS SHALL BE SHOWN ON THE FIRE PROTECTION SYSTEM | | | ENGINEERING DOCUMENTS. WHEN CODES AND STANDARDS ARE NOT | | | AVAILABLE OR APPLICABLE, AND SAID LAYOUT DOCUMENTS ARE | | | TO BE BASED ON ENGINEERING JUDGMENT, ANY REASONS AND | | | ASSUMPTIONS MADE TO DEVELOP THE FIRE PROTECTION CONCEPT | | | SHALL BE IDENTIFIED ON THE FIRE PROTECTION SYSTEM | | | ENGINEERING DOCUMENTS. | | | (5) STRUCTURAL SUPPORT AND STRUCTURAL OPENINGS REQUIRED | | | BY THE FIRE PROTECTION SYSTEM SHALL BE SHOWN ON THE | | | FIRE PROTECTION SYSTEM ENGINEERING DOCUMENTS AND SHALL | | | BE REFERENCED ON STRUCTURAL ENGINEERING DOCUMENTS. | | | (6) WHEN LAYOUT DOCUMENTS CONTAIN MATERIAL DEVIATION | | | FROM THE ENGINEER OF RECORD'S FIRE PROTECTION SYSTEM | | | ENGINEERING DOCUMENT, SUCH LAYOUT DOCUMENTS ARE NOT | | | COMPLIANT UNLESS THEY ARE ACCOMPANIED BY REVISED | | | ENGINEERING DOCUMENTS MADE AND SEALED BY THE ENGINEER | | | OF RECORD FOR THE FIRE PROTECTION SYSTEM. | | | (7) REQUIREMENTS FOR ACTIVATION CONTROL SYSTEMS, | | | SEQUENCE, OPERATING PARAMETERS, INTERLOCKS, SAFETY | | | RELATED DEVICES, INDICATORS AND ALARMS, SHALL BE SHOWN | | | ON THE FIRE PROTECTION SYSTEM ENGINEERING DOCUMENTS, | | | UNLESS SHOWN ON OTHER RELATED DOCUMENTS. | | | (8) ANY INFORMATION DEEMED APPROPRIATE BY THE ENGINEER | | | OF RECORD TO ASSIST THE AUTHORITY HAVING JURISDICTION | | | IN UNDERSTANDING THE OWNER?S INTENDED USE AND PROPOSED | | | PROTECTION OF THE BUILDING OR FACILITY AND TO PROVIDE | | | SUFFICIENT DIRECTION TO THE INSTALLATION CONTRACTOR OR | | | OTHER INTERESTED PARTIES REGARDING THE LAYOUT OF THE | | | SYSTEM(S), SHALL BE INCLUDED IN THE FIRE PROTECTION | | | SYSTEM ENGINEERING DOCUMENTS. | | | SPECIFIC AUTHORITY 471.008, 471.033(2), FS | | | LAW IMPLEMENTED 471.005(7), 471.033(2), FS | | | HISTORY?NEW 5-19-93, FORMERLY 21H-32.003, AMENDED | | | 4-2-2000, 6-26-01 | | | | | | 61G15-32.004 DESIGN OF WATER BASED FIRE PROTECTION | | | SYSTEMS. | | | (1) WATER BASED FIRE PROTECTION SYSTEMS INCLUDE, BUT | | | ARE NOT LIMITED TO, AUTOMATIC SPRINKLER SYSTEMS OF WET, | | | DRY, FINE WATER SPRAY (MIST), MANUAL, AND DELUGE VALVE | | | CONTROLLED TYPES, PUMPING SYSTEMS, STANDPIPES, FIRE | | | WATER MAINS AND DEDICATED FIRE PROTECTION WATER | | | SOURCES. | | | (2) TO ENSURE MINIMUM DESIGN QUALITY IN FIRE PROTECTION | | | SYSTEM ENGINEERING DOCUMENTS, SAID DOCUMENTS SHALL | | | INCLUDE AS A MINIMUM THE FOLLOWING INFORMATION WHEN | | | APPLICABLE: | | | (A) THE POINT OF SERVICE FOR THE FIRE PROTECTION WATER | | | SUPPLY AS DEFINED BY 633.021(18) F.S. | | | (B) APPLICABLE NFPA STANDARD TO BE APPLIED, OR IN THE | | | CASE WHERE NO SUCH STANDARD EXISTS, THE ENGINEERING | | | STUDY, JUDGMENTS, AND/OR PERFORMANCE BASED ANALYSIS AND | | | CONCLUSIONS. | | | (C) CLASSIFICATION OF HAZARD OCCUPANCY FOR EACH ROOM OR | | | AREA. | | | (D) DESIGN APPROACH, WHICH INCLUDES SYSTEM TYPE, | | | DENSITIES, DEVICE TEMPERATURE RATING, AND SPACING FOR | | | EACH SEPARATE 42 HAZARD OCCUPANCY. | | | (E) CHARACTERISTICS OF WATER SUPPLY TO BE USED, SUCH AS | | | MAIN SIZE AND LOCATION, WHETHER IT IS DEAD-END OR | | | CIRCULATING; AND IF DEAD-END, THE DISTANCE TO THE | | | NEAREST CIRCULATING MAIN, AS WELL AS ITS MINIMUM | | | DURATION AND RELIABILITY FOR THE MOST HYDRAULICALLY | | | DEMANDING DESIGN AREA. | | | (F) WHEN PRIVATE OR PUBLIC WATER SUPPLIES ARE USED, THE | | | FLOW TEST DATA, INCLUDING DATE AND TIME OF TEST, WHO | | | CONDUCTED TEST OR SUPPLIED INFORMATION, TEST ELEVATION, | | | STATIC GAUGE PRESSURE AT NO FLOW, FLOW RATE WITH | | | RESIDUAL GAUGE PRESSURE, HYDRANT BUTT COEFFICIENT, AND | | | LOCATION OF TEST IN RELATION TO THE HYDRAULIC POINT OF | | | SERVICE. | | | (G) VALVING AND ALARM REQUIREMENTS TO MINIMIZE | | | POTENTIAL FOR IMPAIRMENTS AND UNRECOGNIZED FLOW OF | | | WATER. | | | (H) MICROBIAL INDUCED CORROSION (MIC). THE ENGINEER OF | | | RECORD SHALL MAKE REASONABLE EFFORTS TO IDENTIFY WATER | | | SUPPLIES THAT COULD LEAD TO MICROBIAL INDUCED CORROSION | | | (MIC). SUCH EFFORTS MAY CONSIST OF DISCUSSIONS WITH THE | | | LOCAL WATER PURVEYOR AND/OR FIRE OFFICIAL, FAMILIARITY | | | WITH CONDITIONS IN THE LOCAL AREA, OR LABORATORY | | | TESTING OF WATER SUPPLIES. WHEN CONDITIONS ARE FOUND | | | THAT MAY RESULT IN MIC CONTAMINATION OF THE FIRE | | | PROTECTION PIPING, THE ENGINEER SHALL DESIGN CORRECTIVE | | | MEASURES. | | | (I) BACKFLOW PREVENTION AND METERING SPECIFICATIONS AND | | | DETAILS TO MEET LOCAL WATER PURVEYOR REQUIREMENTS | | | INCLUDING MAXIMUM ALLOWABLE PRESSURE DROP. | | | (J) QUALITY AND PERFORMANCE SPECIFICATIONS OF ALL YARD | | | AND INTERIOR FIRE PROTECTION COMPONENTS. | | | (3) CONTRACTOR SUBMITTALS WHICH DEVIATE FROM THE ABOVE | | | MINIMUM DESIGN PARAMETERS SHALL BE CONSIDERED MATERIAL | | | DEVIATIONS AND REQUIRE SUPPLEMENTAL ENGINEERING | | | APPROVAL AND DOCUMENTATION. | | | (4) IN THE EVENT THE ENGINEER OF RECORD PROVIDES MORE | | | INFORMATION AND DIRECTION THAN IS ESTABLISHED ABOVE, HE | | | OR SHE SHALL BE HELD RESPONSIBLE FOR THE TECHNICAL | | | ACCURACY OF THE WORK IN ACCORDANCE WITH APPLICABLE | | | CODES, STANDARDS, AND SOUND ENGINEERING PRINCIPLES. | | | SPECIFIC AUTHORITY 471.008, 471.033(2), FS | | | LAW IMPLEMENTED 471.005(7), 471.033(2), FS | | | HISTORY?NEW 5-19-93, FORMERLY 21H-32.004, AMENDED | | | 4-2-2000, 6-26-01, 7-12-05 | | | | | | THESE DOCUMENTS, IN NARRATIVE OR DRAWINGS WITH THE | | | ABOVE REQUIRED INFORMATION SHALL BE SUBMITTED WITH THIS | | | MASTER PERMIT, SHOP DRAWINGS CAN THEN BE DEVELOPED AND | | | SUBMITTED UNDER SEPARATE PERMITS. | | | | | | | | | | | | | | | 11 ) WHEN RESUBMITTING, PLEASE PROVIDE PLAN SHEET | | | REVISION CLOUDS OR NUMBERED NARRATIVE RESPONSES TO THE | | | ABOVE. | | | | | | | | | | | | 12) ADDITIONAL COMMENTS MAY BE PROVIDED ON THE | | | RE-SUBMITTAL OF THE ABOVE. | | | | | | | | | PETER LEDUC | | | FIRE MARSHAL | | | 561-804-4709 | | | [email protected] | | | | | | | | | | | | | | | | | | 30.2.2.2.4 APARTMENT OCCUPANCIES SHALL BE EXEMPT FROM | | | THE REENTRY | | | PROVISIONS OF 7.2.1.5.8 WHERE THE EXIT ENCLOSURE SERVES | | | DIRECTLY ONLY ONE DWELLING UNIT PER FLOOR, AND SUCH | | | EXIT IS A | | | SMOKEPROOF ENCLOSURE IN ACCORDANCE WITH 7.2.3. | | | | | | |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
4 |
Status |
N |
Date |
2019-06-10 |
|
|
Cont ID |
|
| Sent By |
gjohnson |
Date |
2019-06-10 |
Time |
13:10 |
Rev Time |
0.00 |
| Received By |
gjohnson |
Date |
2019-05-30 |
Time |
14:14 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
3 |
Status |
N |
Date |
2019-05-14 |
|
|
Cont ID |
|
| Sent By |
lmarchan |
Date |
2019-05-14 |
Time |
14:34 |
Rev Time |
0.00 |
| Received By |
lmarchan |
Date |
2019-04-24 |
Time |
09:58 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
2 |
Status |
N |
Date |
|
|
|
Cont ID |
|
| Sent By |
|
Date |
2019-04-11 |
Time |
|
Rev Time |
0.00 |
| Received By |
lmarchan |
Date |
2019-03-19 |
Time |
13:54 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
1 |
Status |
N |
Date |
2018-07-10 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2018-07-10 |
Time |
11:25 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2018-05-03 |
Time |
14:27 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
IMPACT |
COUNTY IMPACT FEES |
| Rev No |
2 |
Status |
P |
Date |
2019-05-01 |
|
|
Cont ID |
|
| Sent By |
shill |
Date |
2019-05-01 |
Time |
15:17 |
Rev Time |
0.00 |
| Received By |
shill |
Date |
2019-05-01 |
Time |
15:17 |
Sent To |
|
|
| Notes |
| 2019-05-01 15:18:21 | MU-2018-16270, PAID $7984.78 | | | SEE REVIEW UNDER FOUNDATION PERMIT 17111142 | | | |
|
|
| Review Stop |
IMPACT |
COUNTY IMPACT FEES |
| Rev No |
1 |
Status |
F |
Date |
2018-06-25 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2018-06-25 |
Time |
10:25 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2018-06-25 |
Time |
10:25 |
Sent To |
|
|
| Notes |
| 2018-06-25 10:27:28 | BEFORE A PERMIT TO CONSTRUCT CAN BE ISSUED, IMPACT FEES | | | MUST BE PAID TO PALM BEACH COUNTY. UPON APPROVAL, ONE | | | SET OF PLANS SHALL BE SIGNED OUT AND SUBMITTED TO PALM | | | BEACH COUNTY FOR AN IMPACT FEE REVIEW. THE PLANS WITH | | | THE IMPACT FEE STAMP AND A COPY OF THE PAID RECEIPT | | | MUST BE RETURNED TO THE CITY BUILDING DEPARTMENT BEFORE | | | THE BUILDING PERMIT CAN BE ISSUED. FOR INFORMATION CALL | | | PALM BEACH COUNTY IMPACT FEES AT (561) 233-5025. | | | | | | |
|
|
| Review Stop |
M |
MECHANICAL (A/C) |
| Rev No |
4 |
Status |
P |
Date |
2019-06-05 |
|
|
Cont ID |
|
| Sent By |
ccole |
Date |
2019-06-05 |
Time |
09:50 |
Rev Time |
0.00 |
| Received By |
ccole |
Date |
2019-06-04 |
Time |
17:33 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
M |
MECHANICAL (A/C) |
| Rev No |
3 |
Status |
F |
Date |
2019-05-03 |
|
|
Cont ID |
|
| Sent By |
ccole |
Date |
2019-05-03 |
Time |
09:05 |
Rev Time |
0.00 |
| Received By |
ccole |
Date |
2019-05-02 |
Time |
16:56 |
Sent To |
|
|
| Notes |
| 2019-05-03 09:48:39 | 3RD REVIEW FBC-2017 MECHANICAL | | | PERMIT #18050056 | | | 5/3/19 | | | | | | CODES IN EFFECT: | | | | | | FBC B- FLORIDA BUILDING CODE SIXTH EDITION 2014 | | | FBC M- FLORIDA MECHANICAL CODE SIXTH EDITION 2014 | | | FBC EC- FLORIDA ENERGY CONSERVATION CODE SIXTH EDITION | | | 2014 | | | FBC FG- FLORIDA FUEL GAS CODE SIXTH EDITION 2014 | | | FS- FLORIDA STATUTES | | | FAC- FLORIDA ADMINISTRATIVE CODE | | | WPB- WEST PALM BEACH AMENDMENTS TO THE FBC SIXTH | | | EDITION 2014 | | | | | | PLAN REVIEW RESULTS: DENIED. | | | | | | THIS 3RD REVIEW ITEMIZES THE 1ST AND 2ND REVIEW COMMENT | | | RESULTS. PLEASE NOTE THAT THE PREVIOUS REQUEST FOR A | | | RESPONSE NARRATIVE WAS IGNORED AGAIN. NARRATIVES HELP | | | TO EXPEDITE THE REVIEW PROCESS! | | | | | | | | | 1ST REVIEW: | | | | | | 1) OK, COMPLIED. | | | | | | 2) NON-COMPLIANCE: REQUESTED VENTILATION CALCULATIONS | | | NOT PROVIDED. PLEASE NOTE THAT AUTOMATICALLY CONTROLLED | | | SHUTOFF DAMPERS ARE REQUIRED FOR THE O/A INTAKE DUCTS- | | | SECTION C403.2.4.4 FBC EC. ENERGY CONSERVATION. | | | | | | 6) NON-COMPLIANCE: M-1, M-2, M-3: THE SIZES OF THE | | | LINEAR DIFFUSERS AND GRILLS SHOWN ON THE PLAN APPEAR TO | | | INCORRECT BECAUSE THE WIDTH MEASUREMENTS ARE SHOWN IN | | | FEET INSTEAD OF INCHES. | | | | | | 9) PARTIAL COMPLIANCE: | | | 1. THE SHAFT IN WHICH THE DUCT IS INSTALLED SHALL BE | | | CONSTRUCTED AND FIRE-RESISTANCE RATED AS REQUIRED BY | | | THE FLORIDA BUILDING CODE, BUILDING. | | | 8 .EXHAUST FAN OPERATION SHALL BE MONITORED IN AN | | | APPROVED LOCATION AND SHALL INITIATE AN AUDIBLE OR | | | VISUAL SIGNAL WHEN THE FAN IS NOT IN OPERATION. | | | 9. MAKEUP AIR SHALL BE PROVIDED FOR THE EXHAUST SYSTEM. | | | 10 .A CLEANOUT OPENING SHALL BE LOCATED AT THE BASE OF | | | THE SHAFT TO PROVIDE ACCESS TO THE DUCT TO ALLOW FOR | | | CLEANING AND INSPECTION. THE FINISHED OPENING SHALL BE | | | NOT LESS THAN 12"X12". | | | | | | 10) OK. (KITCHEN APPLIANCES AND EXHAUST HOOD SPEC | | | SHEETS MAY BE DEFERRED SUBMITTALS. PLEASE NOTE ALL | | | COOKING APPLIANCES SHALL BE LISTED AND LABELED AS | | | HOUSE-HOLD TYPE FOR DOMESTIC USE. MAKE UP AIR FOR | | | EXHAUST MAY BE REUIRED IN ACCORDANCE WITH SECTION 505.2 | | | FBC M.) | | | | | | 11) OK. (COMPLETE WIND LOAD ENGINEERING INCLUDING NOA'S | | | AND/OR PRODUCT APPROVALS FOR FANS, FAN CURBS, AND ROOF | | | STANDS MAY BE DEFERRED SUBMITTALS. ALL SUBMITTALS SHALL | | | BEAR THE APPROVAL STAMP OF THE EOR.) | | | | | | 2ND REVIEW: | | | | | | 1) NON-COMPLIANCE: FIRE-RATED SHAFTS ARE REQUIRED FOR | | | THE MULTI-STORY TOILET AND DRYER EXHAUST DUCTS- SECTION | | | 607.6 FBC M. | | | | | | 2) NON-COMPLIANCE: M-1: PROVIDE A SEQUENCE OF OPERATION | | | FOR EF-4 IN THE FIRE PUMP ROOM. | | | | | | 3) NON-COMPLIANCE: M-1, M-2, M-3: THE TOILET ROOM | | | SUPPLY DUCT IS SHOWN RUNNING THROUGH A FIRE-RATED | | | TOILET EXHAUST SHAFT WHICH IS PROHIBITED - SEE NOTE #4 | | | ON THE PLAN AND SECTION 607.7 FBC M. | | | | | | 4) OK. (COMPLETE ENGINEERING FOR INSTALLATION OF THE | | | ROOF FANS MAY BE DEFERRED SUBMIITALS.) | | | | | | 5) NON-COMPLIANCE: M-5: THE REVISED AC SCHEDULE IS | | | INDICATING THE INCORRECT MODEL NUMBER FOR AHU-2- PLEASE | | | CORRECT.( AHU-2 TRANE MODEL TEM6AOC42 IS SHOWN TO HAVE | | | THE SAME CAPACTIES IN THE SCHEDULE AS THE 3-TON TRANE | | | MODEL TEM6AOC36). | | | | | | 6) OK, COMPLIED. | | | | | | 7) OK, COMPLIED. | | | | | | 8) NOT PROVIDED: THE AC LOAD CALCULATIONS SHALL BE | | | PERFORMED IN ACCORDANCE WITH ACCA STANDARD 183 OR ACCA | | | MANUAL N. THIS A COMMERCIAL MULTI-FAMILY PROJECT THAT | | | EXCEEDS 3 STORIES- SEE SECTIONS 202, C403.2.1, | | | C407.5.2.2, AND C406.5.2.3 FBC EC. | | | | | | | | | WHEN RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE | | | LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY | | | RE-SUBMITTAL FORM. ADDITIONALLY, PLEASE INSERT | | | CORRECTED PLAN SHEETS INTO THE SETS, REMOVE THE | | | PREVIOUSLY REVIEWED SHEETS AND MARK VOID ON THEM, AND | | | KEEP THEM WITH THE SUBMITTALS | | | | | | CHRISTOPHER L. COLE | | | MECHANICAL PLANS EXAMINER | | | 401 CLEMATIS STREET | | | WEST PALM BEACH FL 33401 | | | 561-805-6719 | | | [email protected] | | | |
|
|
| Review Stop |
M |
MECHANICAL (A/C) |
| Rev No |
2 |
Status |
F |
Date |
2019-03-28 |
|
|
Cont ID |
|
| Sent By |
ccole |
Date |
2019-03-28 |
Time |
13:11 |
Rev Time |
0.00 |
| Received By |
ccole |
Date |
2019-03-28 |
Time |
12:22 |
Sent To |
|
|
| Notes |
| 2019-03-28 13:12:05 | 2ND REVIEW FBC-2017 MECHANICAL | | | PERMIT #18050056 | | | 3/28/19 | | | | | | CODES IN EFFECT: | | | | | | FBC B- FLORIDA BUILDING CODE SIXTH EDITION 2017 | | | FBC M- FLORIDA MECHANICAL CODE SIXTH EDITION 2017 | | | FBC EC- FLORIDA ENERGY CONSERVATION CODE SIXTH EDITION | | | 2017 | | | FBC FG- FLORIDA FUEL GAS CODE SIXTH EDITION 2017 | | | FS- FLORIDA STATUTES | | | FAC- FLORIDA ADMINISTRATIVE CODE | | | WPB- WEST PALM BEACH AMENDMENTS TO THE FBC SIXTH | | | EDITION 2017 | | | PLAN REVIEW RESULTS: DENIED. | | | | | | THE 1ST REVIEW COMMENTS LISTED BELOW STILL EXIST. NO | | | CORRECTIONS HAVE BEEN MADE TO THE PLANS IN RESPONSE TO | | | THOSE COMMENTS, AND NO RESPONSE NARRATIVE FROM THE | | | ARCHITECT OR ENGINEER OF RECORD HAS BEEN PROVIDED. IN | | | ADDITION TO THOSE COMMENTS PLEASE NOTE THE "NEW | | | COMMENTS" THAT ARE BASED ON THE RESUBMITTED PLANS. | | | WHEN RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE | | | LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY | | | RE-SUBMITTAL FORM. ADDITIONALLY, PLEASE INSERT | | | CORRECTED PLAN SHEETS INTO THE SETS, REMOVE THE | | | PREVIOUSLY REVIEWED SHEETS AND MARK VOID ON THEM, AND | | | KEEP THEM WITH THE SUBMITTALS | | | | | | 1) SHEET CVR: THE INDEX SHOWS 10 MECHANICAL PLAN SHEETS | | | (M-1- M-10), HOWEVER THERE ARE ONLY 6 PLAN SHEETS IN | | | THE SETS (M-1- M-6). | | | | | | 2) PLEASE INDICATE HOW THE APARTMENTS ARE TO BE | | | VENTILATED- NATURALLY IN ACCORDANCE WITH SECTION 402 | | | FBC M, OR MECHANICALLY IN ACCORDANCE WITH SECTION 403 | | | FBC M. THE CURRENT PLAN DOES NOT SHOW ANY OUTDOOR AIR | | | BEING DUCTED INTO THE AIR HANDLERS SO THE ASSUMPTION IS | | | NATURAL VENTILATION WILL BE THE MEANS. PLEASE CONFIRM | | | AND PROVIDE CALCULATIONS IN COMPLIANCE WITH SECTION | | | 402.2 FOR NATURAL, OR TABLE 403.3.1 FOR MECHANICAL. | | | | | | 6) M-1, M-2, M-3: THE SIZES OF THE LINEAR DIFFUSERS AND | | | GRILLS SHOWN ON THE PLAN APPEAR TO INCORRECT BECAUSE | | | THE WIDTH MEASUREMENTS ARE SHOWN IN FEET INSTEAD OF | | | INCHES. | | | | | | 9) SUBMIT MANUFACTURER'S SPECIFICATIONS FOR THE DRYERS | | | PER SECTION 504.9 AND 913 FBC M, AND CORRECT THE PLANS | | | TO SHOW COMPLIANCE WITH THE FOLLOWING REQUIREMENTS FOR | | | COMMON DRYER EXHAUST SYSTEMS IN MULTISTORY STRUCTURES- | | | SECTION 504.10: | | | 1. THE SHAFT IN WHICH THE DUCT IS INSTALLED SHALL BE | | | CONSTRUCTED AND FIRE-RESISTANCE RATED AS REQUIRED BY | | | THE FLORIDA BUILDING CODE, BUILDING. | | | 2. DAMPERS SHALL BE PROHIBITED IN THE EXHAUST DUCT. | | | PENETRATIONS OF THE SHAFT AND DUCTWORK SHALL BE | | | PROTECTED IN ACCORDANCE WITH SECTION 607.5.5, EXCEPTION | | | 2. | | | 3 .RIGID METAL DUCTWORK SHALL BE INSTALLED WITHIN THE | | | SHAFT TO CONVEY THE EXHAUST. THE DUCTWORK SHALL BE | | | CONSTRUCTED OF SHEET STEEL HAVING A MINIMUM THICKNESS | | | OF 0.0187 INCH (0.4712 MM) (NO. 26 GAGE) AND IN | | | ACCORDANCE WITH SMACNA DUCT CONSTRUCTION STANDARDS. | | | 4. THE DUCTWORK WITHIN THE SHAFT SHALL BE DESIGNED AND | | | INSTALLED WITHOUT OFFSETS. | | | 5. THE EXHAUST FAN MOTOR DESIGN SHALL BE IN ACCORDANCE | | | WITH SECTION 503.2. | | | 6. THE EXHAUST FAN MOTOR SHALL BE LOCATED OUTSIDE OF | | | THE AIRSTREAM. | | | 7. THE EXHAUST FAN SHALL RUN CONTINUOUSLY, AND SHALL BE | | | CONNECTED TO A STANDBY POWER SOURCE. | | | 8 .EXHAUST FAN OPERATION SHALL BE MONITORED IN AN | | | APPROVED LOCATION AND SHALL INITIATE AN AUDIBLE OR | | | VISUAL SIGNAL WHEN THE FAN IS NOT IN OPERATION. | | | 9. MAKEUP AIR SHALL BE PROVIDED FOR THE EXHAUST SYSTEM. | | | 10 .A CLEANOUT OPENING SHALL BE LOCATED AT THE BASE OF | | | THE SHAFT TO PROVIDE ACCESS TO THE DUCT TO ALLOW FOR | | | CLEANING AND INSPECTION. THE FINISHED OPENING SHALL BE | | | NOT LESS THAN 12 INCHES BY 12 INCHES (305 MM BY 305 | | | MM). SCREENS SHALL NOT BE INSTALLED AT THE TERMINATION. | | | 11. THE COMMON MULTISTORY DUCT SYSTEM SHALL SERVE ONLY | | | CLOTHES DRYERS AND SHALL BE INDEPENDENT OF OTHER | | | EXHAUST SYSTEMS. | | | | | | 10) SUBMIT MANUFACTURER'S SPECIFICATIONS FOR THE COOK | | | TOPS, OVENS, AND KITCHEN EXHAUST HOODS PER SECTIONS | | | 917.2, AND 505.1 FBC M. (COOK TOP AND OVEN SPECS NOT | | | SUBMITTED). | | | | | | 11) M5, M6: PROVIDE THE WIND LOAD DESIGN CRITERIA FOR | | | INSTALLATION OF THE ROOFTOP CONDENSERS AND STANDS, AND | | | SUBMIT A FL. PRODUCT APPROVAL OR MIAMI-DADE NOA FOR THE | | | STANDS- SECTION 301.15 FBC M. (THE SUBMITTALS FOR THE | | | ROOF STAND AND BRACKET ARE NOT VALID FL. PRODUCT | | | APPROVALS OR NOA'S. (THE SUBMITTALS DO NOT BEAR VALID | | | PRODUCT CONTROL NUMBERS.) | | | | | | NEW COMMENTS | | | | | | 1) FIRE-RATED SHAFTS ARE REQUIRED FOR THE MULTI-STORY | | | TOILET AND DRYER EXHAUST DUCTS- SECTION 607.6 FBC M. | | | | | | 2) M-1: PROVIDE A SEQUENCE OF OPERATION FOR EF-4 IN THE | | | FIRE PUMP ROOM. | | | | | | 3) M-1, M-2, M-3: THE TOILET ROOM SUPPLY DUCT IS SHOWN | | | RUNNING THROUGH THE FIRE-RATED TOILET EXHAUST SHAFT | | | WHICH IS PROHIBITED - SEE NOTE #4 ON THE PLAN AND | | | SECTION 607.5.5 FBC M. | | | | | | 4) M-4: SUBMIT THE MIAMI-DADE NOA AND/OR THE FL. | | | PRODUCT APPROVAL FOR THE CUE MODEL EXHAUST FANS. | | | | | | 5) M-5: THE REVISED AC SCHEDULE IS INDICATING THE | | | INCORRECT MODEL NUMBER FOR AHU-2- PLEASE CORRECT. | | | | | | 6) ERV'S ARE REQUIRED FOR THE EF-1, EF-2, AND EF-4- SEE | | | SECTION C403.2.6. | | | | | | 7) PLEASE CLARIFY IF THE PLANS ARE TO BE DESIGNED UNDER | | | THE FBC-2014 OR 2017 (SEE BUILDING REVIEW COMMENTS). | | | BASED ON SHEET CVR I AM REVIEWING UNDER THE FBC-2017. | | | | | | 8) THE AC LOAD CALCULATIONS SHALL BE PERFORMED IN | | | ACCORDANCE WITH ACCA STANDARD 183 OR ACCA MANUAL N. | | | THIS A COMMERCIAL MULTI-FAMILY PROJECT THAT EXCEEDS 3 | | | STORIES- SEE SECTIONS 202, C403.2.1, C407.5.2.2, AND | | | C406.5.2.3 FBC EC. | | | | | | WHEN RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE | | | LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY | | | RE-SUBMITTAL FORM. ADDITIONALLY, PLEASE INSERT | | | CORRECTED PLAN SHEETS INTO THE SETS, REMOVE THE | | | PREVIOUSLY REVIEWED SHEETS AND MARK VOID ON THEM, AND | | | KEEP THEM WITH THE SUBMITTALS | | | | | | CHRISTOPHER L. COLE | | | MECHANICAL PLANS EXAMINER | | | 401 CLEMATIS STREET | | | WEST PALM BEACH FL 33401 | | | 561-805-6719 | | | [email protected] | | | |
|
|
| Review Stop |
M |
MECHANICAL (A/C) |
| Rev No |
1 |
Status |
F |
Date |
2018-06-06 |
|
|
Cont ID |
|
| Sent By |
ccole |
Date |
2018-06-06 |
Time |
16:46 |
Rev Time |
0.00 |
| Received By |
ccole |
Date |
2018-06-05 |
Time |
17:46 |
Sent To |
|
|
| Notes |
| 2018-06-06 16:47:20 | 1ST REVIEW FBC-2017 MECHANICAL | | | PERMIT #18050056 | | | 6/6/18 | | | | | | CODES IN EFFECT: | | | | | | FBC B- FLORIDA BUILDING CODE SIXTH EDITION 2017 | | | FBC M- FLORIDA MECHANICAL CODE SIXTH EDITION 2017 | | | FBC EC- FLORIDA ENERGY CONSERVATION CODE SIXTH EDITION | | | 2017 | | | FBC R- FLORIDA RESIDENTIAL CODE SIXTH EDITION 2017 | | | FBC FG- FLORIDA FUEL GAS CODE SIXTH EDITION 2017 | | | FS- FLORIDA STATUTES | | | FAC- FLORIDA ADMINISTRATIVE CODE | | | WPB- WEST PALM BEACH AMENDMENTS TO THE FBC SIXTH | | | EDITION 2017 | | | | | | PLAN REVIEW RESULTS: DENIED. | | | | | | 1) SHEET CVR: THE INDEX SHOWS 10 MECHANICAL PLAN SHEETS | | | (M-1- M-10), HOWEVER THERE ARE ONLY 6 PLAN SHEETS IN | | | THE SETS (M-1- M-6). | | | | | | 2) PLEASE INDICATE HOW THE APARTMENTS ARE TO BE | | | VENTILATED- NATURALLY IN ACCORDANCE WITH SECTION 402 | | | FBC M, OR MECHANICALLY IN ACCORDANCE WITH SECTION 403 | | | FBC M. THE CURRENT PLAN DOES NOT SHOW ANY OUTDOOR AIR | | | BEING DUCTED INTO THE AIR HANDLERS SO THE ASSUMPTION IS | | | NATURAL VENTILATION WILL BE THE MEANS. PLEASE CONFIRM | | | AND PROVIDE CALCULATIONS IN COMPLIANCE WITH SECTION | | | 402.2 FOR NATURAL, OR TABLE 403.3.1 FOR MECHANICAL. | | | | | | 3) THE ENERGYGAUGE COMPLIANCE SUBMITTAL NEEDS TO BE | | | UPDATED TO THE SIXTH EDITION (2017) EDITION. PLEASE | | | NOTE THAT THE REVISED SUBMITTAL MUST PROVIDE COMPLIANCE | | | DATA FOR THE 2-TON AND 2.5 TON SYSTEMS WHICH IS MISSING | | | FROM THE CURRENT SUBMITTAL. | | | | | | 4) SHEETS M-1, M-2, & M-3: THE AC CLOSET DOORS ON ALL | | | FLOORS SHALL EITHER BE NON-COMBUSTIBLE OR SHALL HAVE A | | | FLAME SPREAD INDEX OF NOT MORE THAN 25 AND A | | | SMOKE-DEVELOPED INDEX OF NOT MORE THAN 50- SEE SECTION | | | C403.2.9.2 FBC EC AND SECTION 602.2.1 FBC M. | | | | | | 5) M-1, M-2, M-3: THE TRANSFER DUCTS FROM THE BEDROOMS | | | ARE UNDERSIZED BASED ON SECTION 601.6 (1) FBC M. THE | | | CROSS-SECTIONAL AREA OF THE TRANSFER DUCTS SHALL BE | | | 1-1/2 TIMES THE CROSS SECTIONAL AREA OF THE SUPPLY | | | DUCTS ENTERING THE ROOMS. | | | | | | 6) M-1, M-2, M-3: THE SIZES OF THE LINEAR DIFFUSERS AND | | | GRILLS SHOWN ON THE PLAN APPEAR TO INCORRECT BECAUSE | | | THE WIDTH MEASUREMENTS ARE SHOWN IN FEET INSTEAD OF | | | INCHES. | | | | | | 7) M-1, M-2, M-3, M-4: THE TOILET EXHAUST SYSTEMS ARE | | | CONFUSING BECAUSE THE FANS ARE LABELED TEF ON THE FLOOR | | | PLANS, AND EF IN THE SCHEDULE. ARE THERE FANS IN THE | | | BATHROOMS AND ON THE ROOFS? PLEASE CLARIFY. | | | | | | 8) M-6: PROVIDE TOILET EXHAUST RISER DRAWINGS SIMILAR | | | TO THE DRYER EXHAUST RISER DETAIL. | | | | | | 9) SUBMIT MANUFACTURER'S SPECIFICATIONS FOR THE DRYERS | | | PER SECTION 504.9 AND 913 FBC M, AND CORRECT THE PLANS | | | TO SHOW COMPLIANCE WITH THE FOLLOWING REQUIREMENTS FOR | | | COMMON DRYER EXHAUST SYSTEMS IN MULTISTORY STRUCTURES- | | | SECTION 504.10: | | | | | | 1. THE SHAFT IN WHICH THE DUCT IS INSTALLED SHALL BE | | | CONSTRUCTED AND FIRE-RESISTANCE RATED AS REQUIRED BY | | | THE FLORIDA BUILDING CODE, BUILDING. | | | 2. DAMPERS SHALL BE PROHIBITED IN THE EXHAUST DUCT. | | | PENETRATIONS OF THE SHAFT AND DUCTWORK SHALL BE | | | PROTECTED IN ACCORDANCE WITH SECTION 607.5.5, EXCEPTION | | | 2. | | | 3 .RIGID METAL DUCTWORK SHALL BE INSTALLED WITHIN THE | | | SHAFT TO CONVEY THE EXHAUST. THE DUCTWORK SHALL BE | | | CONSTRUCTED OF SHEET STEEL HAVING A MINIMUM THICKNESS | | | OF 0.0187 INCH (0.4712 MM) (NO. 26 GAGE) AND IN | | | ACCORDANCE WITH SMACNA DUCT CONSTRUCTION STANDARDS. | | | 4. THE DUCTWORK WITHIN THE SHAFT SHALL BE DESIGNED AND | | | INSTALLED WITHOUT OFFSETS. | | | 5. THE EXHAUST FAN MOTOR DESIGN SHALL BE IN ACCORDANCE | | | WITH SECTION 503.2. | | | 6. THE EXHAUST FAN MOTOR SHALL BE LOCATED OUTSIDE OF | | | THE AIRSTREAM. | | | 7. THE EXHAUST FAN SHALL RUN CONTINUOUSLY, AND SHALL BE | | | CONNECTED TO A STANDBY POWER SOURCE. | | | 8 .EXHAUST FAN OPERATION SHALL BE MONITORED IN AN | | | APPROVED LOCATION AND SHALL INITIATE AN AUDIBLE OR | | | VISUAL SIGNAL WHEN THE FAN IS NOT IN OPERATION. | | | 9. MAKEUP AIR SHALL BE PROVIDED FOR THE EXHAUST SYSTEM. | | | 10 .A CLEANOUT OPENING SHALL BE LOCATED AT THE BASE OF | | | THE SHAFT TO PROVIDE ACCESS TO THE DUCT TO ALLOW FOR | | | CLEANING AND INSPECTION. THE FINISHED OPENING SHALL BE | | | NOT LESS THAN 12 INCHES BY 12 INCHES (305 MM BY 305 | | | MM). SCREENS SHALL NOT BE INSTALLED AT THE TERMINATION. | | | 11. THE COMMON MULTISTORY DUCT SYSTEM SHALL SERVE ONLY | | | CLOTHES DRYERS AND SHALL BE INDEPENDENT OF OTHER | | | EXHAUST SYSTEMS. | | | | | | 10) SUBMIT MANUFACTURER'S SPECIFICATIONS FOR THE COOK | | | TOPS, OVENS, AND KITCHEN EXHAUST HOODS PER SECTIONS | | | 917.2, AND 505.1 FBC M. | | | | | | 11) M5, M6: PROVIDE THE WIND LOAD DESIGN CRITERIA FOR | | | INSTALLATION OF THE ROOFTOP CONDENSERS AND STANDS, AND | | | SUBMIT A FL. PRODUCT APPROVAL OR MIAMI-DADE NOA FOR THE | | | STANDS- SECTION 301.15 FBC M. | | | | | | 12) THE ROOF MOUNTING CERTIFICATION DETAILS, AND LETTER | | | FROM INGERSOLL RAND THAT ARE COPIED AND PASTED ON M-6 | | | ARE OUTDATED AND ARE CITING THE OUTDATED CODE. PLEASE | | | PROVIDE AN UPDATED COPY THAT IS RELEVANT TO THE CURRENT | | | INSTALLATION. | | | | | | WHEN RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE | | | LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY | | | RE-SUBMITTAL FORM. ADDITIONALLY, PLEASE INSERT | | | CORRECTED PLAN SHEETS INTO THE SETS, REMOVE THE | | | PREVIOUSLY REVIEWED SHEETS AND MARK VOID ON THEM, AND | | | KEEP THEM WITH THE SUBMITTALS | | | | | | CHRISTOPHER L. COLE | | | MECHANICAL PLANS EXAMINER | | | 401 CLEMATIS STREET | | | WEST PALM BEACH FL 33401 | | | 561-805-6719 | | | [email protected] | | | | | | HTTPS://WWW.SURVEYMONKEY.COM/R/WESTPALMBEACHCONSTRUCTIO | | | NSERVICES | | | |
|
|
| Review Stop |
NFIP |
NFIP REVIEW ACTIVITY |
| Rev No |
1 |
Status |
P |
Date |
2019-06-05 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2019-06-05 |
Time |
19:00 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2019-06-05 |
Time |
19:00 |
Sent To |
|
|
| Notes |
| 2019-06-05 19:05:07 | ELEVATION CERTIFICATES TO BE SUBMITTED AND APPROVED | | | DURING CONSTRUCTION AND AT FINAL. C.O. WILL NOT BE | | | ISSUED WITHOUT AN APPROVED FINAL ELEVATION CERTIFICATE. |
|
|
| Review Stop |
P |
PLUMBING |
| Rev No |
5 |
Status |
P |
Date |
2019-06-11 |
|
|
Cont ID |
|
| Sent By |
gjohnson |
Date |
2019-06-11 |
Time |
08:39 |
Rev Time |
0.00 |
| Received By |
gjohnson |
Date |
2019-06-11 |
Time |
08:39 |
Sent To |
|
|
| Notes |
| 2019-06-11 08:44:03 | PLUMBING PROVISO: | | | | | | REVISE PLAN TO COMPLY WITH THE FOLLOWING COMMENTS: | | | | | | | | | 4. AAV ARE NOT ALLOWED AS VENTS BELOW THE 4TH BRANCH | | | DOWN FROM THE TOP OF THE STACK UNLESS PROVIDED WITH A | | | RELIEF VENT . PER FBC PL 918.3.1 | | | | | | 5. FLOOR DRAINS SHALL HAVE TRAP PRIMERS SHOW ON | | | ISOMETRIC DRAWING. PER FBC PL 1002.4.1 | | | | | | 6. WYE STRAINERS ARE REQUIRED ON PRV PROVIDE DETAIL. | | | PER FBC PL 604.8 | | | | | | 7. PLACE NOT ON PLAN A SEPARATE PERMIT IS REQUIRED FOR | | | BACKFLOW AT WATER METER. WPB UTILITIES DEPT. | | | | | | 8. THE NOTE ON THE PLAN FOR THE ELEVATOR SUMP PUMP IS | | | REFERENCING A DETAIL I COULD NOT LOCATE ON ON THE PLAN | | | PLEASE PROVIDE DETAIL AND MANUFACTURE SPECIFICATIONS | | | WITH OIL MINDER OR DRAIN THROUGH OIL INTERCEPTOR. PER | | | FBC PL 1003.4 | | | | | | GEORGE JOHNSON | | | PLUMBING PLANS EXAMINER | | | CITY OF WEST PALM BEACH | | | 561-805-6711 | | | [email protected] |
|
|
| Review Stop |
P |
PLUMBING |
| Rev No |
4 |
Status |
F |
Date |
2019-06-10 |
|
|
Cont ID |
|
| Sent By |
gjohnson |
Date |
2019-06-10 |
Time |
13:10 |
Rev Time |
0.00 |
| Received By |
gjohnson |
Date |
2019-06-10 |
Time |
12:09 |
Sent To |
|
|
| Notes |
| 2019-06-10 13:10:43 | 3RD REVIEW: 18050056 | | | | | | 2017 FLORIDA BUILDING CODE 6TH EDITION | | | 2017 FLORIDA BUILDING CODE - PLUMBING, SIXTH EDITION | | | 2017 FLORIDA BUILDING CODE - ACCESSIBILITY, SIXTH | | | EDITION | | | 2017 FLORIDA BUILDING CODE - FUEL GAS, SIXTH EDITION | | | 2017 FLORIDA BUILDING CODE - RESIDENTIAL, SIXTH EDITION | | | 2017 FLORIDA BUILDING CODE - EXISTING BUILDING, SIXTH | | | EDITION | | | 2017 FLORIDA BUILDING CODE - ENERGY CONSERVATION, SIXTH | | | EDITION | | | | | | PREVIOUS PLUMBING COMMENTS NOT COMPLIED WITH : COMMENT | | | #1 WILL HAVE TO BE COMPLIED WITH BEFORE I CAN PROVISO | | | THE PLAN I SUGGEST A MEETING SO THAT WE CAN RESOLVE | | | THIS, SEE MY CONTACT INFO BELOW. | | | | | | 1. SHT. A208 DETAIL #1 THE GROUND FLOOR UNIT SHALL HAVE | | | A BATHROOM THAT MEETS THE FHA REQUIREMENTS OF EITHER | | | SPEC A OR B THE DETAIL DOES NOT SHOW THIS AND IT IS | | | UNCLEAR WHAT THE NOTES FOR THE CLEAR FLOOR SPACE AND | | | THE OFFSET LAVATORY ARE REFERRING TO IN THE ROOM NEXT | | | TO THE BATHE ROOM IT IS LABELED GUEST BATH AND POWDER | | | AND IT SHOWS THE ABBREVIATIONS FOR THE A SHOWER 2 | | | LAVATORY'S AND 2 TOILETS PLEASE CLARIFY. CLEARLY SHOW | | | THE CLEAR FLOOR SPACE FOR THE TOILET , LAVATORY AND A | | | PARALLEL FLOOR SPACE FOR THE SHOWER TO COMPLY WITH FHA | | | GUIDELINES REQ #7 FIG #6 | | | | | | THE FHA REQUIRES THE PRIMARY ENTRY LEVEL TO A MULTI | | | STORIED DWELLING UNIT TO HAVE A USABLE BATHROOM AND | | | KITCHEN ON THE SAME LEVEL. THE SPEC B BATHROOM ON THE | | | 2ND FLOOR DOES NOT MEET THIS REQUIREMENT THE FACT THAT | | | THE USABLE BATHROOM ON THE 2ND FLOOR CAN NOT BE | | | ACCESSED BY THE OCCUPANT EXCEPT BY EXISTING THE UNIT | | | AND USING THE COMMON ELEVATOR TO REACH IT. FOR FURTHER | | | GUIDANCE ON THIS DESIGN IT MIGHT BE HELPFUL TO CONTACT | | | FAIR HOUSING FIRST SPEAK TO AMBER @ 888-341-7781 OR | | | THEIR WEBSITE HTTPS://WWW.FAIRHOUSINGFIRST.ORG/ | | | | | | | | | | | | | | | 4. AAV ARE NOT ALLOWED AS VENTS BELOW THE 4TH BRANCH | | | DOWN FROM THE TOP OF THE STACK UNLESS PROVIDED WITH A | | | RELIEF VENT . PER FBC PL 918.3.1 | | | | | | 5. FLOOR DRAINS SHALL HAVE TRAP PRIMERS SHOW ON | | | ISOMETRIC DRAWING. PER FBC PL 1002.4.1 | | | | | | 6. WYE STRAINERS ARE REQUIRED ON PRV PROVIDE DETAIL. | | | PER FBC PL 604.8 | | | | | | 7. PLACE NOT ON PLAN A SEPARATE PERMIT IS REQUIRED FOR | | | BACKFLOW AT WATER METER. WPB UTILITIES DEPT. | | | | | | 8. THE NOTE ON THE PLAN FOR THE ELEVATOR SUMP PUMP IS | | | REFERANCING A DETAIL I COULD NOT LOCATE ON ON THE PLAN | | | PLEASE PROVIDE DETAIL AND MANUFACTURE SPECIFICATIONS | | | WIT OIL MINDER ON DRAIN THROUGH OIL INTERCEPTOR. PER | | | FBC PL 1003.4 | | | | | | GEORGE JOHNSON | | | PLUMBING PLANS EXAMINER | | | CITY OF WEST PALM BEACH | | | 561-805-6711 | | | [email protected] |
|
|
| Review Stop |
P |
PLUMBING |
| Rev No |
3 |
Status |
F |
Date |
2019-05-03 |
|
|
Cont ID |
|
| Sent By |
gjohnson |
Date |
2019-05-03 |
Time |
10:55 |
Rev Time |
0.00 |
| Received By |
gjohnson |
Date |
2019-05-02 |
Time |
15:49 |
Sent To |
|
|
| Notes |
| 2019-05-03 10:56:27 | 3RD REVIEW: 18050056 | | | | | | 2017 FLORIDA BUILDING CODE 6TH EDITION | | | 2017 FLORIDA BUILDING CODE - PLUMBING, SIXTH EDITION | | | 2017 FLORIDA BUILDING CODE - ACCESSIBILITY, SIXTH | | | EDITION | | | 2017 FLORIDA BUILDING CODE - FUEL GAS, SIXTH EDITION | | | 2017 FLORIDA BUILDING CODE - RESIDENTIAL, SIXTH EDITION | | | 2017 FLORIDA BUILDING CODE - EXISTING BUILDING, SIXTH | | | EDITION | | | 2017 FLORIDA BUILDING CODE - ENERGY CONSERVATION, SIXTH | | | EDITION | | | | | | PLUMBING COMMENTS: | | | | | | 1. SHT. A208 DETAIL #1 THE GROUND FLOOR UNIT SHALL HAVE | | | A BATHROOM THAT MEETS THE FHA REQUIREMENTS OF EITHER | | | SPEC A OR B THE DETAIL DOES NOT SHOW THIS AND IT IS | | | UNCLEAR WHAT THE NOTES FOR THE CLEAR FLOOR SPACE AND | | | THE OFFSET LAVATORY ARE REFERRING TO IN THE ROOM NEXT | | | TO THE BATHE ROOM IT IS LABELED GUEST BATH AND POWDER | | | AND IT SHOWS THE ABBREVIATIONS FOR THE A SHOWER 2 | | | LAVATORY'S AND 2 TOILETS PLEASE CLARIFY. CLEARLY SHOW | | | THE CLEAR FLOOR SPACE FOR THE TOILET , LAVATORY AND A | | | PARALLEL FLOOR SPACE FOR THE SHOWER TO COMPLY WITH FHA | | | GUIDELINES REQ #7 FIG #6 | | | | | | 2. THE LAVATORY'S IN THE SPEC B BATHROOMS SHALL BE A | | | MAX OF 34" OF FINISH FLOOR. PER FHA GUIDELINES REQ. #7 | | | | | | 3. 2ND REQUEST SHOW LOCATION OF THE GRAB BAR BACKING IN | | | ALL BATHROOM SHOW ON ACCESSIBLE ROUTE FLOOR PLANS. FHA | | | REQ #6 | | | | | | 4. AAV ARE NOT ALLOWED AS VENTS BELOW THE 4TH BRANCH | | | DOWN FROM THE TOP OF THE STACK UNLESS PROVIDED WITH A | | | RELIEF VENT . PER FBC PL 918.3.1 | | | | | | 5. FLOOR DRAINS SHALL HAVE TRAP PRIMERS SHOW ON | | | ISOMETRIC DRAWING. PER FBC PL 1002.4.1 | | | | | | 6. WYE STRAINERS ARE REQUIRED ON PRV PROVIDE DETAIL. | | | PER FBC PL 604.8 | | | | | | 7. PLACE NOT ON PLAN A SEPARATE PERMIT IS REQUIRED FOR | | | BACKFLOW AT WATER METER. WPB UTILITIES DEPT. | | | | | | 8. THE NOTE ON THE PLAN FOR THE ELEVATOR SUMP PUMP IS | | | REFERANCING A DETAIL I COULD NOT LOCATE ON ON THE PLAN | | | PLEASE PROVIDE DETAIL AND MANUFACTURE SPECIFICATIONS | | | WIT OIL MINDER ON DRAIN THROUGH OIL INTERCEPTOR. PER | | | FBC PL 1003.4 | | | | | | GEORGE JOHNSON | | | PLUMBING PLANS EXAMINER | | | CITY OF WEST PALM BEACH | | | 561-805-6711 | | | [email protected] |
|
|
| Review Stop |
P |
PLUMBING |
| Rev No |
2 |
Status |
F |
Date |
2019-04-03 |
|
|
Cont ID |
|
| Sent By |
thunt |
Date |
2019-04-03 |
Time |
13:20 |
Rev Time |
0.00 |
| Received By |
thunt |
Date |
2019-04-03 |
Time |
11:55 |
Sent To |
|
|
| Notes |
| 2019-04-03 13:20:03 | PLUMBING 2ND REVIEW**DENIED** PLEASE NOTE FL ST 553.80 | | | (B)2B WITH RESPECT TO EVALUATION OF DESIGN | | | PROFESSIONALS? DOCUMENTS, IF A LOCAL GOVERNMENT FINDS | | | IT NECESSARY, IN ORDER TO ENFORCE COMPLIANCE WITH THE | | | FLORIDA BUILDING CODE AND ISSUE A PERMIT, TO REJECT | | | DESIGN DOCUMENTS REQUIRED BY THE CODE THREE OR MORE | | | TIMES FOR FAILURE TO CORRECT A CODE VIOLATION | | | SPECIFICALLY AND CONTINUOUSLY NOTED IN EACH REJECTION, | | | INCLUDING, BUT NOT LIMITED TO, EGRESS, FIRE PROTECTION, | | | STRUCTURAL STABILITY, ENERGY, ACCESSIBILITY, LIGHTING, | | | VENTILATION, ELECTRICAL, MECHANICAL, PLUMBING, AND GAS | | | SYSTEMS, OR OTHER REQUIREMENTS IDENTIFIED BY RULE OF | | | THE FLORIDA BUILDING COMMISSION ADOPTED PURSUANT TO | | | CHAPTER 120, THE LOCAL GOVERNMENT SHALL IMPOSE, EACH | | | TIME AFTER THE THIRD SUCH REVIEW THE PLANS ARE REJECTED | | | FOR THAT CODE VIOLATION, A FEE OF FOUR TIMES THE AMOUNT | | | OF THE PROPORTION OF THE PERMIT FEE ATTRIBUTED TO PLANS | | | REVIEW. | | | | | | | | | COMMENTS 1-8 HAVE NOT BE ADDRESSED. NO NEW | | | ARCHITECTURAL PLANS HAVE BEEN SUBMITTED AND PLUMBING | | | SHEETS 4,5,6,7,8 ARE NOT SIGNED AND DATE BY | | | PROFESSIONAL ENGINEER OF RECORD JULIO C. VIDAL AS | | | REQUIRED BY 61G15-23.001 | | | | | | UNABLE TO PROVIDE A COMPLETE AND THOROUGH REVIEW UNTIL | | | NEW PLANS ARE SUBMITTED, SIGNED AND SEALED AND ALL OF | | | THE 1ST REVIEW COMMENTS ARE MEET. PLEASE BE ADVISED | | | THIS BUILDING FALLS UNDER THE FEDERAL FAIR HOUSING ACT | | | AND EACH UNIT IS REQUIRED TO COMPLY. | | | | | | | | | PLEASE NOTE THAT SUBMITTAL OF ADDITIONAL AND/OR REVISED | | | MATERIALS MAY RESULT IN NEW PLAN REVIEW COMMENTS. | | | WHEN RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE | | | LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY | | | RE-SUBMITTAL FORM. PLEASE, ADDITIONALLY, INSERT | | | CORRECTED PAGES INTO TO SUBMITTAL AND REMOVE OR VOID | | | THE PREVIOUSLY REVIEWED SHEETS. | | | | | | | | | TIM HUNT | | | PLUMBING PLANS EXAMINER/ PLUMBING INSPECTOR | | | CITY OF WEST PALM BEACH | | | 561-248-2703 | | | [email protected] |
|
|
| Review Stop |
P |
PLUMBING |
| Rev No |
1 |
Status |
F |
Date |
2018-06-19 |
|
|
Cont ID |
|
| Sent By |
gjohnson |
Date |
2018-06-19 |
Time |
13:00 |
Rev Time |
0.00 |
| Received By |
gjohnson |
Date |
2018-06-15 |
Time |
10:50 |
Sent To |
|
|
| Notes |
| 2018-06-19 13:00:59 | 1ST REVIEW: FBC 2014 5TH EDITION | | | FHADM = FAIR HOUSING ACT DESIGN MANUAL | | | | | | PLUMBING COMMENTS: | | | 1. SHT. A202, 203, 203 SHOWS A LINIER DRAIN BETWEEN THE | | | MASTER BATHROOMS LAVATORIES? PLEASE CLARIFY. PER WPB | | | AMEND TO FBC 107.2.1 | | | 2. SHT. A208 THE SHOWER IN BATHROOM #2 REQUIRES A | | | PARALLEL 30X48 CLEAR FLOOR SPACE. PER FHADM PG. 7.56 | | | 3. SHT. A208 IN THE MASTER BATHROOM THE DETAIL #2 THE | | | STATIONARY SECTION OF THE GLASS PARTITION SHALL BE A | | | MAXIMUM OF 24? EXTENDING FROM THE WALL AND 18? OF THE | | | TOILET PER FHADM PG. 7.43 | | | 4. SHT. A208 PLEASE LABEL THE BATHROOMS WITH THE DESIGN | | | SPEC PER FHADM PG. 7.35 | | | 5. PLEASE SHOW THE DIMENSION OF THE SHOWER DOORS. PER | | | WPB AMEND TO FBC 107.2.1 | | | 6. PROVIDE DETAIL FOR KNEE SPACE AT THE LAVATORY IN THE | | | STUDY BATHROOM PER WPB AMEND TO FBC 107.2.1 | | | 7. THE SHOWER IN THE GROUND UNIT SHALL HAVE A PARALLEL | | | CLEAR FLOOR SPACE. PER FHADM PG. 7.56 | | | 8. SHT. A208 PLEASE INDICATE ON THE DETAILS THE AREAS | | | IN THE BATHROOMS WHERE THE GRAB BAR BACKING IS BEING | | | INSTALLED. | | | 9. PROVIDE A SANITARY ISOMETRIC, PLEASE LABEL ALL RISE | | | TO MATCH THE PLUMBING FLOOR PLAN. PER WPB AMEND TO FBC | | | 107.3.5.1.3(13) | | | 10. SHT. P-6 SHOW SHUT OFF VALVES FOR GROUND FLOOR | | | UNIT. PER FBC PL 606.1 | | | 11. PLEASE PROVIDE DETAIL FOR THE UNIT SHUT OFF VALVES. | | | THE WATER RISER IS NOT SHOWING COLD WATER BRANCHES. PER | | | WPB AMEND TO FBC 107.2.1 | | | | | | PLEASE NOTE THAT SUBMITTAL OF ADDITIONAL AND/OR REVISED | | | MATERIALS MAY RESULT IN NEW PLAN REVIEW COMMENTS. | | | WHEN RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE | | | LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY | | | RE-SUBMITTAL FORM. PLEASE, ADDITIONALLY, INSERT | | | CORRECTED PAGES INTO TO SUBMITTAL AND REMOVE OR VOID | | | THE PREVIOUSLY REVIEWED SHEETS. | | | | | | GEORGE JOHNSON | | | PLUMBING PLANS EXAMINER | | | CITY OF WEST PALM BEACH | | | 561-805-6711 | | | [email protected] | | | |
|
|
| Review Stop |
Z |
ZONING |
| Rev No |
4 |
Status |
P |
Date |
2019-06-06 |
|
|
Cont ID |
|
| Sent By |
llouie |
Date |
2019-06-06 |
Time |
|
Rev Time |
0.00 |
| Received By |
llouie |
Date |
2019-06-06 |
Time |
|
Sent To |
|
|
| Notes |
| 2019-06-06 09:15:25 | ZONING APPROVED WITH THE FOLLOWING PROVISO: | | | | | | 1.) MINOR SITE PLAN AMENDMENT TO REFLECT THE AS-BUILT | | | WILL BE REQUIRED PRIOR TO THE ISSUANCE OF A CERTIFICATE | | | OF OCCUPANCY (C.O.). (EMAIL REFERENCE ATTACHED). | | | | | | | | | REFERENCE: FSPR 16-03A | | | | | | |
|
|
| Review Stop |
Z |
ZONING |
| Rev No |
3 |
Status |
P |
Date |
2019-05-02 |
|
|
Cont ID |
|
| Sent By |
llouie |
Date |
2019-05-02 |
Time |
|
Rev Time |
0.00 |
| Received By |
llouie |
Date |
2019-05-01 |
Time |
|
Sent To |
|
|
| Notes |
| 2019-05-02 12:40:57 | ZONING APPROVED WITH THE FOLLOWING PROVISO: | | | | | | 1.) MINOR SITE PLAN AMENDMENT TO REFLECT THE AS-BUILT | | | WILL BE REQUIRED PRIOR TO THE ISSUANCE OF A CERTIFICATE | | | OF OCCUPANCY (C.O.). (EMAIL REFERENCE ATTACHED). | | | | | | | | | REFERENCE: FSPR 16-03A | | | | | | |
|
|
| Review Stop |
Z |
ZONING |
| Rev No |
2 |
Status |
P |
Date |
2019-03-26 |
|
|
Cont ID |
|
| Sent By |
llouie |
Date |
2019-03-26 |
Time |
|
Rev Time |
0.00 |
| Received By |
llouie |
Date |
2019-03-26 |
Time |
13:01 |
Sent To |
|
|
| Notes |
| 2019-03-26 13:34:39 | REFERENCE: FSPR 16-03A AND ZBA FINAL ORDER 3337. |
|
|
| Review Stop |
Z |
ZONING |
| Rev No |
1 |
Status |
F |
Date |
2018-05-22 |
|
|
Cont ID |
|
| Sent By |
LL |
Date |
2018-05-22 |
Time |
|
Rev Time |
|
| Received By |
llouie |
Date |
2018-05-22 |
Time |
|
Sent To |
|
|
| Notes |
| 2018-05-22 11:04:50 | ** FAILED ** | | | | | | PLEASE ADDRESS THE FOLLOWING COMMENTS. RESPOND TO THE | | | COMMENTS IN WRITING AND/OR ON THE PLANS WHERE | | | APPLICABLE: | | | | | | 1.) CHANGES DETECTED IN THE PLANS THAT DIFFER FROM THE | | | APPROVED PLANS FOR THE PROJECT. A MINOR SITE PLAN | | | AMENDMENT TO THE APPROVED PLANS SHALL BE APPROVED BY | | | THE PLANNING DIVISION PRIOR TO BUILDING PERMIT. [NOTE: | | | APPLICATION FSPR 16-03A CURRENTLY UNDER REVIEW BY THE | | | PLANNING DIVISION. SCHEDULED FOR THE 6/13 PPRC | | | MEETING.]. | | | | | | | | | NOTES: | | | | | | REVISION MAY RESULT IN ADDITIONAL COMMENTS. | | | | | | CONTACT LINDA LOUIE @ (561) 822-1458 IF THERE ARE | | | QUESTIONS. | | | | | | ZONE: MF32 | | | | | | REFERENCE: ZBA FINAL ORDER 3337 AND FSPR 16-03/A | | | | | | |
|
|
|