| Plan Review Stops For Permit 18041054 |
| Review Stop |
B |
BUILDING (STRUCTURAL) |
| Rev No |
3 |
Status |
P |
Date |
2018-06-19 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2018-06-19 |
Time |
11:33 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2018-06-19 |
Time |
11:19 |
Sent To |
I |
|
| Notes |
| 2018-06-19 11:27:43 | FBC-R4501.19 FINAL INSPECTION. FINAL ELECTRICAL AND | | | BARRIER CODE INSPECTION SHALL BE COMPLETED PRIOR TO | | | FILLING THE POOL WITH WATER. | | | | | | |
|
|
| Review Stop |
B |
BUILDING (STRUCTURAL) |
| Rev No |
2 |
Status |
P |
Date |
2018-06-11 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2018-06-11 |
Time |
13:39 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2018-06-11 |
Time |
13:39 |
Sent To |
I |
|
| Notes |
|
|
| Review Stop |
B |
BUILDING (STRUCTURAL) |
| Rev No |
1 |
Status |
F |
Date |
2018-05-03 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2018-05-03 |
Time |
08:24 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2018-05-03 |
Time |
08:07 |
Sent To |
I |
|
| Notes |
| 2018-05-03 08:44:57 | PLAN | | | REVIEW COMMENTS | | | | | | 1ST REVIEW: FBC SIXTH EDITION (2017) | | | ROBERT MCDOUGAL, CBO | | | COMMERCIAL COMBINATION PLANS EXAMINER | | | (561) 805-6714 | | | [email protected] | | | | | | DENIED BY BUILDING | | | PLEASE ADDRESS THE ITEMS NOTED BELOW: | | | | | | 1) THE PLANS SHOW A SPA LOCATED IN THE CENTER OF A POOL | | | OF WATER THAT IS ONLY 6 INCHES DEEP. THE WATER HAS TO | | | BE OVER 24 INCHES DEEP IN ORDER TO MEET THE DEFINITION | | | OF A SWIMMING POOL. THIS WOULD BE CONSIDERED A WADING | | | POOL. FBC R 4501.2 | | | | | | 2) PROVIDE POOL AND SPA SECTION DETAILS THAT ACCURATELY | | | REFLECT THE PROPOSED CONSTRUCTION. SHOW THE DEPTH OF | | | THE POOL AND THE HEIGHT OF THE SPA WALLS ABOVE THE | | | SURROUNDING WADING POOL. FBC 107.2.1 |
|
|
| Review Stop |
E |
ELECTRICAL |
| Rev No |
3 |
Status |
P |
Date |
2018-06-19 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2018-06-19 |
Time |
11:23 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2018-06-19 |
Time |
11:23 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
E |
ELECTRICAL |
| Rev No |
2 |
Status |
P |
Date |
2018-06-06 |
|
|
Cont ID |
|
| Sent By |
jleahy |
Date |
2018-06-06 |
Time |
15:24 |
Rev Time |
0.00 |
| Received By |
jleahy |
Date |
2018-06-06 |
Time |
15:24 |
Sent To |
P |
|
| Notes |
|
|
| Review Stop |
E |
ELECTRICAL |
| Rev No |
1 |
Status |
P |
Date |
2018-04-27 |
|
|
Cont ID |
|
| Sent By |
jleahy |
Date |
2018-04-27 |
Time |
16:19 |
Rev Time |
0.00 |
| Received By |
jleahy |
Date |
2018-04-27 |
Time |
16:19 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
G |
GAS REVIEW |
| Rev No |
2 |
Status |
N |
Date |
2018-06-07 |
|
|
Cont ID |
|
| Sent By |
tklarge |
Date |
2018-06-07 |
Time |
03:15 |
Rev Time |
0.00 |
| Received By |
tklarge |
Date |
2018-06-07 |
Time |
03:15 |
Sent To |
|
|
| Notes |
| 2018-06-07 03:15:22 | THERE IS NO GAS ON THIS POOL. TKL. | | | |
|
|
| Review Stop |
G |
GAS REVIEW |
| Rev No |
1 |
Status |
N |
Date |
2018-06-07 |
|
|
Cont ID |
|
| Sent By |
tklarge |
Date |
2018-04-30 |
Time |
13:49 |
Rev Time |
0.00 |
| Received By |
tklarge |
Date |
2018-04-30 |
Time |
13:41 |
Sent To |
|
|
| Notes |
| 2018-04-30 13:51:37 | THERE IS NO GAS ON THIS POOL. TKL. |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
3 |
Status |
N |
Date |
2018-06-19 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2018-06-19 |
Time |
11:33 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2018-06-12 |
Time |
13:40 |
Sent To |
|
|
| Notes |
| 2018-06-14 13:40:38 | RESUB ROUTED TO TKLARGE |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
2 |
Status |
N |
Date |
2018-06-11 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2018-06-11 |
Time |
13:39 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2018-05-24 |
Time |
13:14 |
Sent To |
|
|
| Notes |
| 2018-06-07 06:06:28 | 6/7 TO RM DESK | | | | | 2018-05-25 13:14:59 | RESUB ROUTED TO ZONING INBOX |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
1 |
Status |
N |
Date |
2018-05-03 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2018-05-03 |
Time |
08:48 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2018-04-23 |
Time |
12:32 |
Sent To |
|
|
| Notes |
| 2018-04-24 12:32:58 | ROUTED TO ZONING INBOX |
|
|
| Review Stop |
P |
PLUMBING |
| Rev No |
3 |
Status |
P |
Date |
2018-06-19 |
|
|
Cont ID |
|
| Sent By |
tklarge |
Date |
2018-06-19 |
Time |
07:20 |
Rev Time |
0.00 |
| Received By |
tklarge |
Date |
2018-06-19 |
Time |
06:38 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
P |
PLUMBING |
| Rev No |
2 |
Status |
F |
Date |
2018-06-07 |
|
|
Cont ID |
|
| Sent By |
tklarge |
Date |
2018-06-07 |
Time |
03:15 |
Rev Time |
0.00 |
| Received By |
tklarge |
Date |
2018-06-07 |
Time |
03:05 |
Sent To |
|
|
| Notes |
| 2018-06-07 03:14:48 | 1) SUBMIT TOTAL DYNAMIC HEAD CALCULATIONS AS REQUIRED | | | BY ANSI/APSP/ ICC-7 2013 SEC. 4.4.9, 4.4.9.1. THE | | | MAXIMUM FLOW OF THE PUMP FROM THE PUMP CURVE IS NO | | | LONGER PERMITTED TO BE USED.THE FLOW RATE SHALL BE | | | DETERMINED BY USING COMPLETE SYSTEM TDH CALCULATIONS | | | AND THEN LOOKING UP THE FLOW RATE USING THE | | | MANUFACTURER'S CERTIFIED PUMP CURVE.2ND REQUEST. | | | YOU HAVE PROVIDED THE TDH BUT WHERE ARE THE | | | CALCULATIONS AS TO HOW YOU ARRIVED AT THIS NUMBER? | | | 2) SUBMIT TWO COPIES OF THE PUMP CURVE. THE TOTAL | | | DYNAMIC HEAD MUST BE MATCHED AGAINST THE PUMP CURVE TO | | | DETERMINE THE MAXIMUM SSYSTEM FLOW FOR THE SPECIFIC | | | TDH. PLEASE REFER TO THE VERBIAGE IN COMMENT #1. | | | | | | TIM LARGE | | | CHIEF PLUMBING INSPECTOR | | | PLUMBING PLAN REVIEW | | | 561-805-6692 | | | [email protected] | | | | | | |
|
|
| Review Stop |
P |
PLUMBING |
| Rev No |
1 |
Status |
F |
Date |
2018-04-30 |
|
|
Cont ID |
|
| Sent By |
tklarge |
Date |
2018-04-30 |
Time |
13:40 |
Rev Time |
0.00 |
| Received By |
tklarge |
Date |
2018-04-30 |
Time |
13:40 |
Sent To |
|
|
| Notes |
| 2018-04-30 13:50:40 | 1) SUBMIT TOTAL DYNAMIC HEAD CALCULATIONS AS REQUIRED | | | BY ANSI/APSP/ ICC-7 2013 SEC. 4.4.9, 4.4.9.1. THE | | | MAXIMUM FLOW OF THE PUMP FROM THE PUMP CURVE IS NO | | | LONGER PERMITTED TO BE USED.THE FLOW RATE SHALL BE | | | DETERMINED BY USING COMPLETE SYSTEM TDH CALCULATIONS | | | AND THEN LOOKING UP THE FLOW RATE USING THE | | | MANUFACTURER'S CERTIFIED PUMP CURVE. | | | | | | | | | TIM LARGE | | | CHIEF PLUMBING INSPECTOR | | | PLUMBING PLAN REVIEW | | | 561-805-6692 | | | [email protected] | | | | | | |
|
|
| Review Stop |
Z |
ZONING |
| Rev No |
2 |
Status |
P |
Date |
2018-05-29 |
|
|
Cont ID |
|
| Sent By |
mcruz |
Date |
2018-05-29 |
Time |
|
Rev Time |
0.00 |
| Received By |
mcruz |
Date |
2018-05-29 |
Time |
14:07 |
Sent To |
B |
|
| Notes |
|
|
| Review Stop |
Z |
ZONING |
| Rev No |
1 |
Status |
F |
Date |
2018-04-26 |
|
|
Cont ID |
|
| Sent By |
ajones |
Date |
2018-04-26 |
Time |
16:56 |
Rev Time |
0.00 |
| Received By |
ajones |
Date |
2018-04-26 |
Time |
16:56 |
Sent To |
I |
|
| Notes |
| 2018-04-26 16:59:53 | 4/26/18- FAILED- | | | 1. SURVEY AND SITE PLANS SHOW DIFFERENT LOCATIONS FOR | | | THE POOL/SPA. | | | 2. THE ZONING AND LAND DEVELOLPMENT REGULATIONS REQUIRE | | | A 5 FOOT SETBACK FROM THE WATER EDGE TO THE SIDE AND | | | REAR PROPERTY LINES. | | | | | | ANGELLA VANN | | | 561-822-1441 | | | [email protected] |
|
|