| 2018-05-01 12:28:08 | 1) THE SITE PLAN SHOWS A GAS GRILL. THE PIPE SIZE OF |
| | EACH SECTION OF GAS PIPING SHALL BE DETERMINED USING |
| | THE LONGEST LENGTH OF PIPING FROM THE POINT OF DELIVERY |
| | TO THE MOST REMOTE OUTLET AND THE LOAD ON THE SECTION. |
| | SHOW THE DISTANCE FROM THE POINT OF DELIVERY, (GAS |
| | METER) TO THE MOST REMOTE OUTLET IN THE BUILDING AND / |
| | OR SYSTEM PER THE 2017 FBC-FUEL GAS SEC.402.4.1, |
| | 402.4.2, OR 2017 FBC-RES. SEC. G 2413.4.1, |
| | G2413.4.2.2017 FBC-FUEL GAS SEC. 402.4.1. |
| | 2) SHOW THE TYPE OF PIPE MATERIAL BEING INSTALLED FOR |
| | THE GRILL AND THE SIZE OF THE PIPE. WPB AMENDMENTS TO |
| | FBC SEC.107.2.1. |
| | 3) LIST THE BTU LOAD OF EACH APPLIANCE AND THE TOTAL |
| | BTU LOAD ON THE SYSTEM. REFER TO THE 2017 FBC-FUEL GAS |
| | SECS.401.8, 402.2, AND TABLES 402.4 (1) THRU 402.4 (37) |
| | OR 2017 FBC-RES. SEC. G2413.3, G2413.4 AND TABLES |
| | G2413.4 (1 ) THROUGH G2413.4 (21). |
| | 4) SUBMIT MANUF. SPECIFICATIONS FOR THE GRILL. FGC |
| | SEC.305.1, FBC-RES. SEC.G2408.1. |
| | 5) INDICATE ON THE PLAN IF THE GRILL IS LOCATED UNDER A |
| | ROOF. WPB AMEND. TO FBC SEC. 107.2.1. |
| | 6) THE DESCRIPTION OF WORK ON THE GAS APPLICATION NOTES |
| | AN EXISTING NATURAL GAS METER BUT THE PLANS SHOW A NEW |
| | NATURAL GAS METER AND THE SITE PLAN SHOWS A "FUTURE |
| | POSSIBLE NG METER SITE.". WHICH IS IT? CLARIFY. WPB |
| | AMEND. TO FBC SEC. 107.2.1. |
| | 7) SPECIFICATIONS FOR A GAS PRESSURE REGULATOR HAVE |
| | BEEN SUBMITTED. IF THIS IS A LESS THAN 2 PSI SYSTEM, |
| | WHY THE REGULATORS? CLARIFY. |
| | 8) THE GAS PLAN REFERENCES TABLE 402.4 (21) OF THE 2017 |
| | FUEL GAS CODE AND COPIES OF THE SAME TABLE HAVE BEEN |
| | SUBMITTED WHICH IS FOR PE PIPE WITH A PRESSURE DROP OF |
| | 0.5 IN. W.C. BUT SIZING TABLES FROM GASTITE HAVE ALSO |
| | BEEN SUBMITTED WITH A LENGTH OF 30 FEET IDENTIFIED AND |
| | A PIPE SIZE OF 1 INCH. THE GAS PLAN SHOWS A DISTANCE OF |
| | 10 FEET AND 3/4 INCH PE. IN ADDITION, THE TABLE FROM |
| | GASTITE IS FOR A PRESSURE DROP OF 6.0 IN. W.C. AT THIS |
| | POINT, I HAVE ABSOLUTELY NO IDEA OF WHAT TABLE IS BEING |
| | USED TO SIZE THIS SYSTEM. SUBMIT TWO COPIES OF THE GAS |
| | SIZING TABLES BEING USED TO DESIGN THIS SYSTEM AND THE |
| | GAS PLAN SHALL ALSO REFLECT THE CORRECT SIZING TABLES. |
| | REMOVE ALL SIZING TABLES THAT DO NOT APPLY. WPB AMEND. |
| | TO FBC SEC. 107.2.1. |
| | 9) A SIZING TABLE FOR A 2 PSI SYSTEM HAS BEEN SUBMITTED |
| | BUT THE GAS PLAN SHOWS A LESS THAN 2 PSI SYSTEM. WHICH |
| | IS IT? CLARIFY. |
| | |
| | TIM LARGE |
| | CHIEF PLUMBING INSPECTOR |
| | PLUMBING PLAN REVIEW |
| | 561-805-6692 |
| | [email protected] |
| | |
| | |
| | |