Plan Review Details - Permit 18040410
Plan Review Stops For Permit 18040410
Review Stop B BUILDING (STRUCTURAL)
Rev No 7 Status P Date 2020-11-13 Cont ID  
Sent By pvalenti Date 2020-11-13 Time 06:39 Rev Time 0.00
Received By pvalenti Date 2020-11-13 Time 06:39 Sent To  
Notes
2020-11-13 06:44:08PETER E VALENTI
 BUILDING PLANS EXAMINER
 [email protected]
 561-805-6673
  
 FBC = FLORIDA BUILDING CODE, 6TH EDITION (2017)
 FBC B = FBC BUILDING
 FBC EB = FBC EXISTING BUILDING
 FBC A = FBC ACCESSIBILITY
 FBC EC = FBC ENERGY CONSERVATION
 FBC R = FBC RESIDENTIAL
 FBC M = FBC MECHANICAL
 FBC FG = FBC FUEL GAS
  
 BUILDING REVIEW APPROVED.
 PLEASE SEE ELEVATION CERTIFICATE UNDER PERMIT SUBMITTAL
 # 19080006.

Review Stop B BUILDING (STRUCTURAL)
Rev No 6 Status F Date 2019-11-22 Cont ID  
Sent By pvalenti Date 2019-11-22 Time 15:00 Rev Time 0.00
Received By pvalenti Date 2019-11-21 Time 09:46 Sent To  
Notes
2019-11-22 15:01:44***CORRECTIONS***
 PETER E VALENTI
 BUILDING PLANS EXAMINER
 [email protected]
 561-805-6673
  
 FBC = FLORIDA BUILDING CODE, 6TH EDITION (2017)
 FBC B = FBC BUILDING
 FBC EB = FBC EXISTING BUILDING
 FBC A = FBC ACCESSIBILITY
 FBC EC = FBC ENERGY CONSERVATION
 FBC R = FBC RESIDENTIAL
 FBC M = FBC MECHANICAL
  
 FBC B 107.2.1, MISSING THE ELEVATION CERTIFICATE.

Review Stop B BUILDING (STRUCTURAL)
Rev No 5 Status F Date 2019-08-07 Cont ID  
Sent By jgomez Date 2019-08-07 Time 18:09 Rev Time 0.00
Received By pvalenti Date 2019-08-07 Time 17:52 Sent To  
Notes
2019-08-07 17:55:57***CORRECTIONS***
 PETER E VALENTI
 BUILDING PLANS EXAMINER
 [email protected]
 561-805-6673
  
 FBC = FLORIDA BUILDING CODE, 6TH EDITION (2017)
 FBC B = FBC BUILDING
 FBC EB = FBC EXISTING BUILDING
 FBC A = FBC ACCESSIBILITY
 FBC EC = FBC ENERGY CONSERVATION
 FBC R = FBC RESIDENTIAL
 FBC M = FBC MECHANICAL
  
 5TH BUILDING REVIEW DENIED:
  
 1. PROVIDE PRODUCT APPROVALS REVIEWED AND APPROVED BY
 DESIGNER OF RECORD.
  
 2. PROVIDE UPDATED ENERGY CALCULATIONS THAT CORRELATE
 WITH PLANS.
 (THE DOORS AND WINDOWS FROM THE PLANS NEED TO BE
 INCLUDED IN THE ENERGY CALCULATIONS).
  
 3. THE ELEVATION CERTIFICATE NEEDS TO BE CORRECTED,
 (SEE SUBMITTAL # 19080006).
  
 PROVISO: THE INSULATION AT BLOCK WALLS NEEDS TO
 CORRELATE WITH INSULATION ON ENERGY CALCULATIONS AS
 FOLLOWS (R=4.2).
  
  

Review Stop B BUILDING (STRUCTURAL)
Rev No 4 Status F Date 2019-03-25 Cont ID  
Sent By jgomez Date 2019-03-25 Time 15:01 Rev Time 0.00
Received By jgomez Date 2019-03-25 Time 14:43 Sent To  
Notes
2019-03-25 15:01:0703/25/19 RESPONSE TO SHUBHAM GOWDA E-MAIL
 GOOD AFTERNOON SHUBHAM,
 THAT ELEVATION CERTIFICATE IS TOO OLD. IT LOOKS TO BE
 DONE BEFORE THE ADDITION. IT?S DATED 2010/01/05 BY
 CLYDE MCNEAL.
 THE ELEVATION CERTIFICATES WE NEED ARE THE ONES THAT
 ARE DONE DURING CONSTRUCTION. IMPORTANT: THIS PERMIT
 WAS ISSUED PRIOR TO THE FEMA REVISED FLOOD MAPS. THE
 FINISH FLOOR ELEVATIONS WERE DONE BASED ON NGVD29
 VERTICAL DATUM. KEEP THIS IN MIND WHEN SUBMITTING THE
 ELEVATION CERTIFICATES.
 IF SURVEYOR USES NAVD 1988, THEN CONVERSION TO NGVD 29
 WILL NEED TO BE PROVIDED.
 THANK YOU
  
 JULIO GOMEZ
 COMMERCIAL COMBINATION PLANS EXAMINER
 DEVELOPMENT SERVICES DEPARTMENT
 BUILDING DIVISION
 (561)805-6712
 [email protected]
  
  
  
  
  
  
  
 RESIDENTIAL (R3) REVISION, SECOND BUILDING REVIEW
 CHECKLIST.
 CODE: FBC 5TH EDITION (2014).
  
 1- A) OK. SAME ARCH.
  
 B) OK.
  
 C) OK.
  
 D) OK.
  
  
 ORIGINAL COMMENT:
 2- SIZE OF ENTRY DOOR DOESN'T COMPLY WITH SEC. R311.2
 FBC-RESIDENTIAL. NEED 32" MIN. CLEAR OPENING. REVISE AS
 REQUIRED. TYPICALLY 36" DOORS ARE THE ONES THAT COMPLY.
  
 RESPONSE:
 RESPONSE LETTER STATES "STRUCTURAL ENGINEER HAS REVISED
 S-1 SHEET TO SHOW CORRECT DOOR OPENING SIZE". SHEET S-1
 SHOWS 5'-4" OPENING SIZE. DOUBLE 3'X8' DOORS DON'T FIT
 IN THIS OPENING. REVISE AS REQUIRED. SEC. 107.2.1 CITY
 AMENDMENTS.
  
 ORIGINAL COMMENT:
 3- SPECIFY ON PLANS THE EXISTING HOUSE AND EQUIPMENT
 FINISH FLOOR ELEVATION AND THE PROPOSED ADDITION AND
 EQUIPMENT FINISH FLOOR ELEVATION. SEC. 94-546 CITY
 ORDINANCE. NOTE: APPROVED PLANS SPECIFIED THE EXISTING
 AND PROPOSED FINISH FLOOR ELEVATION TO BE 8.05'. BEFORE
 10/05/17 CITY ORDINANCE REQUIRED 1 FOOT FREE BOARD
 ABOVE THE BASE FLOOD ELEVATION. THEREFORE, THIS
 ELEVATION WAS IN COMPLIANCE. ELEVATION CERTIFICATES
 WILL BE REQUIRED DURING CONSTRUCTION.
  
 RESPONSE:
 REPEAT COMMENT. ELEVATION CERTIFICATES HAVE NOT BEEN
 SUBMITTED FOR REVIEW.
  
 ORIGINAL COMMENT:
 4- SHEET S-6: DOORS AND WINDOWS DESIGN PRESSURES SHOWN
 ON 1ST AND 2ND FLOOR PLAN DON'T MATCH DESIGN PRESSURES
 SHOWN ON THE TABLE ON SAME SHEET. REVISE AS REQUIRED TO
 MATCH. ALSO, DESIGN PRESSURES CAN NOT BE LOWER ON THE
 SECOND FLOOR THAN THE FIRST FLOOR. DESIGN PRESSURES CAN
 NOT BE LOWER FOR OPENINGS THAT ARE SMALLER. REVISE AS
 REQUIRED. NOTE: THE EDGE DISTANCE IS 4'-0" MIN AS
 REQUIRED BY NOTE AT THE BOTTOM OF FIGURE R301.2(7)
 FBC-RESIDENTIAL. REVISE AS REQUIRED.
  
 RESPONSE:
 REPEAT COMMENT. NOT ADDRESSED.
 RESPONSE LETTER STATES "STRUCTURAL ENGINEER HAS REVISED
 S-6 TO SHOW WIND PRESSURES". DRAWING WAS NOT REVISED.
  
 5- OK.
  
 4- OK.
  
 ORIGINAL COMMENT:
 5- PROVIDE PRODUCT APPROVAL (2 COPIES) AS REQUIRED BY
 FAC 61G20-3.001 FOR SECOND FLOOR BALCONY DECK COVERING.
 AND, CLEARLY IDENTIFY WHICH APPROVED ASSEMBLY IS GOING
 TO BE USED. NOTE: COORDINATE WITH ITEM #5 ABOVE.
  
 RESPONSE:
 REPEAT COMMENT. PRODUCT APPROVAL NOT SUBMITTED.
  
 6- OK.
  
 IMPORTANT NOTES:
 (1) ELEVATION CERTIFICATES WILL BE REQUIRED DURING
 CONSTRUCTION. (********ELEVATION CERTIFICATES NO
 PROVIDED YET AS OF 03/19/19).
 (2)GARAGE FLOOD VENTS NEED TO BE INSTALLED BELOW THE
 BASE FLOOD ELEVATION (********ELEVATION CERTIFICATES NO
 PROVIDED YET AS OF 03/19/19).
 (3) ORIGINAL PERMIT WAS APPROVED WITH PROVISO. PROVIDE
 REQUIRED INFORMATION . SEE COPY OF PROVISO BELOW.
 (*****NOT ADDRESSED YET AS OF 03/19/19).
  
  
 ****PLEASE PROVIDE RESPONSE LETTER ADDRESSING EACH
 COMMENT TO HELP EXPEDITE THE REVIEW PROCESS.
 ****PLEASE INSERT ANY REVISED DRAWING AND REMOVE OLD
 DRAWING. SUBMIT OLD DRAWINGS FOR REFERENCE OF ALREADY
 REVIEWED DRAWINGS. DO NOT STAPLE OLD DRAWINGS TO PLANS.
  
  
 IF YOU HAVE ANY QUESTIONS, PLEASE CONTACT
 JULIO GOMEZ
 COMMERCIAL COMBINATION PLANS EXAMINER
 DEVELOPMENT SERVICES DEPARTMENT
 BUILDING DIVISION
 (561)805-6712
 [email protected]
  
  
  
  
  
  
 BUILDING REVIEW APPROVED WITH PROVISO: ******(DATED
 02/01/17)
 1- PROVIDE COMPLETE DETAILS/SPECIFICATIONS FOR THE
 INSTALLATION OF BRICK VENEER, INCLUDING VENEER SUPPORTS
 AT OPENINGS. ALSO, SPECIFY WEEP-HOLES, ETC.
 NOTE: PROVIDE COMPLETE DETAILS/ SPECIFICATIONS. DON'T
 CITE CODE SECTIONS.
  
 2- ENERGY CALCULATIONS WERE REVISED FOR FULL HOUSE
 COMPLIANCE INSTEAD OF ADDITION ALONE:
 A) REVISE CEILING INSULATION ITEM #10 TO MATCH PLANS.
 VENTED AND UNVENTED ROOFS.
 B) REVISE ROOF MATERIAL SHOWN ON PAGE 2 OF 5 TO MATCH
 PLANS AND PRODUCT APPROVALS SUBMITTED.
 C) REVISE CONCRETE BLOCK INSULATION ITEM #9 DOESN'T
 MATCH PLANS. SEE DETAIL #2 ON SHEET A-10.
 D) REVISE R-VALUE SHOWN ON THE CEILING INSULATION ON
 PAGE 3 OF 5 TO MATCH PLANS AND INFORMATION SHOWN ON
 ITEM #10.
 E) REVISE DOOR TYPE SPECIFIED ON PAGE 3 OF 5 TO MATCH
 PLANS AND PRODUCT APPROVALS SUBMITTED. THERE ARE NO
 INSULATED DOORS. DOORS WITH GLASS NEED TO BE INCLUDED
 IN THE WINDOWS AREA.
 F) REVISE WINDOWS OVERHANG DEPTH AND SEPARATION TO
 MATCH PLANS.
 G) REVISE NUMBER OF OCCUPANTS ON PAGE 2 OF 5. WHY 20
 PEOPLE IN A SINGLE FAMILY RESIDENCE.
 H) REVISE FLOOR TYPES ON PAGE 2 OF 5. 2ND FLOOR IS NOT
 ON SLAB ON GRADE.
  
 3- PROVIDE PRODUCT APPROVAL (2 COPIES) AS REQUIRED BY
 FAC 61G20-3.002(33) FOR:
 A) GARAGE DOORS THAT MEETS ALL THE DESIGN LOADS SHOWN
 ON SHEET S-6 (POSITIVE AND NEGATIVE).
 B) DOUBLE EXTERIOR DOORS THAT MEET THE DESIGN PRESSURES
 SPECIFIED ON PLANS.
  
 4- ENGINEER OF RECORD TO REVIEW AND APPROVE ABOVE
 PRODUCT APPROVALS.

Review Stop B BUILDING (STRUCTURAL)
Rev No 3 Status F Date 2019-03-19 Cont ID  
Sent By jgomez Date 2019-03-19 Time 10:50 Rev Time 0.00
Received By jgomez Date 2019-03-18 Time 17:47 Sent To  
Notes
2019-03-19 10:50:51RESIDENTIAL (R3) REVISION, SECOND BUILDING REVIEW
 CHECKLIST.
 CODE: FBC 5TH EDITION (2014).
  
 1- A) OK. SAME ARCH.
  
 B) OK.
  
 C) OK.
  
 D) OK.
  
  
 ORIGINAL COMMENT:
 2- SIZE OF ENTRY DOOR DOESN'T COMPLY WITH SEC. R311.2
 FBC-RESIDENTIAL. NEED 32" MIN. CLEAR OPENING. REVISE AS
 REQUIRED. TYPICALLY 36" DOORS ARE THE ONES THAT COMPLY.
  
 RESPONSE:
 RESPONSE LETTER STATES "STRUCTURAL ENGINEER HAS REVISED
 S-1 SHEET TO SHOW CORRECT DOOR OPENING SIZE". SHEET S-1
 SHOWS 5'-4" OPENING SIZE. DOUBLE 3'X8' DOORS DON'T FIT
 IN THIS OPENING. REVISE AS REQUIRED. SEC. 107.2.1 CITY
 AMENDMENTS.
  
 ORIGINAL COMMENT:
 3- SPECIFY ON PLANS THE EXISTING HOUSE AND EQUIPMENT
 FINISH FLOOR ELEVATION AND THE PROPOSED ADDITION AND
 EQUIPMENT FINISH FLOOR ELEVATION. SEC. 94-546 CITY
 ORDINANCE. NOTE: APPROVED PLANS SPECIFIED THE EXISTING
 AND PROPOSED FINISH FLOOR ELEVATION TO BE 8.05'. BEFORE
 10/05/17 CITY ORDINANCE REQUIRED 1 FOOT FREE BOARD
 ABOVE THE BASE FLOOD ELEVATION. THEREFORE, THIS
 ELEVATION WAS IN COMPLIANCE. ELEVATION CERTIFICATES
 WILL BE REQUIRED DURING CONSTRUCTION.
  
 RESPONSE:
 REPEAT COMMENT. ELEVATION CERTIFICATES HAVE NOT BEEN
 SUBMITTED FOR REVIEW.
  
 ORIGINAL COMMENT:
 4- SHEET S-6: DOORS AND WINDOWS DESIGN PRESSURES SHOWN
 ON 1ST AND 2ND FLOOR PLAN DON'T MATCH DESIGN PRESSURES
 SHOWN ON THE TABLE ON SAME SHEET. REVISE AS REQUIRED TO
 MATCH. ALSO, DESIGN PRESSURES CAN NOT BE LOWER ON THE
 SECOND FLOOR THAN THE FIRST FLOOR. DESIGN PRESSURES CAN
 NOT BE LOWER FOR OPENINGS THAT ARE SMALLER. REVISE AS
 REQUIRED. NOTE: THE EDGE DISTANCE IS 4'-0" MIN AS
 REQUIRED BY NOTE AT THE BOTTOM OF FIGURE R301.2(7)
 FBC-RESIDENTIAL. REVISE AS REQUIRED.
  
 RESPONSE:
 REPEAT COMMENT. NOT ADDRESSED.
 RESPONSE LETTER STATES "STRUCTURAL ENGINEER HAS REVISED
 S-6 TO SHOW WIND PRESSURES". DRAWING WAS NOT REVISED.
  
 5- OK.
  
 4- OK.
  
 ORIGINAL COMMENT:
 5- PROVIDE PRODUCT APPROVAL (2 COPIES) AS REQUIRED BY
 FAC 61G20-3.001 FOR SECOND FLOOR BALCONY DECK COVERING.
 AND, CLEARLY IDENTIFY WHICH APPROVED ASSEMBLY IS GOING
 TO BE USED. NOTE: COORDINATE WITH ITEM #5 ABOVE.
  
 RESPONSE:
 REPEAT COMMENT. PRODUCT APPROVAL NOT SUBMITTED.
  
 6- OK.
  
 IMPORTANT NOTES:
 (1) ELEVATION CERTIFICATES WILL BE REQUIRED DURING
 CONSTRUCTION. (********ELEVATION CERTIFICATES NO
 PROVIDED YET AS OF 03/19/19).
 (2)GARAGE FLOOD VENTS NEED TO BE INSTALLED BELOW THE
 BASE FLOOD ELEVATION (********ELEVATION CERTIFICATES NO
 PROVIDED YET AS OF 03/19/19).
 (3) ORIGINAL PERMIT WAS APPROVED WITH PROVISO. PROVIDE
 REQUIRED INFORMATION . SEE COPY OF PROVISO BELOW.
 (*****NOT ADDRESSED YET AS OF 03/19/19).
  
  
 ****PLEASE PROVIDE RESPONSE LETTER ADDRESSING EACH
 COMMENT TO HELP EXPEDITE THE REVIEW PROCESS.
 ****PLEASE INSERT ANY REVISED DRAWING AND REMOVE OLD
 DRAWING. SUBMIT OLD DRAWINGS FOR REFERENCE OF ALREADY
 REVIEWED DRAWINGS. DO NOT STAPLE OLD DRAWINGS TO PLANS.
  
  
 IF YOU HAVE ANY QUESTIONS, PLEASE CONTACT
 JULIO GOMEZ
 COMMERCIAL COMBINATION PLANS EXAMINER
 DEVELOPMENT SERVICES DEPARTMENT
 BUILDING DIVISION
 (561)805-6712
 [email protected]
  
  
  
  
  
  
 BUILDING REVIEW APPROVED WITH PROVISO: ******(DATED
 02/01/17)
 1- PROVIDE COMPLETE DETAILS/SPECIFICATIONS FOR THE
 INSTALLATION OF BRICK VENEER, INCLUDING VENEER SUPPORTS
 AT OPENINGS. ALSO, SPECIFY WEEP-HOLES, ETC.
 NOTE: PROVIDE COMPLETE DETAILS/ SPECIFICATIONS. DON'T
 CITE CODE SECTIONS.
  
 2- ENERGY CALCULATIONS WERE REVISED FOR FULL HOUSE
 COMPLIANCE INSTEAD OF ADDITION ALONE:
 A) REVISE CEILING INSULATION ITEM #10 TO MATCH PLANS.
 VENTED AND UNVENTED ROOFS.
 B) REVISE ROOF MATERIAL SHOWN ON PAGE 2 OF 5 TO MATCH
 PLANS AND PRODUCT APPROVALS SUBMITTED.
 C) REVISE CONCRETE BLOCK INSULATION ITEM #9 DOESN'T
 MATCH PLANS. SEE DETAIL #2 ON SHEET A-10.
 D) REVISE R-VALUE SHOWN ON THE CEILING INSULATION ON
 PAGE 3 OF 5 TO MATCH PLANS AND INFORMATION SHOWN ON
 ITEM #10.
 E) REVISE DOOR TYPE SPECIFIED ON PAGE 3 OF 5 TO MATCH
 PLANS AND PRODUCT APPROVALS SUBMITTED. THERE ARE NO
 INSULATED DOORS. DOORS WITH GLASS NEED TO BE INCLUDED
 IN THE WINDOWS AREA.
 F) REVISE WINDOWS OVERHANG DEPTH AND SEPARATION TO
 MATCH PLANS.
 G) REVISE NUMBER OF OCCUPANTS ON PAGE 2 OF 5. WHY 20
 PEOPLE IN A SINGLE FAMILY RESIDENCE.
 H) REVISE FLOOR TYPES ON PAGE 2 OF 5. 2ND FLOOR IS NOT
 ON SLAB ON GRADE.
  
 3- PROVIDE PRODUCT APPROVAL (2 COPIES) AS REQUIRED BY
 FAC 61G20-3.002(33) FOR:
 A) GARAGE DOORS THAT MEETS ALL THE DESIGN LOADS SHOWN
 ON SHEET S-6 (POSITIVE AND NEGATIVE).
 B) DOUBLE EXTERIOR DOORS THAT MEET THE DESIGN PRESSURES
 SPECIFIED ON PLANS.
  
 4- ENGINEER OF RECORD TO REVIEW AND APPROVE ABOVE
 PRODUCT APPROVALS.

Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status F Date 2018-05-03 Cont ID  
Sent By jgomez Date 2018-05-03 Time 16:09 Rev Time 0.00
Received By jgomez Date 2018-05-03 Time 16:07 Sent To  
Notes
2018-05-03 16:08:1405/03/18
 WILLIAM WATERS MESSAGE STATED THAT HE'S THE SAME ARCH.
 OF RECORD. LEFT MESSAGES ON WILLIAM WATERS (ARCH.)
 VOICE MAIL. NEED HIS INFORMATION IN TITLE BLOCK AND
 CLARIFIED THAT HOUSE DOESN'T HAVE TO BE RAISED.
 ELEVATION CERTIFICATES WILL BE REQUIRED DURING
 CONSTRUCTION.
  
  
  
  
  
 RESIDENTIAL (R3) REVISION, BUILDING REVIEW COMMENTS
 CODE: FBC 5TH EDITION (2014).
  
 1- A) IT LOOKS LIKE THE ARCHITECT OF RECORD OF THIS
 PROJECT WAS CHANGED. SUCCESSOR ARCHITECT TO FOLLOW FAC
 SEC. 61G-18.002 PROCEDURES. SEE BELOW.
  
 B) NEW ARCHITECT SIGNING AND SEALING THE ARCHITECTURAL
 PLANS TO PROVIDE HIS INFORMATION IN THE TITLE BLOCK AS
 REQUIRED BY FAC 61G1-16.004.
  
 C) MISSING DRAWINGS S2, AND A3. SEE DRAWING INDEX ON
 SHEET CS.
 PROVIDE COMPLETE SET OF DRAWINGS. SEC. 107.2.1 CITY
 AMENDMENTS.
  
 D) COVER SHEET CS NEED TO HAVE THE SEAL AND SIGNATURE
 OF DESIGNER OF RECORD. SEC. 481 F.S.
 NOTE: COORDINATE WITH NAME OF DESIGN PROFESSIONAL SHOWN
 ON THE COVER SHEET.
  
  
 61G1-18.002 PROCEDURES FOR A SUCCESSOR ARCHITECT
 ADOPTING AS HIS OWN THE WORK OF ANOTHER ARCHITECT.
 (1) A SUCCESSOR REGISTERED ARCHITECT SEEKING TO REUSE
 ALREADY SEALED CONTRACT DOCUMENTS UNDER THE SUCCESSOR
 REGISTERED ARCHITECT'S SEAL MUST BE ABLE TO DOCUMENT
 AND PRODUCE UPON REQUEST EVIDENCE THAT HE HAS IN FACT
 RECREATED ALL THE WORK DONE BY THE ORIGINAL REGISTERED
 ARCHITECT. FURTHER, THE SUCCESSOR REGISTERED ARCHITECT
 MUST TAKE ALL PROFESSIONAL AND LEGAL RESPONSIBILITY FOR
 THE DOCUMENTS WHICH HE SEALED AND SIGNED AND CAN IN NO
 WAY EXEMPT HIMSELF FROM SUCH FULL RESPONSIBILITY. PLANS
 NEED NOT BE REDRAWN BY THE SUCCESSOR REGISTERED
 ARCHITECT; HOWEVER, JUSTIFICATION FOR SUCH ACTION MUST
 BE AVAILABLE THROUGH WELL KEPT AND COMPLETE
 DOCUMENTATION ON THE PART OF THE SUCCESSOR REGISTERED
 ARCHITECT AS TO HIS HAVING RETHOUGHT AND REWORKED THE
 ENTIRE DESIGN PROCESS. A SUCCESSOR REGISTERED ARCHITECT
 MUST USE HIS OWN TITLE BLOCK, SEAL AND SIGNATURE AND
 MUST REMOVE THE TITLE BLOCK, SEAL AND SIGNATURE OF THE
 ORIGINAL REGISTERED ARCHITECT BEFORE SEALING, SIGNING
 AND DATING ANY SEALED CONTRACT DOCUMENTS.
 (2) PRIOR TO SEALING, SIGNING AND DATING WORK, A
 SUCCESSOR REGISTERED ARCHITECT SHALL BE REQUIRED TO
 NOTIFY THE ORIGINAL REGISTERED ARCHITECT, HIS
 SUCCESSORS, OR ASSIGNS BY CERTIFIED LETTER TO THE LAST
 KNOWN ADDRESS OF THE ORIGINAL REGISTERED ARCHITECT OF
 THE SUCCESSOR'S INTENTION TO USE OR REUSE THE ORIGINAL
 REGISTERED ARCHITECT'S WORK. THE SUCCESSOR REGISTERED
 ARCHITECT WILL TAKE FULL RESPONSIBILITY FOR THE DRAWING
 AS THOUGH THEY WERE THE SUCCESSOR REGISTERED
 ARCHITECT'S ORIGINAL PRODUCT.
 RULEMAKING AUTHORITY 481.2055 FS. LAW IMPLEMENTED
 481.221(4) FS. HISTORY?NEW 1-16-86, AMENDED 5-16-89,
 FORMERLY 21B-18.002.
  
  
 2- SIZE OF ENTRY DOOR DOESN'T COMPLY WITH SEC. R311.2
 FBC-RESIDENTIAL. NEED 32" MIN. CLEAR OPENING. REVISE AS
 REQUIRED. TYPICALLY 36" DOORS ARE THE ONES THAT COMPLY.
  
 3- SPECIFY ON PLANS THE EXISTING HOUSE AND EQUIPMENT
 FINISH FLOOR ELEVATION AND THE PROPOSED ADDITION AND
 EQUIPMENT FINISH FLOOR ELEVATION. SEC. 94-546 CITY
 ORDINANCE. NOTE: APPROVED PLANS SPECIFIED THE EXISTING
 AND PROPOSED FINISH FLOOR ELEVATION TO BE 8.05'. BEFORE
 10/05/17 CITY ORDINANCE REQUIRED 1 FOOT FREE BOARD
 ABOVE THE BASE FLOOD ELEVATION. THEREFORE, THIS
 ELEVATION WAS IN COMPLIANCE. ELEVATION CERTIFICATES
 WILL BE REQUIRED DURING CONSTRUCTION.
  
 4- SHEET S-6: DOORS AND WINDOWS DESIGN PRESSURES SHOWN
 ON 1ST AND 2ND FLOOR PLAN DON'T MATCH DESIGN PRESSURES
 SHOWN ON THE TABLE ON SAME SHEET. REVISE AS REQUIRED TO
 MATCH. ALSO, DESIGN PRESSURES CAN NOT BE LOWER ON THE
 SECOND FLOOR THAN THE FIRST FLOOR. DESIGN PRESSURES CAN
 NOT BE LOWER FOR OPENINGS THAT ARE SMALLER. REVISE AS
 REQUIRED. NOTE: THE EDGE DISTANCE IS 4'-0" MIN AS
 REQUIRED BY NOTE AT THE BOTTOM OF FIGURE R301.2(7)
 FBC-RESIDENTIAL. REVISE AS REQUIRED.
  
 5- NEW SECOND FLOOR BALCONY: PLANS AND DETAILS CALL FOR
 SLOPE OF 1:60. REVISE AS REQUIRED. ROOF DECKS NEED TO
 BE COVERED WITH APPROVED ROOF COVERINGS. LOW SLOPE
 (FLAT ROOF) REQUIRE AN SLOPE OF 1/4" PER FOOT MIN.
 REVISE THE SLOPE SHOWN ON ALL PLANS AND DETAILS. SEC.
 R903.1 AND SEC. R905.9 FBC-RESIDENTIAL. NOTE: SPECIFY
 PROPOSED ROOF FINISH (TILE, ETC).
  
 4- NEW STAIRS: PROVIDE INFORMATION FOR TREADS AND
 RISERS DIMENSIONS SHOWING COMPLIANCE WITH SEC. R311.7.5
 FBC-RESIDENTIAL.
  
 5- PROVIDE PRODUCT APPROVAL (2 COPIES) AS REQUIRED BY
 FAC 61G20-3.001 FOR SECOND FLOOR BALCONY DECK COVERING.
 AND, CLEARLY IDENTIFY WHICH APPROVED ASSEMBLY IS GOING
 TO BE USED. NOTE: COORDINATE WITH ITEM #5 ABOVE.
  
 6- TOTAL NUMBER OF DRAWINGS SUBMITTED ARE 36 NOT 21 AS
 STATED ON THE REVISION FORM. REVISION FEE WAS UPDATED.
 THE REVISION FEE BALANCE IS $768.75.
  
 IMPORTANT NOTES:
 (1) ELEVATION CERTIFICATES WILL BE REQUIRED DURING
 CONSTRUCTION.
 (2)GARAGE FLOOD VENTS NEED TO BE INSTALLED BELOW THE
 BASE FLOOD ELEVATION.
 (3) ORIGINAL PERMIT WAS APPROVED WITH PROVISO. PROVIDE
 REQUIRED INFORMATION . SEE COPY OF PROVISO BELOW.
  
  
 ****PLEASE PROVIDE RESPONSE LETTER ADDRESSING EACH
 COMMENT TO HELP EXPEDITE THE REVIEW PROCESS.
 ****PLEASE INSERT ANY REVISED DRAWING AND REMOVE OLD
 DRAWING. SUBMIT OLD DRAWINGS FOR REFERENCE OF ALREADY
 REVIEWED DRAWINGS. DO NOT STAPLE OLD DRAWINGS TO PLANS.
  
  
 IF YOU HAVE ANY QUESTIONS, PLEASE CONTACT
 JULIO GOMEZ
 COMMERCIAL COMBINATION PLANS EXAMINER
 DEVELOPMENT SERVICES DEPARTMENT
 BUILDING DIVISION
 (561)805-6712
 [email protected]
  
  
  
  
  
  
 BUILDING REVIEW APPROVED WITH PROVISO:
 1- PROVIDE COMPLETE DETAILS/SPECIFICATIONS FOR THE
 INSTALLATION OF BRICK VENEER, INCLUDING VENEER SUPPORTS
 AT OPENINGS. ALSO, SPECIFY WEEP-HOLES, ETC.
 NOTE: PROVIDE COMPLETE DETAILS/ SPECIFICATIONS. DON'T
 CITE CODE SECTIONS.
  
 2- ENERGY CALCULATIONS WERE REVISED FOR FULL HOUSE
 COMPLIANCE INSTEAD OF ADDITION ALONE:
 A) REVISE CEILING INSULATION ITEM #10 TO MATCH PLANS.
 VENTED AND UNVENTED ROOFS.
 B) REVISE ROOF MATERIAL SHOWN ON PAGE 2 OF 5 TO MATCH
 PLANS AND PRODUCT APPROVALS SUBMITTED.
 C) REVISE CONCRETE BLOCK INSULATION ITEM #9 DOESN'T
 MATCH PLANS. SEE DETAIL #2 ON SHEET A-10.
 D) REVISE R-VALUE SHOWN ON THE CEILING INSULATION ON
 PAGE 3 OF 5 TO MATCH PLANS AND INFORMATION SHOWN ON
 ITEM #10.
 E) REVISE DOOR TYPE SPECIFIED ON PAGE 3 OF 5 TO MATCH
 PLANS AND PRODUCT APPROVALS SUBMITTED. THERE ARE NO
 INSULATED DOORS. DOORS WITH GLASS NEED TO BE INCLUDED
 IN THE WINDOWS AREA.
 F) REVISE WINDOWS OVERHANG DEPTH AND SEPARATION TO
 MATCH PLANS.
 G) REVISE NUMBER OF OCCUPANTS ON PAGE 2 OF 5. WHY 20
 PEOPLE IN A SINGLE FAMILY RESIDENCE.
 H) REVISE FLOOR TYPES ON PAGE 2 OF 5. 2ND FLOOR IS NOT
 ON SLAB ON GRADE.
  
 3- PROVIDE PRODUCT APPROVAL (2 COPIES) AS REQUIRED BY
 FAC 61G20-3.002(33) FOR:
 A) GARAGE DOORS THAT MEETS ALL THE DESIGN LOADS SHOWN
 ON SHEET S-6 (POSITIVE AND NEGATIVE).
 B) DOUBLE EXTERIOR DOORS THAT MEET THE DESIGN PRESSURES
 SPECIFIED ON PLANS.
  
 4- ENGINEER OF RECORD TO REVIEW AND APPROVE ABOVE
 PRODUCT APPROVALS.

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status F Date 2018-04-26 Cont ID  
Sent By jgomez Date 2018-04-26 Time 18:40 Rev Time 0.00
Received By jgomez Date 2018-04-25 Time 18:24 Sent To  
Notes
2018-04-26 18:42:32 
 RESIDENTIAL (R3) REVISION, BUILDING REVIEW COMMENTS
 CODE: FBC 5TH EDITION (2014).
  
 1- A) IT LOOKS LIKE THE ARCHITECT OF RECORD OF THIS
 PROJECT WAS CHANGED. SUCCESSOR ARCHITECT TO FOLLOW FAC
 SEC. 61G-18.002 PROCEDURES. SEE BELOW.
  
 B) NEW ARCHITECT SIGNING AND SEALING THE ARCHITECTURAL
 PLANS TO PROVIDE HIS INFORMATION IN THE TITLE BLOCK AS
 REQUIRED BY FAC 61G1-16.004.
  
 C) MISSING DRAWINGS S2, SN AND A3. SEE DRAWING INDEX ON
 SHEET CS.
 PROVIDE COMPLETE SET OF DRAWINGS. SEC. 107.2.1 CITY
 AMENDMENTS.
  
 D) COVER SHEET CS NEED TO HAVE THE SEAL AND SIGNATURE
 OF DESIGNER OF RECORD. SEC. 481 F.S.
 NOTE: COORDINATE WITH NAME OF DESIGN PROFESSIONAL SHOWN
 ON THE COVER SHEET.
  
  
 61G1-18.002 PROCEDURES FOR A SUCCESSOR ARCHITECT
 ADOPTING AS HIS OWN THE WORK OF ANOTHER ARCHITECT.
 (1) A SUCCESSOR REGISTERED ARCHITECT SEEKING TO REUSE
 ALREADY SEALED CONTRACT DOCUMENTS UNDER THE SUCCESSOR
 REGISTERED ARCHITECT'S SEAL MUST BE ABLE TO DOCUMENT
 AND PRODUCE UPON REQUEST EVIDENCE THAT HE HAS IN FACT
 RECREATED ALL THE WORK DONE BY THE ORIGINAL REGISTERED
 ARCHITECT. FURTHER, THE SUCCESSOR REGISTERED ARCHITECT
 MUST TAKE ALL PROFESSIONAL AND LEGAL RESPONSIBILITY FOR
 THE DOCUMENTS WHICH HE SEALED AND SIGNED AND CAN IN NO
 WAY EXEMPT HIMSELF FROM SUCH FULL RESPONSIBILITY. PLANS
 NEED NOT BE REDRAWN BY THE SUCCESSOR REGISTERED
 ARCHITECT; HOWEVER, JUSTIFICATION FOR SUCH ACTION MUST
 BE AVAILABLE THROUGH WELL KEPT AND COMPLETE
 DOCUMENTATION ON THE PART OF THE SUCCESSOR REGISTERED
 ARCHITECT AS TO HIS HAVING RETHOUGHT AND REWORKED THE
 ENTIRE DESIGN PROCESS. A SUCCESSOR REGISTERED ARCHITECT
 MUST USE HIS OWN TITLE BLOCK, SEAL AND SIGNATURE AND
 MUST REMOVE THE TITLE BLOCK, SEAL AND SIGNATURE OF THE
 ORIGINAL REGISTERED ARCHITECT BEFORE SEALING, SIGNING
 AND DATING ANY SEALED CONTRACT DOCUMENTS.
 (2) PRIOR TO SEALING, SIGNING AND DATING WORK, A
 SUCCESSOR REGISTERED ARCHITECT SHALL BE REQUIRED TO
 NOTIFY THE ORIGINAL REGISTERED ARCHITECT, HIS
 SUCCESSORS, OR ASSIGNS BY CERTIFIED LETTER TO THE LAST
 KNOWN ADDRESS OF THE ORIGINAL REGISTERED ARCHITECT OF
 THE SUCCESSOR'S INTENTION TO USE OR REUSE THE ORIGINAL
 REGISTERED ARCHITECT'S WORK. THE SUCCESSOR REGISTERED
 ARCHITECT WILL TAKE FULL RESPONSIBILITY FOR THE DRAWING
 AS THOUGH THEY WERE THE SUCCESSOR REGISTERED
 ARCHITECT'S ORIGINAL PRODUCT.
 RULEMAKING AUTHORITY 481.2055 FS. LAW IMPLEMENTED
 481.221(4) FS. HISTORY?NEW 1-16-86, AMENDED 5-16-89,
 FORMERLY 21B-18.002.
  
  
 2- SIZE OF ENTRY DOOR DOESN'T COMPLY WITH SEC. R311.2
 FBC-RESIDENTIAL. NEED 32" MIN. CLEAR OPENING. REVISE AS
 REQUIRED. TYPICALLY 36" DOORS ARE THE ONES THAT COMPLY.
  
 3- SPECIFY ON PLANS THE EXISTING HOUSE AND EQUIPMENT
 FINISH FLOOR ELEVATION AND THE PROPOSED ADDITION AND
 EQUIPMENT FINISH FLOOR ELEVATION. SEC. 94-546 CITY
 ORDINANCE. NOTE: APPROVED PLANS SPECIFIED THE EXISTING
 AND PROPOSED FINISH FLOOR ELEVATION TO BE 8.05'. BEFORE
 10/05/17 CITY ORDINANCE REQUIRED 1 FOOT FREE BOARD
 ABOVE THE BASE FLOOD ELEVATION. THEREFORE, THIS
 ELEVATION WAS IN COMPLIANCE. ELEVATION CERTIFICATES
 WILL BE REQUIRED DURING CONSTRUCTION.
  
 4- SHEET S-6: DOORS AND WINDOWS DESIGN PRESSURES SHOWN
 ON 1ST AND 2ND FLOOR PLAN DON'T MATCH DESIGN PRESSURES
 SHOWN ON THE TABLE ON SAME SHEET. REVISE AS REQUIRED TO
 MATCH. ALSO, DESIGN PRESSURES CAN NOT BE LOWER ON THE
 SECOND FLOOR THAN THE FIRST FLOOR. DESIGN PRESSURES CAN
 NOT BE LOWER FOR OPENINGS THAT ARE SMALLER. REVISE AS
 REQUIRED. NOTE: THE EDGE DISTANCE IS 4'-0" MIN AS
 REQUIRED BY NOTE AT THE BOTTOM OF FIGURE R301.2(7)
 FBC-RESIDENTIAL. REVISE AS REQUIRED.
  
 5- NEW SECOND FLOOR BALCONY: PLANS AND DETAILS CALL FOR
 SLOPE OF 1:60. REVISE AS REQUIRED. ROOF DECKS NEED TO
 BE COVERED WITH APPROVED ROOF COVERINGS. LOW SLOPE
 (FLAT ROOF) REQUIRE AN SLOPE OF 1/4" PER FOOT MIN.
 REVISE THE SLOPE SHOWN ON ALL PLANS AND DETAILS. SEC.
 R903.1 AND SEC. R905.9 FBC-RESIDENTIAL. NOTE: SPECIFY
 PROPOSED ROOF FINISH (TILE, ETC).
  
 4- NEW STAIRS: PROVIDE INFORMATION FOR TREADS AND
 RISERS DIMENSIONS SHOWING COMPLIANCE WITH SEC. R311.7.5
 FBC-RESIDENTIAL.
  
 5- PROVIDE PRODUCT APPROVAL (2 COPIES) AS REQUIRED BY
 FAC 61G20-3.001 FOR SECOND FLOOR BALCONY DECK COVERING.
 AND, CLEARLY IDENTIFY WHICH APPROVED ASSEMBLY IS GOING
 TO BE USED. NOTE: COORDINATE WITH ITEM #5 ABOVE.
  
 6- TOTAL NUMBER OF DRAWINGS SUBMITTED ARE 36 NOT 21 AS
 STATED ON THE REVISION FORM. REVISION FEE WAS UPDATED.
 THE REVISION FEE BALANCE IS $768.75.
  
 IMPORTANT NOTES:
 (1) ELEVATION CERTIFICATES WILL BE REQUIRED DURING
 CONSTRUCTION.
 (2)GARAGE FLOOD VENTS NEED TO BE INSTALLED BELOW THE
 BASE FLOOD ELEVATION.
 (3) ORIGINAL PERMIT WAS APPROVED WITH PROVISO. PROVIDE
 REQUIRED INFORMATION . SEE COPY OF PROVISO BELOW.
  
  
 ****PLEASE PROVIDE RESPONSE LETTER ADDRESSING EACH
 COMMENT TO HELP EXPEDITE THE REVIEW PROCESS.
 ****PLEASE INSERT ANY REVISED DRAWING AND REMOVE OLD
 DRAWING. SUBMIT OLD DRAWINGS FOR REFERENCE OF ALREADY
 REVIEWED DRAWINGS. DO NOT STAPLE OLD DRAWINGS TO PLANS.
  
  
 IF YOU HAVE ANY QUESTIONS, PLEASE CONTACT
 JULIO GOMEZ
 COMMERCIAL COMBINATION PLANS EXAMINER
 DEVELOPMENT SERVICES DEPARTMENT
 BUILDING DIVISION
 (561)805-6712
 [email protected]
  
  
  
  
  
  
 BUILDING REVIEW APPROVED WITH PROVISO:
 1- PROVIDE COMPLETE DETAILS/SPECIFICATIONS FOR THE
 INSTALLATION OF BRICK VENEER, INCLUDING VENEER SUPPORTS
 AT OPENINGS. ALSO, SPECIFY WEEP-HOLES, ETC.
 NOTE: PROVIDE COMPLETE DETAILS/ SPECIFICATIONS. DON'T
 CITE CODE SECTIONS.
  
 2- ENERGY CALCULATIONS WERE REVISED FOR FULL HOUSE
 COMPLIANCE INSTEAD OF ADDITION ALONE:
 A) REVISE CEILING INSULATION ITEM #10 TO MATCH PLANS.
 VENTED AND UNVENTED ROOFS.
 B) REVISE ROOF MATERIAL SHOWN ON PAGE 2 OF 5 TO MATCH
 PLANS AND PRODUCT APPROVALS SUBMITTED.
 C) REVISE CONCRETE BLOCK INSULATION ITEM #9 DOESN'T
 MATCH PLANS. SEE DETAIL #2 ON SHEET A-10.
 D) REVISE R-VALUE SHOWN ON THE CEILING INSULATION ON
 PAGE 3 OF 5 TO MATCH PLANS AND INFORMATION SHOWN ON
 ITEM #10.
 E) REVISE DOOR TYPE SPECIFIED ON PAGE 3 OF 5 TO MATCH
 PLANS AND PRODUCT APPROVALS SUBMITTED. THERE ARE NO
 INSULATED DOORS. DOORS WITH GLASS NEED TO BE INCLUDED
 IN THE WINDOWS AREA.
 F) REVISE WINDOWS OVERHANG DEPTH AND SEPARATION TO
 MATCH PLANS.
 G) REVISE NUMBER OF OCCUPANTS ON PAGE 2 OF 5. WHY 20
 PEOPLE IN A SINGLE FAMILY RESIDENCE.
 H) REVISE FLOOR TYPES ON PAGE 2 OF 5. 2ND FLOOR IS NOT
 ON SLAB ON GRADE.
  
 3- PROVIDE PRODUCT APPROVAL (2 COPIES) AS REQUIRED BY
 FAC 61G20-3.002(33) FOR:
 A) GARAGE DOORS THAT MEETS ALL THE DESIGN LOADS SHOWN
 ON SHEET S-6 (POSITIVE AND NEGATIVE).
 B) DOUBLE EXTERIOR DOORS THAT MEET THE DESIGN PRESSURES
 SPECIFIED ON PLANS.
  
 4- ENGINEER OF RECORD TO REVIEW AND APPROVE ABOVE
 PRODUCT APPROVALS.

Review Stop E ELECTRICAL
Rev No 2 Status P Date 2019-11-27 Cont ID  
Sent By jpearson Date 2019-11-27 Time 08:30 Rev Time 0.00
Received By jpearson Date 2019-11-27 Time 08:30 Sent To  
Notes
***NONE***

Review Stop E ELECTRICAL
Rev No 1 Status P Date 2018-04-27 Cont ID  
Sent By jpearson Date 2018-04-27 Time 10:13 Rev Time 0.00
Received By jpearson Date 2018-04-27 Time 09:22 Sent To I
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 5 Status N Date 2020-11-13 Cont ID  
Sent By pvalenti Date 2020-11-13 Time 06:47 Rev Time 0.00
Received By pvalenti Date 2020-11-13 Time 06:47 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 4 Status P Date 2019-12-02 Cont ID  
Sent By lcrespo Date 2019-12-02 Time 06:57 Rev Time 0.00
Received By lcrespo Date 2019-11-14 Time 15:17 Sent To  
Notes
2019-11-15 15:17:24R34

Review Stop I INCOMING/PROCESSING
Rev No 3 Status N Date 2019-08-08 Cont ID  
Sent By pvalenti Date 2019-08-08 Time 11:09 Rev Time 0.00
Received By pvalenti Date 2019-07-22 Time 15:09 Sent To  
Notes
2019-07-31 13:13:287/31 TO PV DESK
  
2019-07-22 15:09:39RESUB ROUTED TO JGOMEZ

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2019-03-19 Cont ID  
Sent By jgomez Date 2019-03-19 Time 10:50 Rev Time 0.00
Received By jgomez Date 2019-03-11 Time 11:08 Sent To I
Notes
2019-03-13 11:08:15RESUB ROUTED TO ZONING INBOX

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date   Cont ID  
Sent By   Date 2018-04-27 Time   Rev Time 0.00
Received By lmarchan Date 2018-04-10 Time 14:14 Sent To  
Notes
2018-04-11 14:15:12R27

Review Stop M MECHANICAL (A/C)
Rev No 3 Status P Date 2019-11-22 Cont ID  
Sent By pvalenti Date 2019-11-22 Time 15:02 Rev Time 0.00
Received By pvalenti Date 2019-11-22 Time 15:02 Sent To  
Notes
***NONE***

Review Stop M MECHANICAL (A/C)
Rev No 2 Status P Date 2019-08-07 Cont ID  
Sent By cmontell Date 2019-08-07 Time 18:09 Rev Time 0.00
Received By pvalenti Date 2019-08-07 Time 18:08 Sent To  
Notes
***NONE***

Review Stop M MECHANICAL (A/C)
Rev No 1 Status P Date 2018-04-19 Cont ID  
Sent By hmoser Date 2018-04-19 Time 13:08 Rev Time 0.00
Received By cmontell Date 2018-04-19 Time 12:21 Sent To  
Notes
***NONE***

Review Stop P PLUMBING
Rev No 2 Status P Date 2019-12-02 Cont ID  
Sent By gjohnson Date 2019-12-02 Time 06:47 Rev Time 0.00
Received By lcrespo Date 2019-12-02 Time 06:47 Sent To  
Notes
2019-12-02 07:17:3412/02/19 REVIEWED FOR CODE COMPLIANCE (PLUMBING)
  
 BY REVIEWING THE PLANS / SPECIFICATIONS FOR CODE
 COMPLIANCE DOES NOT RELIEVE THE OWNER, DESIGN
 PROFESSIONAL, CONTRACTORS OR THEIR REPRESENTATIVES FROM
 THE RESPONSIBILITY TO COMPLY WITH ALL LOCAL, STATE AND
 NATIONAL CODES AND STANDARDS IN EFFECT AT THE TIME OF
 PERMIT ISSUANCE. OUR REVIEW IS NOT A CHECK OF EVERY
 ITEM AND DOES NOT PREVENT THIS DEPARTMENT FROM
 REQUIRING CORRECTIONS DURING CONSTRUCTION. ANY CHANGES
 / ALTERATIONS TO APPROVED PLANS SHALL BE APPROVED TO
 AVOID VOIDING OF THE PERMIT.
  
 LUIS A. CRESPO
 PLUMBING INSPECTOR /
 PLUMBING PLAN REVIEW
 AVAILABLE FROM 6:30 AM 7:30 / 2:00 PM TO 5:00 PM
 [email protected]
 561-701-6437
  

Review Stop P PLUMBING
Rev No 1 Status P Date 2018-04-25 Cont ID  
Sent By gjohnson Date 2018-04-25 Time 16:42 Rev Time 0.00
Received By gjohnson Date 2018-04-25 Time 15:47 Sent To  
Notes
***NONE***

Review Stop Z ZONING
Rev No 2 Status P Date 2019-03-14 Cont ID  
Sent By awooten Date 2019-03-14 Time   Rev Time 0.00
Received By awooten Date 2019-03-14 Time   Sent To B
Notes
***NONE***

Review Stop Z ZONING
Rev No 1 Status P Date 2018-04-23 Cont ID  
Sent By awooten Date 2018-04-23 Time   Rev Time  
Received By awooten Date 2018-04-23 Time   Sent To  
Notes
***NONE***