| Plan Review Stops For Permit 18030507 |
| Review Stop |
B |
BUILDING (STRUCTURAL) |
| Rev No |
1 |
Status |
P |
Date |
2018-03-23 |
|
|
Cont ID |
|
| Sent By |
tmoore |
Date |
2018-03-23 |
Time |
08:37 |
Rev Time |
0.00 |
| Received By |
tmoore |
Date |
2018-03-23 |
Time |
08:37 |
Sent To |
ENG |
|
| Notes |
| 2018-03-23 08:37:52 | HAVE ALL NEEDED UTILITY RELEASES. PASSING AND MOVING TO | | | ENGINEERING'S MAILBOX. TM |
|
|
| Review Stop |
ENG |
ENGINEERING CSD |
| Rev No |
1 |
Status |
P |
Date |
2018-03-27 |
|
|
Cont ID |
|
| Sent By |
hhall |
Date |
2018-03-27 |
Time |
10:24 |
Rev Time |
0.00 |
| Received By |
hhall |
Date |
2018-03-27 |
Time |
10:24 |
Sent To |
HIST |
|
| Notes |
|
|
| Review Stop |
HIST |
HISTORICAL |
| Rev No |
1 |
Status |
P |
Date |
2018-03-28 |
|
|
Cont ID |
|
| Sent By |
destabro |
Date |
2018-03-28 |
Time |
16:25 |
Rev Time |
0.00 |
| Received By |
destabro |
Date |
2018-03-28 |
Time |
16:25 |
Sent To |
I |
|
| Notes |
| 2018-03-28 16:26:05 | 3/28/2018 - NOT A HISTORIC/DESIGNATED STRUCTURE. DLE |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
1 |
Status |
N |
Date |
2018-03-28 |
|
|
Cont ID |
|
| Sent By |
cpuell |
Date |
2018-03-28 |
Time |
17:27 |
Rev Time |
0.00 |
| Received By |
cpuell |
Date |
2018-03-12 |
Time |
14:43 |
Sent To |
|
|
| Notes |
| 2018-03-13 14:43:12 | ROUTED TO TMOORE'S DESK |
|
|
|