Plan Review Details - Permit 17110469
Plan Review Stops For Permit 17110469
Review Stop E ELECTRICAL
Rev No 3 Status P Date 2017-12-14 Cont ID  
Sent By jleahy Date 2017-12-14 Time 13:22 Rev Time 0.00
Received By jleahy Date 2017-12-14 Time 13:22 Sent To  
Notes
***NONE***

Review Stop E ELECTRICAL
Rev No 2 Status F Date 2017-12-08 Cont ID  
Sent By jleahy Date 2017-12-08 Time 16:04 Rev Time 0.00
Received By jleahy Date 2017-12-08 Time 16:04 Sent To I
Notes
2017-12-08 16:08:29YOU NEED TO READ COMMENTS FROM ORIGINAL PLAN REVIEW
  
 ENGINEERS SEAL AND SIGNATURE REQUIRED ON PLANS PER
 471.003(H) 480 VOLTS
  
 SUBMIT A SINED CONTRACT FOR EVENT WORK , WHICH WOULD
 INCLUDE ALL MATERIALS, AND LABOR.
  
 SIGNED CONTRACT TO BE SUBMITTED OR CITY WILL ACCESS A
 VALUE OF $80,000 FOR PERMIT VALUE.

Review Stop E ELECTRICAL
Rev No 1 Status F Date 2017-11-28 Cont ID  
Sent By jleahy Date 2017-11-28 Time 07:11 Rev Time 0.00
Received By jleahy Date 2017-11-28 Time 07:11 Sent To  
Notes
2017-11-28 07:30:44FLORIDA BUILDING CODE 2014 5TH EDITION
 FLORIDA BUILDING CODE ENERGY CONSERVATION 2014 5TH ED
 NFPA 70 2011 EDITION
  
 JAKE LEAHY
 ELECTRICAL PLANS EXAMINER II
 561-805-6713
 [email protected]
  
 PLAN IS REQUIRED TO BE SIGNED AND SEALED BY A DESIGN
 PROFESSIONAL OR THE ELECTRICAL CONTRACTOR QUALIFIER. FS
 471.003(2)(H); 471.025; FBC 107.2.1
  
 480 VOLT DISTRIBUTION IS ABOVE LICENSE ALLOWANCE, NEEDS
 ENGINEERS SEAL
  
 FBC-107.1 GENERAL - FAC 61G15-23.002 - PROVIDE A TITLE
 BLOCK FOR THE ENGINEER OF RECORD CONSISTENT WITH THE
 REQUIREMENTS OF THIS SECTION, E.G.: FIRM NAME, LICENSE
 NUMBER, PHONE NUMBER...ETC.
  
 FBC 109.3 BUILDING PERMIT VALUATION. FOR PERMITTING
 PURPOSES, VALUATION OF BUILDINGS AND SYSTEMS SHALL BE
 TOTAL REPLACEMENT VALUE TO INCLUDE STRUCTURAL,
 ELECTRIC, PLUMBING, MECHANICAL,
 INTERIOR FINISH, RELATIVE SITE WORK, ARCHITECTURAL AND
 DESIGN FEES, MARKETING COSTS, OVERHEAD AND PROFIT;
 EXCLUDING ONLY LAND VALUE. VALUATION REFERENCES MAY
 INCLUDE THE LATEST PUBLISHED
 DATA OF NATIONAL CONSTRUCTION COST ANALYSIS SERVICES
 (MARSHALL-SWIFT, MEANS, ETC.), AS PUBLISHED BY
 INTERNATIONAL CODE CONGRESS. FINAL BUILDING PERMIT
 VALUATION SHALL BE SET BY THE BUILDING OFFICIAL.
  
 VALUE SHOWN IS LOW, PLEASE PROVIDE A SIGNED CONTRACT
 FOR WORK PROVIDED.
  
  

Review Stop FIRE FIRE DEPARTMENT
Rev No 2 Status P Date 2017-12-08 Cont ID  
Sent By pleduc Date 2017-12-08 Time   Rev Time 0.00
Received By pleduc Date 2017-12-07 Time 16:04 Sent To E
Notes
***NONE***

Review Stop FIRE FIRE DEPARTMENT
Rev No 1 Status P Date 2017-11-21 Cont ID  
Sent By jleahy Date 2017-11-28 Time 07:31 Rev Time 0.00
Received By pleduc Date 2017-11-21 Time 11:04 Sent To E
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2017-12-08 Cont ID  
Sent By jleahy Date 2017-12-08 Time 16:08 Rev Time 0.00
Received By jleahy Date 2017-12-06 Time 10:45 Sent To  
Notes
2017-12-07 10:45:58RESUB ROUTED TO FIRE INBOX

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2017-11-28 Cont ID  
Sent By jleahy Date 2017-11-28 Time 07:31 Rev Time 0.00
Received By jleahy Date 2017-11-13 Time 08:07 Sent To FIRE
Notes
2017-11-21 08:08:01DELAYED, DID NOT SEND UNTIL 11/21/17


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved