| Plan Review Stops For Permit 17110388 |
| Review Stop |
FIRE |
FIRE DEPARTMENT |
| Rev No |
1 |
Status |
P |
Date |
2017-11-13 |
|
|
Cont ID |
|
| Sent By |
pleduc |
Date |
2017-11-13 |
Time |
|
Rev Time |
0.00 |
| Received By |
pleduc |
Date |
2017-11-13 |
Time |
12:25 |
Sent To |
M |
|
| Notes |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
4 |
Status |
N |
Date |
|
|
|
Cont ID |
|
| Sent By |
|
Date |
2018-09-05 |
Time |
|
Rev Time |
0.00 |
| Received By |
lmarchan |
Date |
2018-08-21 |
Time |
14:24 |
Sent To |
|
|
| Notes |
| 2018-09-04 13:16:12 | TO L MARCHANT | | 2018-08-22 14:24:42 | RESUB ROUTED TO ZONING INBOX |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
3 |
Status |
N |
Date |
|
|
|
Cont ID |
|
| Sent By |
|
Date |
2018-08-13 |
Time |
|
Rev Time |
0.00 |
| Received By |
lmarchan |
Date |
2018-08-07 |
Time |
14:53 |
Sent To |
|
|
| Notes |
| 2018-08-10 14:30:18 | TO LMARCHAN. | | 2018-08-08 14:53:45 | RESUB ROUTED TO ZONING INBOX |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
2 |
Status |
N |
Date |
2018-03-01 |
|
|
Cont ID |
|
| Sent By |
cpuell |
Date |
2018-03-01 |
Time |
13:24 |
Rev Time |
0.00 |
| Received By |
cpuell |
Date |
2018-02-07 |
Time |
13:59 |
Sent To |
|
|
| Notes |
| 2018-02-28 17:06:32 | 2/28 TO AA DESK | | | | | | | | 2018-02-28 14:00:03 | 2/28 TO CC DESK | | | | | 2018-02-08 13:59:41 | RESUB ROUTED TO ZONING INBOX |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
1 |
Status |
N |
Date |
2017-12-04 |
|
|
Cont ID |
|
| Sent By |
cpuell |
Date |
2017-12-04 |
Time |
15:21 |
Rev Time |
0.00 |
| Received By |
cpuell |
Date |
2017-11-09 |
Time |
10:06 |
Sent To |
|
|
| Notes |
| 2017-11-13 10:06:44 | ROUTED TO FIRE INBOX |
|
|
| Review Stop |
M |
MECHANICAL (A/C) |
| Rev No |
4 |
Status |
P |
Date |
2018-09-05 |
|
|
Cont ID |
|
| Sent By |
ccole |
Date |
2018-09-05 |
Time |
11:07 |
Rev Time |
0.00 |
| Received By |
ccole |
Date |
2018-09-05 |
Time |
10:30 |
Sent To |
I |
|
| Notes |
|
|
| Review Stop |
M |
MECHANICAL (A/C) |
| Rev No |
3 |
Status |
F |
Date |
2018-08-13 |
|
|
Cont ID |
|
| Sent By |
ccole |
Date |
2018-08-13 |
Time |
15:59 |
Rev Time |
0.00 |
| Received By |
ccole |
Date |
2018-08-13 |
Time |
13:43 |
Sent To |
I |
|
| Notes |
| 2018-08-13 16:05:47 | 3RD REVIEW FBC-2014 MECHANICAL | | | PERMIT #17110388 | | | 8/13/18 | | | | | | PLAN REVIEW RESULTS: DENIED. | | | | | | 1) BASED ON THE SUBMITTED AC SIZING CALCULATIONS FOR | | | THE KITCHEN, ALEX KHAROSKA OF CREDO CONSULTING | | | ENGINEERS IS STATING IN HIS LETTER THAT THE EXISTING | | | 8-TON COOLING SYSTEM PERMITTED UNDER THE MASTER PERMIT | | | #17020359, MUST BE ENLARGED TO A 10-TON SYSTEM TO | | | ABSORB THE ADDITIONAL HEAT LOAD IN THE KITCHEN FROM THE | | | EXHAUST HOOD MAKE UP AIR. PLEASE PROVIDE A PERMIT | | | APPLICATION AND PLAN FOR ENLARGING THE SYSTEM.- SECTION | | | 107.2.1 WEST PALM BEACH AMENDMENTS TO THE FBC. | | | | | | WHEN RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE | | | LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY | | | RE-SUBMITTAL FORM. ADDITIONALLY, PLEASE INSERT | | | CORRECTED PLAN SHEETS INTO THE SETS, REMOVE THE | | | PREVIOUSLY REVIEWED SHEETS AND MARK VOID ON THEM, AND | | | KEEP THEM WITH THE SUBMITTALS. | | | | | | CHRISTOPHER L. COLE | | | MECHANICAL PLANS EXAMINER | | | 401 CLEMATIS STREET | | | WEST PALM BEACH FL 33401 | | | 561-805-6719 | | | [email protected] | | | |
|
|
| Review Stop |
M |
MECHANICAL (A/C) |
| Rev No |
2 |
Status |
F |
Date |
2018-02-28 |
|
|
Cont ID |
|
| Sent By |
ccole |
Date |
2018-02-28 |
Time |
16:56 |
Rev Time |
0.00 |
| Received By |
ccole |
Date |
2018-02-28 |
Time |
14:05 |
Sent To |
|
|
| Notes |
| 2018-02-28 17:04:29 | 2ND REVIEW FBC-2014 MECHANICAL | | | PERMIT #17110388 | | | 2/28/18 | | | | | | PLAN REVIEW RESULTS: DENIED. | | | | | | 1) IN AN EFFORT TO SHOW THE COMPLIANCE WITH SECTION | | | 508.1.1 MAKEUP AIR TEMPERATURE FOR THE KITCHEN HOOD | | | EXHAUST SYSTEM, THE ENGINEER HAS SUBMITTED AC LOAD | | | CALCULATIONS , HOWEVER THE CALCULATIONS PROVIDE GENERAL | | | HEAT LOAD DATA FOR THE KITCHEN IN BTUH, BUT DO NOT | | | SPECIFICALLY INDICATE THE HEAT LOAD FROM THE MAKEUP | | | AIR, OR INDICATE THAT THE AC SYSTEM HAS BEEN SIZED TO | | | | | | ACCOMODATE THE ADDED LOAD. | | | | | | WHEN RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE | | | LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY | | | RE-SUBMITTAL FORM. ADDITIONALLY, PLEASE INSERT | | | CORRECTED PLAN SHEETS INTO THE SETS, REMOVE THE | | | PREVIOUSLY REVIEWED SHEETS AND MARK VOID ON THEM, AND | | | KEEP THEM WITH THE SUBMITTALS. | | | | | | CHRISTOPHER L. COLE | | | MECHANICAL PLANS EXAMINER | | | 401 CLEMATIS STREET | | | WEST PALM BEACH FL 33401 | | | 561-805-6719 | | | [email protected] | | | |
|
|
| Review Stop |
M |
MECHANICAL (A/C) |
| Rev No |
1 |
Status |
F |
Date |
2017-11-18 |
|
|
Cont ID |
|
| Sent By |
ccole |
Date |
2017-11-18 |
Time |
08:48 |
Rev Time |
0.00 |
| Received By |
ccole |
Date |
2017-11-18 |
Time |
08:48 |
Sent To |
Z |
|
| Notes |
| 2017-11-18 08:55:51 | 1ST REVIEW FBC-2014 MECHANICAL | | | PERMIT #17110388 | | | 11/18/17 | | | | | | PLAN REVIEW RESULTS: DENIED. | | | | | | 1) VERIFY COMPLIANCE WITH SECTION 508.1.1: MAKEUP AIR | | | TEMPERATURE. | | | THE TEMPERATURE DIFFERENTIAL BETWEEN MAKEUP AIR AND THE | | | AIR IN THE CONDITIONED SPACE SHALL NOT EXCEED 10?F | | | (6?C) EXCEPT WHERE THE ADDED HEATING AND COOLING LOADS | | | OF THE MAKEUP AIR DO NOT EXCEED THE CAPACITY OF THE | | | HVAC SYSTEM. | | | | | | 2) PROVIDE WIND LOAD ENGINEERING FOR INSTALLATION OF | | | THE ROOFTOP FANS AND THE MAKEUP AIR DUCT ON THE | | | EXTERIOR WALL. PLEASE PROVIDE THE DESIGN CRITERIA PER | | | SECTION 1609 FBC-014 BUILDING, AND THE MIAMI-DADE NOA'S | | | FOR THE FANS. | | | | | | CHRISTOPHER L. COLE | | | MECHANICAL PLANS EXAMINER | | | 401 CLEMATIS STREET | | | WEST PALM BEACH FL 33401 | | | 561-805-6719 | | | [email protected] | | | | | | |
|
|
| Review Stop |
Z |
ZONING |
| Rev No |
4 |
Status |
P |
Date |
2018-09-04 |
|
|
Cont ID |
|
| Sent By |
aaponte |
Date |
2018-09-04 |
Time |
13:00 |
Rev Time |
0.00 |
| Received By |
aaponte |
Date |
2018-09-04 |
Time |
13:00 |
Sent To |
|
|
| Notes |
| 2018-09-04 13:15:48 | PROVISO:1. DUCT SHALL BE PAINTED IN THE SAME COLOR THAN | | | THE WALL TO MINIMIZE IMPACT. | | | 2. PARAPET WALL SHALL BE THE SAME HEIGHT THAN | | | EQUIPEMENT. |
|
|
| Review Stop |
Z |
ZONING |
| Rev No |
3 |
Status |
F |
Date |
2018-08-10 |
|
|
Cont ID |
|
| Sent By |
aaponte |
Date |
2018-08-10 |
Time |
14:29 |
Rev Time |
0.00 |
| Received By |
aaponte |
Date |
2018-08-10 |
Time |
14:28 |
Sent To |
M |
|
| Notes |
| 2018-08-10 14:29:52 | 1. REPEAT COMMENT: PARAPET WALL SHALL BE RAISED TO BE | | | THE SAME HEIGHT OF PROPOSED EQUIPMENT TO COMPLY WITH | | | MECHANICAL SCREENING. | | | 2. PLEASE INDICATE IN WHICH ELEVATION IS THE GALVANIZED | | | DUCT PROPOSED. DUCT WILL NOT BE ALLOWED ON THE STREET | | | FRONTAGES. | | | FOR ADDITIONAL INFORMATION PLEASE CONTACT ANA MARIA | | | APONTE AT 561-822-1439. |
|
|
| Review Stop |
Z |
ZONING |
| Rev No |
2 |
Status |
F |
Date |
2018-03-01 |
|
|
Cont ID |
|
| Sent By |
AA |
Date |
2018-03-01 |
Time |
11:40 |
Rev Time |
0.00 |
| Received By |
aaponte |
Date |
2018-02-13 |
Time |
11:34 |
Sent To |
|
|
| Notes |
| 2018-03-01 11:47:18 | 1. REPEAT COMMENT: PARAPET WALL SHALL BE RAISED TO BE | | | THE SAME HEIGHT OF PROPOSED EQUIPMENT TO COMPLY WITH | | | MECHANICAL SCREENING. | | | 2. PLEASE INDICATE IN WHICH ELEVATION IS THE GALVANIZED | | | DUCT PROPOSED. WHAT IS THE PROPOSED SCREENING FOR SUCH | | | MECHANICAL EQUIPMENT? | | | FOR ADDITIONAL INFORMATION PLEASE CONTACT ANA MARIA | | | APONTE AT 561-822-1439. |
|
|
| Review Stop |
Z |
ZONING |
| Rev No |
1 |
Status |
F |
Date |
2017-12-04 |
|
|
Cont ID |
|
| Sent By |
KM |
Date |
2017-12-04 |
Time |
|
Rev Time |
0.00 |
| Received By |
kmartin |
Date |
2017-12-04 |
Time |
14:13 |
Sent To |
I |
|
| Notes |
| 2017-12-04 14:15:48 | PARAPET SHALL BE RAISED TO MATCH THE MECHANICAL | | | EQUIPMENT. | | | | | | FOR MORE INFORMATION, PLEASE CONTACT KEVIN MARTIN | | | -URBAN DESIGN PLANNER AT [email protected]. |
|
|