| 2017-10-19 12:37:21 | 1ST REVIEW: FBC 2014 5TH EDITION |
| | |
| | PLUMBING COMMENTS: |
| | |
| | 1. AIR ADMITTANCE VALVES SHALL NOT BE USED ON SUMP PITS |
| | UNLESS THEY COMPLY WITH FBC PL 918.8 PROVIDE |
| | MANUFACTURE SPECIFICATION THAT SHOW THE AAV WAS |
| | ENGINEERED TO USE AS A VENT FOR A SUMP PIT SYSTEM. |
| | PER FBC PL 918.8 PROHIBITED INSTALLATIONS. |
| | AIR ADMITTANCE VALVES WITHOUT AN ENGINEERED DESIGN |
| | SHALL NOT BE UTILIZED TO VENT SUMPS OR TANKS OF ANY |
| | TYPE. |
| | |
| | 2. THE BACK WATER VALVE SHALL NOT BE INSTALLED ON THIS |
| | SYSTEM PER FBC PL 715.1 SEWAGE BACKFLOW. |
| | PLUMBING FIXTURES INSTALLED ON A FLOOR WITH A FINISHED |
| | FLOOR ELEVATION ABOVE THE ELEVATION OF THE MANHOLE |
| | COVER OF THE NEXT UPSTREAM MANHOLE IN THE PUBLIC SEWER |
| | SHALL NOT DISCHARGE THROUGH A BACKWATER VALVE. |
| | |
| | 3. PLEASE PROVIDE A DETAIL SHOWING COMPLIANCE WITH FBC |
| | PL 712.3.5. PUMP CONNECTION TO THE DRAINAGE SYSTEM. |
| | PUMPS CONNECTED TO THE DRAINAGE SYSTEM SHALL CONNECT TO |
| | A BUILDING SEWER, BUILDING DRAIN, SOIL STACK, WASTE |
| | STACK OR HORIZONTAL BRANCH DRAIN. WHERE THE DISCHARGE |
| | LINE CONNECTS INTO HORIZONTAL DRAINAGE PIPING, THE |
| | CONNECTION SHALL BE MADE THROUGH A WYE FITTING INTO THE |
| | TOP OF THE DRAINAGE PIPING AND SUCH WYE FITTING SHALL |
| | BE LOCATED NOT LESS THAN 10 PIPE DIAMETERS FROM THE |
| | BASE OF ANY SOIL STACK, WASTE STACK OR FIXTURE DRAIN. |
| | |
| | 4. SUBMITTAL 17090216 FOR THE SUMP PIT SHALL BE |
| | APPROVED BEFORE THIS REV CAN BE APPROVED OR THE |
| | SUBMITTAL AND REV SHALL BE COMBINED. |
| | |
| | 5. PLEASE PROVIDE MANUFACTURE SPECIFICATIONS FOR THE |
| | SUMP PUMP. PER WPB AMEND TO FBC 107.2.1 |
| | |
| | |
| | PLEASE NOTE THAT SUBMITTAL OF ADDITIONAL AND/OR REVISED |
| | MATERIALS MAY RESULT IN NEW PLAN REVIEW COMMENTS. |
| | WHEN RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE |
| | LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY |
| | RE-SUBMITTAL FORM. PLEASE, ADDITIONALLY, INSERT |
| | CORRECTED PAGES INTO TO SUBMITTAL AND REMOVE OR VOID |
| | THE PREVIOUSLY REVIEWED SHEETS. |
| | |
| | GEORGE JOHNSON |
| | PLUMBING PLANS EXAMINER |
| | CITY OF WEST PALM BEACH |
| | 561-805-6711 |
| | [email protected] |
| | |
| | |