| 2018-04-25 12:03:55 | PERMIT # 17100128 |
| | REVIEW COMMENTS - FIRE DEPARTMENT |
| | |
| | 1) APPROVAL OF THIS SUBMITTAL DOES NOT CONSTITUTE |
| | APPROVAL OR AUTHORIZATION TO OCCUPY THE BUILDING. A |
| | 131-FIRE FINAL INSPECTION SHALL BE SCHEDULED, VIA THE |
| | CITY'S PERMIT AUTOMATED SYSTEM, AND A FULL FIRE |
| | INSPECTION SHALL BE CONDUCTED TO ENSURE COMPLIANCE OF |
| | ALL APPLICABLE FIRE CODES AND/ OR AHJ REQUIREMENTS AS A |
| | CONDITION OF TCO. |
| | |
| | 2) APPROVAL OF THE USE OF THE CORRIDOR THAT IS PART OF |
| | PHASE 2, AS A SECOND MEANS OF EGRESS OF PART OF PHASE |
| | 1, WILL REQUIRE COMPLIANCE OF THAT CORRIDOR WITH ALL |
| | EXIT CORRIDOR REQUIREMENTS AS LISTED IN NFPA 101, |
| | CHAPTER 7: MEANS OF EGRESS; PRIOR TO APPROVAL OF TCO |
| | FOR PHASE 1. |
| | |
| | 3) USE OF THE CORRIDOR THAT IS PART OF PHASE 2, AS A |
| | MEANS OF EGRESS, PRESENTS A CONCERN WITH ACCESSIBILITY |
| | TO THE VACANT UNITS THAT WILL STILL BE UNDER |
| | CONSTRUCTION. WHAT MEASURES WILL BE IN PLACE TO ENSURE |
| | THAT THESE UNITS WILL NOT BE ACCESSIBLE TO ANYONE |
| | UTILIZING THE CORRIDOR AS A MEANS OF EGRESS? HOW TO WE |
| | MAINTAIN THE UNITS CLOSED AND SECURED AT ALL TIMES, SO |
| | THAT ONLY CONSTRUCTION PERSONNEL ARE ACCESSING THEM? |
| | |
| | 4) STAIRWAYS # 2, 3, AND 4, SHALL BE IN FULL COMPLIANCE |
| | OF ALL REQUIREMENTS LISTED UNDER NFPA 101, CHAPTER 7: |
| | MEANS OF EGRESS; PRIOR TO APPROVAL OF TCO FOR PHASE 1. |
| | |
| | 5) ALL FIRE AND LIFE SAFETY SYSTEMS FOR THE BUILDING |
| | SHALL BE FULLY INSTALLED, FUNCTIONAL, TESTED, AND |
| | APPROVED, PRIOR TO OBTAINING TCO. THIS REQUIREMENT |
| | INCLUDES, BUT IS NOT LIMITED TO, THE FIRE ALARM SYSTEM, |
| | THE FIRE SPRINKLER SYSTEM, EXIT SIGNS, EMERGENCY |
| | LIGHTING, FIRE EXTINGUISHERS, ETC. |
| | |
| | |
| | |
| | SUE ELLEN CALDERON |
| | ASSISTANT FIRE MARSHAL |
| | FIRE INVESTIGATOR & INSPECTOR |
| | OFFICE OF THE FIRE MARSHAL |
| | WEST PALM BEACH FIRE RESCUE |
| | [email protected] |
| | (561) 804-4751 |
| | |