Plan Review Details - Permit 17090200
Plan Review Stops For Permit 17090200
Review Stop B BUILDING (STRUCTURAL)
Rev No 3 Status P Date 2018-02-28 Cont ID  
Sent By aclange Date 2018-02-28 Time 07:37 Rev Time 0.00
Received By aclange Date 2018-02-26 Time 13:24 Sent To  
Notes
2018-02-27 11:39:33PROVISO:
 PRIOR TO CONCRETE POUR, A "BUILDING UNDER CONSTRUCTION"
 (FORM BOARD) ELEVATION CERTIFICATE IS REQUIRED.
 PRIOR TO FINAL INSPECTION, A "FINISHED CONSTRUCTION"
 ELEVATION CERTIFICATE IS REQUIRED. THE FINISHED
 CONSTRUCTION ELEVATION CERTIFICATE MAY BE SENT VIA
 EMAIL FOR PRELIMINARY REVIEW. A SIGNED AND SEALED
 ORIGINAL FINISHED CONSTRUCTION ELEVATION CERTIFICATE IS
 TO BE SUBMITTED AT THE BUILDING DIVISION, REVIEWED AND
 APPROVED PRIOR TO FINAL INSPECTION. THIS SHOULD BE DONE
 AS EARLY AS POSSIBLE AFTER FINAL GRADE IS COMPLETE.

Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status F Date 2018-02-01 Cont ID  
Sent By aclange Date 2018-02-01 Time 09:28 Rev Time 0.00
Received By aclange Date 2018-02-01 Time 09:23 Sent To  
Notes
2018-02-01 09:26:37****PLAN REVIEW COMMENTS****
 PERMIT APPLICATION 17090200
 ART LANGE - BUILDING PLANS EXAMINER
 561-805-6667 [email protected]
 FBC FLORIDA BUILDING CODE 2014 5TH EDITION/ FRC FLORIDA
 RESIDENTIAL CODE 2015 5TH EDITION
  
 2ND REVIEW
 DATE: FEBRUARY 1, 2018
 ACTION: PLAN REVIEW IN PROCESS REVIEW NOT COMPLETE
  
 1. NO ACTION REQUIRED AT THIS TIME.
 NOTICE ONLY; THE CITY OF WEST PALM BEACH ART IN PUBLIC
 PLACES ORDINANCE REQUIREMENT THAT APPLIES TO ANY
 REMODEL OR NEW CONSTRUCTION PROJECT FOR WHICH THE
 PERMIT APPLICATION WAS SUBMITTED AFTER 7/1/14, AND THE
 TOTAL PROJECT CONSTRUCTION COSTS ARE EQUAL TO OR
 GREATER THAN $500,000. PER CITY OF WEST PALM BEACH
 ORDINANCE NO. 4504-14, AND CITY OF WEST PALM BEACH CODE
 OF ORDINANCES, ARTICLE V, ART IN PUBLIC PLACES, SECTION
 78-123(A) AND SECTION 78-126(A), THE ART ASSESSMENT IS
 1% OF THE TOTAL PROJECT CONSTRUCTION COST.
 PER CITY OF WEST PALM BEACH CODE OF ORDINANCES, ARTICLE
 V, ART IN PUBLIC PLACES, SECTION 78-122, RENOVATION AND
 NEW CONSTRUCTION PROJECTS ARE ASSESSED CUMULATIVELY, SO
 THE ART ASSESSMENT WILL BE APPLICABLE TO ALL FUTURE
 PROJECTS.
  
 2. FLOOD ZONE CERITICATE NOT PROVIDED.
 FLOOD ZONE CERTIFICATES:
 FBC BUILDING 1612 AND CITY OF WPB CODE OF ORDINANCES
 SECTION 94-546. STRUCTURE IS LOCATED IN AN "A" FLOOD
 ZONE. A FLOOD ELEVATION CERTIFICATE WILL BE REQUIRED.
 DURING THE PERMITTING OF THIS STRUCTURE THERE WILL BE
 REQUIRED (3) DIFFERENT FLOOD ZONE CERTIFICATES
 REQUIRED:
  
 (1) A FLOOD ZONE CERTIFICATE IS REQUIRED AS PART OF THE
 PLAN REVIEW DOCUMENTS WITH THE PROPOSED FINISH FLOOR
 HEIGHT.
  
 (2) ONCE THE FIRST FLOOR SLAB IS POURED THE 2ND
 ELEVATION CERTIFICATE IS REQUIRED.
  
 (3) BEFORE THE ISSUANCE OF A CERTIFICATE OF OCCUPANCY
 OR A CERTIFICATE OF COMPLETION THE 3RD FLOOD ZONE
 CERTIFICATE IS REQUIRED WITH THE HEIGHT OF ALL EXTERIOR
 ATTENDANTS A/C PADS OR OTHER SLABS FOR GENERATORS.
  
 3. NOT ADDRESSED.
 SUBSURFACE EXPLORATION AND GEOTECHNICAL REPORT FROM
 ARDAMAN AND ASSOCIATES HAS NOT BEEN ACKNOWLEDGED BY THE
 ARCHITECT OF RECORD. PLEASE PROVIDE A STAMP AND
 SIGNATURE SHOWING THAT YOU HAVE SEEN THIS DOCUMENT.
 SEE 8.2.1 FOR RECOMMENDED FOUNDATION OPTIONS ON THIS
 REPORT. ON S0.0.1 FOUNDATION NOTE 1 BASED ON
 RECOMMENDATIONS FROM THE GEOTECHNICAL REPORT NOT HAS
 NOT BEEN ADDRESSED. SINCE THE RECOMMENDATION OF USING
 AUGERED CAST IN PLACE CONCRETE PILES HAS NOT BEEN USED
 WILL VIBROCOMPACTION BE COMBINED WITH A JET GROUNTING
 PROGRAM.
  
  
 SUPPORTING DOCUMENTS SUBMITTED FROM ARDAMAN @
 ASSOCIATED SHALL BE REVIEWED BY THE ARCHITECT OF RECORD
 AND STAMPED AS REVIEWED AND APPROVED.
 FL 61G1-23.015 (2) THE ARCHITECT IS RESPONSIBLE FOR
 SUPERVISING AND REVIEWING ALL PROJECT DATA, REPORTS,
 SHOP DRAWINGS ETC...
  
 4. ADDRESSED
 4A. ADDRESSED
  
 4B. NOT ADDRESSED. I EMAILED THE CONTRACTOR TIM MOORE
 AN COPY OF THE THRESHOLD INSPECTOR APPLICATION ON
 1/31/18 AT 4:23PM
  
 THRESHOLD INSPECTOR: WPB AMENDMENT 109.3.6.2 W.P.B.
 CONSTRUCTION SERVICES DEPARTMENT REQUESTS FOR THRESHOLD
 BUILDINGS A SPECIAL INSPECTOR AS REQUIRED BY FL S S
 553.79(5) FLORIDA STATUTES TO THE MINIMUM INSPECTIONS
 REQUIRED BY THIS CODE. THE THRESHOLD INSPECTION FORMS
 ARE REQUIRED TO BE FILED OUT BY ALL PARTIES WITH
 INTEREST, NOTARIZED AND RETURNED TO THIS OFFICE, AND
 REVIEWED AND APPROVED BEFORE PERMIT ISSUANCE WILL TAKE
 PLACE.
  
 4C. NOT ADDRESSED
 FOR THE SPECIAL INSPECTOR PLEASE PROVIDE A RESUME' OF
 INSPECTION EXPERIENCE ON PREVIOUS PROJECT. THE RESUME'
 MUST BE ACCOMPANIED BY ALL CERTIFICATES AS SPECIFIED
 HEREIN. THE BUILDING OFFICIAL OR HIS DESIGNEE WILL
 REVIEW THE RESUME'. AFTER THE RESUME' IS REVIEWED, AN
 INTERVIEW WILL BE SCHEDULED. UNDER NO CIRCUMSTANCES
 WILL AN INSPECTOR BE INTERVIEWED FOR WORK WITHOUT FIRST
 MEETING THE ABOVE CRITERIA.
  
 5. ADDRESSED
  
 6. ADDRESSED
  
 7. ADDRESSED
  
 8. ADDRESSED
  
 9. ADDRESSED
  
 10. ADDRESSED
  
 11. PERIMETER FENCING UNDER A SEPARATE PERMIT. PLEASE
 PROVIDE COMPLIANCE WITH: FBC-B 3306.5 BARRIERS.
 BARRIERS SHALL BE A MINIMUM OF 8 FEET (2438 MM) IN
 HEIGHT AND SHALL BE PLACED ON THE SIDE OF THE WALKWAY
 NEAREST THE CONSTRUCTION. BARRIERS SHALL EXTEND THE
 ENTIRE LENGTH OF THE CONSTRUCTION SITE.
  
 12. ALL CONSTRUCTION TRAILERS (MOBILE OR MODULAR
 BUILDINGS) THAT ARE GOING TO HAVE MEETING IN THEM WILL
 BE REQUIRED TO GET A PERMIT, 102.2( E ) MOBILE OR
 MODULAR STRUCTURES USED AS TEMPORARY OFFICES, EXCEPT
 THAT THE PROVISIONS OF PART V (SECTION 553.501-553.513,
 FLORIDA STATUTES) RELATING TO ACCESSIBILITY BY PERSONS
 WITH DISABILITIES, AND PERMITS SHALL BE REQUIRED FOR
 STRUCTURAL SUPPORT AND TIE DOWN, ELECTRICAL SUPPLY, AND
 ALL UTILITY CONNECTIONS TO SUCH MOBILE OR MODULAR
 STRUCTURES.
  
 13. ADDRESSED
  
 14. ADDRESSED.
  
 15. ADDRESSED
  
 16. NOT ADDRESSED AT THIS TIME.
 BEFORE A PERMIT TO CONSTRUCT, MAY BE ISSUED, IMPACT
 FEES MUST BE PAID TO PALM BEACH COUNTY. THE ACTUAL
 PERMIT SET OF PLANS MUST BE STAMPED BY THAT OFFICE, AND
 A COPY OF THE PAID RECEIPT ATTACHED TO THE PERMIT
 APPLICATION. PLEASE CALL (561)233-5025 FOR MORE
 INFORMATION.
  
 17. ADDRESSED
  
  
 WHEN RESUBMITTING, PLEASE COMPLETE A RESUBMITTAL FORM:
  
 HTTP://WPB.ORG/DEVELOPMENT/WP-CONTENT/UPLOADS/SITES/33/
 2013/09/APPLICATION_RESUBMITTAL_FORM_04132010.PDF
  
 THIS FORM IS ALSO AVAILABLE AT THE BUILDING DIVISION.
 WHEN RESUBMITTING, SWAP OUT SHEETS WHICH HAVE CHANGED
 SO THAT THERE ARE TWO COMPLETE, COLLATED SETS OF PLANS
 READY FOR PERMIT ISSUANCE. OLD SHEETS ARE TO BE
 RETAINED IN THE PERMIT APPLICATION PACKAGE (SEPARATE
 FROM THE PERMIT SETS) AND MARKED *OLD SHEETS* OR
 *VOID*. PLEASE KEEP BOTH SETS OF OLD VOIDED SHEETS IN
 THE PERMIT PACKAGE.
 A RESPONSE LETTER INDICATING HOW EACH ITEM WAS
 ADDRESSED WILL HELP TO EXPEDITE PLAN REVIEW.
  
  
 DEVELOPMENT SERVICES HOME PAGE
 HTTP://WWW.CITYOFWPB.COM/CONSTRUCTION/INDEX.PHP

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status F Date 2017-11-07 Cont ID  
Sent By shill Date 2017-11-07 Time 15:41 Rev Time 0.00
Received By aclange Date 2017-11-07 Time 09:40 Sent To  
Notes
2017-11-07 15:43:30****PLAN REVIEW COMMENTS****
 PERMIT APPLICATION 17090200
 ART LANGE BUILDING PLANS EXAMINER
 561-805-6667 [email protected]
  
 FBC FLORIDA BUILDING CODE 2014 5TH EDITION/ FRC FLORIDA
 RESIDENTIAL CODE 2015 5TH EDITION
  
 1ST REVIEW
 DATE: NOVEMBER 7, 2017
 ACTION: DENIED
  
 1. NOTICE ONLY; THE CITY OF WEST PALM BEACH ART IN
 PUBLIC PLACES ORDINANCE REQUIREMENT THAT APPLIES TO ANY
 REMODEL OR NEW CONSTRUCTION PROJECT FOR WHICH THE
 PERMIT APPLICATION WAS SUBMITTED AFTER 7/1/14, AND THE
 TOTAL PROJECT CONSTRUCTION COSTS ARE EQUAL TO OR
 GREATER THAN $500,000. PER CITY OF WEST PALM BEACH
 ORDINANCE NO. 4504-14, AND CITY OF WEST PALM BEACH CODE
 OF ORDINANCES, ARTICLE V, ART IN PUBLIC PLACES, SECTION
 78-123(A) AND SECTION 78-126(A), THE ART ASSESSMENT IS
 1% OF THE TOTAL PROJECT CONSTRUCTION COST.
 PER CITY OF WEST PALM BEACH CODE OF ORDINANCES, ARTICLE
 V, ART IN PUBLIC PLACES, SECTION 78-122, RENOVATION AND
 NEW CONSTRUCTION PROJECTS ARE ASSESSED CUMULATIVELY, SO
 THE ART ASSESSMENT WILL BE APPLICABLE TO ALL FUTURE
 PROJECTS.
  
 2. FLOOD ZONE CERTIFICATES
 FBC BUILDING 1612 AND CITY OF WPB CODE OF ORDINANCES
 SECTION 94-546. STRUCTURE IS LOCATED IN AN "A" FLOOD
 ZONE. A FLOOD ELEVATION CERTIFICATE WILL BE REQUIRED.
  
 DURING THE PERMITTING OF THIS STRUCTURE THERE WILL BE
 REQUIRED (3) DIFFERENT FLOOD ZONE CERTIFICATES
 REQUIRED:
  
 (1) A FLOOD ZONE CERTIFICATE IS REQUIRED AS PART OF THE
 PLAN REVIEW DOCUMENTS WITH THE PROPOSED FINISH FLOOR
 HEIGHT.
  
 (2) ONCE THE FIRST FLOOR SLAB IS POURED THE 2ND
 ELEVATION CERTIFICATE IS REQUIRED
  
 (3) BEFORE THE ISSUANCE OF A CERTIFICATE OF OCCUPANCY
 OR A CERTIFICATE OF COMPLETION THE 3RD FLOOD ZONE
 CERTIFICATE IS REQUIRED WITH THE HEIGHT OF ALL EXTERIOR
 ATTENDANTS A/C PADS OR OTHER SLABS FOR GENERATORS.
  
 3. SUPPORTING DOCUMENTS SUBMITTED FROM ARDAMAN @
 ASSOCIATED SHALL BE REVIEWED BY THE ARCHITECT OF RECORD
 AND STAMPED AS REVIEWED AND APPROVED.
  
 FL 61G1-23.015 (2) THE ARCHITECT IS RESPONSIBLE FOR
 SUPERVISING AND REVIEWING ALL PROJECT DATA, REPORTS,
 SHOP DRAWINGS ETC...
  
 4. THIS BUILDING QUALIFIES AS A THRESHOLD BUILDING.
 ?THRESHOLD BUILDING" MEANING ANY BUILDING WHICH IS
 GREATER THAN (3) STORIES OR 50 FT. IN HEIGHT, OR WHICH
 HAS AN ASSEMBLY OCCUPANCY CLASSIFICATION AS DENIED IN
 THE FLORIDA BUILDING CODE WHICH EXCEEDS 5,000 SQ. FT.
 IN AREA AND AN OCCUPANT CONTENT OF GREATER THAN 500
 PERSONS.
  
 4A. THRESHOLD INSPECTION PLAN FL S. S. 553.71(7). 2010
 WEST PALM BEACH AMENDMENTS TO THE FLORIDA BUILDING
 CODE, CHAPTER 1, ADMINISTRATION 109.3.6.1 THE ENFORCING
 AGENCY SHALL REQUIRE A (WRITTEN/ TYPED) SPECIAL
 INSPECTOR TO PERFORM STRUCTURAL INSPECTIONS ON A
 THRESHOLD BUILDING PURSUANT TO A STRUCTURAL INSPECTION
 PLAN PREPARED BY THE ENGINEER OF RECORD. THE STRUCTURAL
 INSPECTION PLAN MUST BE SUBMITTED TO THE ENFORCING
 AGENCY PRIOR TO THE ISSUANCE OF A BUILDING PERMIT FOR
 THE CONSTRUCTION OF A THRESHOLD BUILDING. THE PURPOSE
 OF THE STRUCTURAL INSPECTION PLAN IS TO PROVIDE
 SPECIFIC INSPECTION PROCEDURES AND SCHEDULES SO THAT
 THE BUILDING CAN BE ADEQUATELY INSPECTED FOR COMPLIANCE
 WITH THE PERMITTED DOCUMENTS.
  
 4B. THRESHOLD INSPECTOR: WPB AMENDMENT 109.3.6.2 W.P.B.
 CONSTRUCTION SERVICES DEPARTMENT REQUESTS FOR THRESHOLD
 BUILDINGS A SPECIAL INSPECTOR AS REQUIRED BY FL S S
 553.79(5) FLORIDA STATUTES TO THE MINIMUM INSPECTIONS
 REQUIRED BY THIS CODE. THE THRESHOLD INSPECTION FORMS
 ARE REQUIRED TO BE FILED OUT BY ALL PARTIES WITH
 INTEREST, NOTARIZED AND RETURNED TO THIS OFFICE, AND
 REVIEWED AND APPROVED BEFORE PERMIT ISSUANCE WILL TAKE
 PLACE.
  
 4C. FOR THE SPECIAL INSPECTOR PLEASE PROVIDE A RESUME'
 OF INSPECTION EXPERIENCE ON PREVIOUS PROJECT. THE
 RESUME' MUST BE ACCOMPANIED BY ALL CERTIFICATES AS
 SPECIFIED HEREIN. THE BUILDING OFFICIAL OR HIS DESIGNEE
 WILL REVIEW THE RESUME'. AFTER THE RESUME' IS REVIEWED,
 AN INTERVIEW WILL BE SCHEDULED. UNDER NO CIRCUMSTANCES
 WILL AN INSPECTOR BE INTERVIEWED FOR WORK WITHOUT FIRST
 MEETING THE ABOVE CRITERIA.
  
 5. PLEASE SHOW HOW SLOPE LIMITS WILL BE ACHIEVED. 2014
 FBC 3304.1.1 SLOPE LIMITS. SLOPES FOR PERMANENT FILL
 SHALL NOT BE STEEPER THAN ONE UNIT VERTICAL IN TWO
 UNITS HORIZONTAL (50-PERCENT SLOPE). CUT SLOPES FOR
 PERMANENT EXCAVATIONS SHALL NOT BE STEEPER THAN ONE
 UNIT VERTICAL IN TWO UNITS HORIZONTAL (50-PERCENT
 SLOPE). DEVIATION FROM THE FOREGOING LIMITATIONS FOR
 CUT SLOPES SHALL BE PERMITTED ONLY UPON THE
 PRESENTATION OF A SOIL INVESTIGATION REPORT ACCEPTABLE
 TO THE BUILDING OFFICIAL.
  
 6. WHEN EXCAVATING WILL THE EXCESS SOILS BE STORED ON
 SITE? 2014 FBC 3304.1.2 SURCHARGE. NO FILL OR OTHER
 SURCHARGE LOADS SHALL BE PLACED ADJACENT TO ANY
 BUILDING OR STRUCTURE UNLESS SUCH BUILDING OR STRUCTURE
 IS CAPABLE OF WITHSTANDING THE ADDITIONAL LOADS CAUSED
 BY THE FILL OR SURCHARGE. EXISTING FOOTINGS OR
 FOUNDATIONS WHICH CAN BE AFFECTED BY ANY EXCAVATION
 SHALL BE UNDERPINNED ADEQUATELY OR OTHERWISE PROTECTED
 AGAINST SETTLEMENT AND SHALL BE PROTECTED AGAINST LATER
 MOVEMENT.
  
 7. PLEASE PROVIDE COMPLIANCE WITH: POLLUTION PREVENTION
 PLAN. 2010 FBC-B 3307.1 PROTECTION REQUIRED. ADJOINING
 PUBLIC AND PRIVATE PROPERTY SHALL BE PROTECTED FROM
 DAMAGE DURING CONSTRUCTION, REMODELING AND DEMOLITION
 WORK. PROVISIONS SHALL BE MADE TO CONTROL WATER RUNOFF
 AND EROSION DURING CONSTRUCTION OR DEMOLITION
 ACTIVITIES. THE PERSON MAKING OR CAUSING AN EXCAVATION
 TO BE MADE SHALL PROVIDE WRITTEN NOTICE TO THE OWNERS
 OF ADJOINING BUILDINGS ADVISING THEM THAT THE
 EXCAVATION IS TO BE MADE AND THAT THE ADJOINING
 BUILDINGS SHOULD BE PROTECTED. SAID NOTIFICATION SHALL
 BE DELIVERED NOT LESS THAN 10 DAYS PRIOR TO THE
 SCHEDULED STARTING DATE OF THE EXCAVATION.
 109.3.10 IMPACT OF CONSTRUCTION. ALL CONSTRUCTION
 ACTIVITY REGULATED BY THIS CODE SHALL BE PERFORMED IN A
 MANNER SO AS NOT TO ADVERSELY IMPACT THE CONDITION OF
 ADJACENT PROPERTY, UNLESS SUCH ACTIVITY IS PERMITTED TO
 AFFECT SAID PROPERTY PURSUANT TO CONSENT BY THE
 APPLICABLE PROPERTY OWNER, UNDER TERMS & CONDITIONS
 AGREEABLE TO THE APPLICABLE PROPERTY OWNER. THIS
 INCLUDES BUT IS NOT LIMITED TO THE CONTROL OF DUST,
 NOISE, WATER OR DRAINAGE RUN-OFF, DEBRIS, AND THE
 STORAGE OF CONSTRUCTION MATERIALS. NEW CONSTRUCTION
 ACTIVITY SHALL NOT ADVERSELY IMPACT HISTORIC SURFACE
 WATER DRAINAGE FLOWS SERVING ADJACENT PROPERTIES, & MAY
 REQUIRE SPECIAL DRAINAGE DESIGN COMPLYING WITH
 ENGINEERING STANDARDS TO PRESERVE THE POSITIVE PATTERNS
 OF THE AFFECTED SITES. ACCORDINGLY, DEVELOPERS,
 CONTRACTORS, AND OWNERS OF ALL NEW RESIDENTIAL
 DEVELOPMENT, INCLUDING ADDITIONS, POOLS, PATIOS,
 DRIVEWAYS, DECKS, OR SIMILAR ITEMS, ON EXISTING
 PROPERTIES RESULTING IN A DECREASE IN EXCESS OF 800SQ.
 FT. OF PERMEABLE LAND AREA ON ANY PARCEL SHALL AS A
 PERMIT CONDITION, PROVIDE A PROFESSIONALLY PREPARED
 DRAINAGE PLAN CLEARLY INDICATING COMPLIANCE WITH THIS
 PARAGRAPH. UPON COMPLETION OF THE IMPROVEMENT, A
 CERTIFICATION FROM A LICENSED ENGINEER SHALL BE
 SUBMITTED TO THE INSPECTOR IN ORDER TO RECEIVE APPROVAL
 OF THE FINAL INSPECTION.
  
 8. PLEASE PROVIDE COMPLIANCE WITH: 2010 FBC 3303.5
 WATER ACCUMULATION. PROVISION SHALL BE MADE TO PREVENT
 THE ACCUMULATION OF WATER OR DAMAGE TO ANY FOUNDATIONS
 ON THE PREMISES OR THE ADJOINING PROPERTY.
  
 9. FBC 3306.9 ADJACENT TO EXCAVATIONS. EVERY EXCAVATION
 ON A SITE LOCATED 5 FEET (1524 MM) OR LESS FROM THE
 STREET LOT LINE SHALL BE ENCLOSED WITH A BARRIER NOT
 LESS THAN 6 FEET (1829 MM) HIGH. WHERE LOCATED MORE
 THAN 5 FEET (1524 MM) FROM THE STREET LOT LINE, A
 BARRIER SHALL BE ERECTED WHEN REQUIRED BY THE BUILDING
 OFFICIAL. BARRIERS SHALL BE OF ADEQUATE STRENGTH TO
 RESIST WIND PRESSURE AS SPECIFIED IN CHAPTER 16.
  
 10. PERIMETER FENCING UNDER A SEPARATE PERMIT. PLEASE
 PROVIDE COMPLIANCE WITH: FBC-B 3306.5 BARRIERS.
 BARRIERS SHALL BE A MINIMUM OF 8 FEET (2438 MM) IN
 HEIGHT AND SHALL BE PLACED ON THE SIDE OF THE WALKWAY
 NEAREST THE CONSTRUCTION. BARRIERS SHALL EXTEND THE
 ENTIRE LENGTH OF THE CONSTRUCTION SITE.
  
 11. ALL CONSTRUCTION TRAILERS (MOBILE OR MODULAR
 BUILDINGS) THAT ARE GOING TO HAVE MEETING IN THEM WILL
 BE REQUIRED TO GET A PERMIT, 102.2( E ) MOBILE OR
 MODULAR STRUCTURES USED AS TEMPORARY OFFICES, EXCEPT
 THAT THE PROVISIONS OF PART V (SECTION 553.501-553.513,
 FLORIDA STATUTES) RELATING TO ACCESSIBILITY BY PERSONS
 WITH DISABILITIES, AND PERMITS SHALL BE REQUIRED FOR
 STRUCTURAL SUPPORT AND TIE DOWN, ELECTRICAL SUPPLY, AND
 ALL UTILITY CONNECTIONS TO SUCH MOBILE OR MODULAR
 STRUCTURES.
  
 12. TO DATE THERE HAS BEEN NO PERMIT APPLIED FOR, FOR
 TEST PILING INCOMPLIANCE WITH THE 2014 FBC-B
 1810.3.3.1.2 LOAD TEST.
  
 13. TO DATE WE HAVE NO COMPANY SIGNED ON TO OVERSEE THE
 AUGER CAST PILE OR TEST PILE. FBC-B 1803.4 QUALIFIED
 REPRESENTATIVE. 2010 FLORIDA BUILDING CODE W * 2010
 WEST PALM BEACH AMENDMENTS TO THE FLORIDA BUILDING
 CODE, CHAPTER 1, ADMINISTRATION SECTION 117 TESTS. THE
 BUILDING OFFICIAL MAY REQUIRE TESTS OR TEST REPORTS AS
 PROOF OF COMPLIANCE. REQUIRED TESTS ARE TO BE MADE AT
 THE EXPENSE OF THE OWNER, OR AGENT, BY AN APPROVED
 TESTING LABORATORY OR OTHER APPROVED AGENCY.
  
 13A. SHOW HOW THE RECOMMENDATIONS FROM THE SUBSURFACE
 EXPLORATION AND GEOTECHNICAL ENGINEERING EVALUATION
 RECOMMENDATIONS WILL BE MET. FOR EXAMPLE 8.1.2 WILL
 SHEET PILE BE USED ON THE WEST EDGE OF THE HELEN WILKES
 SITE OR ALONG OLIVE AVE AND 2ND STREET. WILL
 COMPRESSION/ TENSION PILES BE USED TO SUPPORT THE
 SUPERSTRUCTURE? SHOW DETAILS ON PLANS HOW THIS WILL BE
 ACHIEVED.
  
 14. BEFORE A PERMIT TO CONSTRUCT, MAY BE ISSUED, IMPACT
 FEES MUST BE PAID TO PALM BEACH COUNTY. THE ACTUAL
 PERMIT SET OF PLANS MUST BE STAMPED BY THAT OFFICE, AND
 A COPY OF THE PAID RECEIPT ATTACHED TO THE PERMIT
 APPLICATION. PLEASE CALL (561) 233-5025 FOR MORE
 INFORMATION.
  
 15. FBC 105.13 PHASED PERMIT APPROVAL. AFTER SUBMITTAL
 OF THE APPROPRIATE CONSTRUCTION DOCUMENTS, THE BUILDING
 OFFICIAL IS AUTHORIZED TO ISSUE A PERMIT FOR THE
 CONSTRUCTION OF FOUNDATIONS OR ANY OTHER PART OF A
 BUILDING OR STRUCTURE BEFORE THE CONSTRUCTION DOCUMENTS
 FOR THE WHOLE BUILDING OR STRUCTURE HAVE BEEN
 SUBMITTED. THE HOLDER OF SUCH PERMIT FOR THE FOUNDATION
 OR OTHER PARTS OF A BUILDING OR STRUCTURE SHALL PROCEED
 AT THE HOLDER?S OWN RISK WITH THE BUILDING OPERATION
 AND WITHOUT ASSURANCE THAT A PERMIT FOR THE ENTIRE
 STRUCTURE WILL BE GRANTED. CORRECTIONS MAY BE REQUIRED
 TO MEET THE REQUIREMENTS OF THE TECHNICAL CODES. THIS
 PROVISION IS ONLY FOR THE FLORIDA BUILDING CODE, ALL
 OTHER AGENCY APPROVALS NECESSARY FOR CONSTRUCTION MUST
 BE SECURED PRIOR TO THIS PROVISION BEING APPLIED.
  
 16. SHOW HOW BUILDING SEPARATION WILL COMPLY WITH
 BUILDINGS ON THE SAME LOT FBC 705.3. ALSO INCLUDE HOW
 UNEXPOSED SURFACE TEMPERATURE WILL BE CONSIDERED FBC
 705.7 AND FIGURE 705.7 FOR EQUIVALENT OPENING FACTOR.
  
 17. PERMIT APPLICATION APPLIED AS OWNER BUILDER. THIS
 IS NOT ALLOWED PER FL ST. 489, A CONTRACTOR IS REQUIRED
 PRIOR TO ISSUING OF PERMIT. NO PLAN REVIEW FEES HAVE
 BEEN PAID. FBC 109.
  
 WHEN RESUBMITTING, PLEASE COMPLETE A RESUBMITTAL FORM:
 HTTP://WPB.ORG/DEVELOPMENT/WP-CONTENT/UPLOADS/SITES/33/
 2013/09/APPLICATION_RESUBMITTAL_FORM_04132010.PDF
 THIS FORM IS ALSO AVAILABLE AT THE BUILDING DIVISION.
 WHEN RESUBMITTING, SWAP OUT SHEETS WHICH HAVE CHANGED
 SO THAT THERE ARE TWO COMPLETE, COLLATED SETS OF PLANS
 READY FOR PERMIT ISSUANCE. OLD SHEETS ARE TO BE
 RETAINED IN THE PERMIT APPLICATION PACKAGE (SEPARATE
 FROM THE PERMIT SETS) AND MARKED *OLD SHEETS* OR
 *VOID*. PLEASE KEEP BOTH SETS OF OLD VOIDED SHEETS IN
 THE PERMIT PACKAGE.
 A RESPONSE LETTER INDICATING HOW EACH ITEM WAS
 ADDRESSED WILL HELP TO EXPEDITE PLAN REVIEW.
 DEVELOPMENT SERVICES HOME PAGE
 HTTP://WWW.CITYOFWPB.COM/CONSTRUCTION/INDEX.PHP
  
  
  
  
  

Review Stop E ELECTRICAL
Rev No 2 Status P Date 2018-02-21 Cont ID  
Sent By jpearson Date 2018-02-21 Time 12:34 Rev Time 0.00
Received By jpearson Date 2018-02-12 Time 12:34 Sent To  
Notes
2018-02-21 12:35:47RISER PROVIDED, CHANGED RESULT TO PASS.
2018-02-12 12:34:10CODES IN EFFECT:
 FBC = FLORIDA BUILDING CODE 2014 5TH EDITION
 FBC CE = FLORIDA BUILDING CODE ENERGY CONSERVATION 2014
 5TH EDITION
 FBC RE = FLORIDA RESIDENTIAL CODE 2014 5TH EDITION,
 PART VIII ELECTRICAL
 NEC = NFPA 70 2011 EDITION, NATIONAL ELECTRICAL CODE
 FS = FLORIDA STATUTES
  
 ELECTRICAL REVIEW STATUS: DENIED, SEE COMMENTS BELOW.
  
 PREVIOUS COMMENTS THAT HAVE NOT BEEN ADDRESSED
 SATISFACTORILY HAVE ADDITIONAL COMMENTS IN PARENTHESES.
  
 THIS REVIEW FOR FOUNDATION PERMIT ONLY.
 1. PROVIDE RISER DIAGRAM, SHOWING ALL DETAILS OF
 SERVICE EQUIPMENT, WIRE AND BREAKER SIZES FOR SERVICE.
 SHOW GEC SIZE AND SYSTEM, SHOW INTERSYSTEM BONDING
 TERMINATION POINT. INCLUDE DETAIL OF THE SECOND
 RELIABLE POWER SOURCE FOR THE FIRE PUMP REQUIRED. NEC
 215.5, 230, 250.50, 250.94, 408.30, 695.3; FBC 107.2.1
 (YOUR RESPONSE TO THIS COMMENT STATES THAT I SHOULD SEE
 THE MAIN BUILDING PERMIT PLANS. AT THE TIME THIS REVIEW
 WAS COMPLETED, 9/25/17, THE MAIN BUILDING PLANS HAD NOT
 BEEN REVIEWED. THEY WERE NOT COMPLETED UNTIL 12/6/17.
 THEREFORE, MUCH OF THIS INFORMATION WAS NOT KNOWN.
 REGARDLESS, FOR A FOUNDATION PERMIT, THE RISER DIAGRAM
 SHEETS ARE REQUIRED AS A MATTER OF PUBLIC RECORD.
 SUBMIT ANY SHEETS THAT SHOW THE RISER DIAGRAM WITH
 DETAILS OF UNDERGROUND FEEDS AND GROUNDING FOR THE
 FOUNDATION.)
  
 END OF COMMENTS.
  
 PLEASE NOTE: SUBMITTAL OF ADDITIONAL AND/OR REVISED
 MATERIALS MAY RESULT IN NEW PLAN REVIEW COMMENTS. WHEN
 RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE
 LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY
 RESUBMITTAL FORM. ADDITIONALLY, INSERT CORRECTED PAGES
 INTO THE ORIGINAL SUBMITTAL AND REMOVE OR VOID THE
 PREVIOUSLY REVIEWED SHEETS.
  
 SINCERELY,
  
 JOHN PEARSON
 ELECTRICAL PLANS EXAMINER
 561-805-6746
 [email protected]
  

Review Stop E ELECTRICAL
Rev No 1 Status F Date 2017-09-25 Cont ID  
Sent By jpearson Date 2017-09-25 Time 11:18 Rev Time 0.00
Received By jpearson Date 2017-09-25 Time 11:17 Sent To  
Notes
2017-09-25 11:20:02CODES IN EFFECT:
 FBC = FLORIDA BUILDING CODE 2014 5TH EDITION
 FBC CE = FLORIDA BUILDING CODE ENERGY CONSERVATION 2014
 5TH EDITION
 FBC RE = FLORIDA RESIDENTIAL CODE 2014 5TH EDITION,
 PART VIII ELECTRICAL
 NEC = NFPA 70 2011 EDITION, NATIONAL ELECTRICAL CODE
 FS = FLORIDA STATUTES
  
 ELECTRICAL REVIEW STATUS: DENIED, SEE COMMENTS BELOW.
  
 THIS REVIEW FOR FOUNDATION PERMIT ONLY.
 1. PROVIDE RISER DIAGRAM, SHOWING ALL DETAILS OF
 SERVICE EQUIPMENT, WIRE AND BREAKER SIZES FOR SERVICE.
 SHOW GEC SIZE AND SYSTEM, SHOW INTERSYSTEM BONDING
 TERMINATION POINT. INCLUDE DETAIL OF THE SECOND
 RELIABLE POWER SOURCE FOR THE FIRE PUMP REQUIRED. NEC
 215.5, 230, 250.50, 250.94, 408.30, 695.3; FBC 107.2.1
  
 PLEASE NOTE: SUBMITTAL OF ADDITIONAL AND/OR REVISED
 MATERIALS MAY RESULT IN NEW PLAN REVIEW COMMENTS. WHEN
 RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE
 LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY
 RESUBMITTAL FORM. ADDITIONALLY, INSERT CORRECTED PAGES
 INTO THE ORIGINAL SUBMITTAL AND REMOVE OR VOID THE
 PREVIOUSLY REVIEWED SHEETS.
  
 SINCERELY,
  
 JOHN PEARSON
 ELECTRICAL PLANS EXAMINER
 561-805-6746
 [email protected]
  

Review Stop ENG ENGINEERING CSD
Rev No 2 Status P Date 2018-02-23 Cont ID  
Sent By squinone Date 2018-02-23 Time   Rev Time 0.00
Received By squinone Date 2018-02-23 Time   Sent To  
Notes
2018-02-23 15:14:141. AN ENGINEERING DEVELOPMENT APPROVAL APPLICATION WILL
 BE REQUIRED FROM THE ENGINEERING SERVICES DEPARTMENT.
 THE ENGINEERING DEVELOPMENT APPROVAL APPLICATION FORMS
 CAN BE DOWNLOADED FROM THE FOLLOWING WEBSITE LINK: HTTP
 ://WPB.ORG/DEPARTMENTS/ENGINEERING-PUBLIC-WORKS/FORMS,-
 PERMITS-APPLICATIONS
  
 2. PLEASE SUBMIT THE LATEST VERSION OF THE 'AUTO-CALC
 CERTIFIED COST ESTIMATE FORM' FOR SUBMISSION TO CITY OF
 WEST PALM BEACH PUBLIC WORKS DEPARTMENT FOR ADDITIONAL
 WORK PROPOSED. THIS FORM CAN BE DOWNLOADED FROM THE
 FOLLOWING LINK: HTTP://WPB.ORG/DEPARTMENTS/ENGINEERING-
 PUBLIC-WORKS/FORMS,-PERMITS-APPLICATIONS
  
 SOFIA QUINONES-BENEJAM, EI
 PROJECT ENGINEER
 CITY OF WEST PALM BEACH
 401 CLEMATIS STREET, 4TH FLOOR
 WEST PALM BEACH, FL 33402
 (MAILING ADDRESS: PO BOX 3366)
 P: 561.494.1108
 C: 561.459.6518
 F: 561.494.1116
 EMAIL: [email protected]
  
  

Review Stop ENG ENGINEERING CSD
Rev No 1 Status F Date 2017-11-08 Cont ID  
Sent By shill Date 2017-11-08 Time 07:29 Rev Time 0.00
Received By shill Date 2017-11-08 Time 07:29 Sent To  
Notes
2017-11-08 07:30:34CONTACT ENGINEERING DEPARTMENT DIRECTLY AND SUBMIT
 APPLICATION IF REQUIRED
 HTTP://WWW.WPB.ORG/DEPARTMENTS/ENGINEERING-PUBLIC-WORKS
 /FORMS,-PERMITS-APPLICATIONS
  
 ENGINEERING APPROVAL REQUIRED PRIOR TO PERMIT ISSUANCE
  
 MAIN PHONE: (561) 822-1200
  

Review Stop FIRE FIRE DEPARTMENT
Rev No 2 Status P Date 2018-01-31 Cont ID  
Sent By pleduc Date 2018-01-31 Time   Rev Time 0.00
Received By pleduc Date 2018-01-31 Time 09:18 Sent To  
Notes
***NONE***

Review Stop FIRE FIRE DEPARTMENT
Rev No 1 Status P Date 2017-09-20 Cont ID  
Sent By wjolin Date 2017-09-20 Time 09:27 Rev Time 0.00
Received By wjolin Date 2017-09-20 Time 09:22 Sent To  
Notes
2017-09-20 09:23:03290 NORTH OLIVE AVENUE - APARTMENTS & PARKING GARAGE
 PERMIT #17090200
 REVIEW COMMENTS - FIRE DEPARTMENT
 **APARTMENT/GARAGE FOUNDATION ONLY**
  
 FIRE PROTECTION BACKFLOW PREVENTERS: PER NFPA 24
 SECTION 6.2.1, ALL CONNECTIONS TO PRIVATE FIRE SERVICE
 MAINS FOR FIRE PROTECTION SYSTEMS SHALL BE ARRANGED IN
 ACCORDANCE WITH ONE OF THE FOLLOWING SO THAT THEY CAN
 BE ISOLATED:
 (1)A POST INDICATOR VALVE INSTALLED NOT LESS THAN 40
 FEET FROM THE BUILDING.
 (A) FOR BUILDINGS LESS THAN 40 FEET IN HEIGHT, A POST
 INDICATOR VALVE SHALL BE PERMITTED TO BE INSTALLED
 CLOSER THAN 40 FEET BUT AT LEAST AS FAR FROM THE
 BUILDING AS THE HEIGHT OF THE WALL FACING THE POST
 INDICATOR VALVE.
 (2) A WALL POST INDICATOR VALVE
 (3) AN INDICATING VALVE IN A PIT, INSTALLED IN
 ACCORDANCE WITH SECTION 6.4
 (4) A BACKFLOW PREVENTER WITH AT LEAST ONE INDICATING
 VALVE NOT LESS THAN 40 FEET FROM THE BUILDING.
 (A) FOR BUILDINGS LESS THAN 40 FEET IN HEIGHT, A
 BACKFLOW PREVENTER WITH AT LEAST ONE INDICATING VALVE
 SHALL BE PERMITTED TO BE INSTALLED CLOSER THAN 40 FEET
 BUT AT LEAST AS FAR FROM THE BUILDING AS THE HEIGHT OF
 THE WALL FACING THE BACKFLOW PREVENTER.
 (5) CONTROL VALVES INSTALLED IN A FIRE-RATED ROOM
 ACCESSIBLE FROM THE EXTERIOR
 (6) CONTROL VALVES IN A FIRE-RATED STAIR ENCLOSURE
 ACCESSIBLE FROM THE EXTERIOR AS PERMITTED BY THE
 AUTHORITY HAVING JURISDICTION
  
 THE CITY OF WEST PALM BEACH REQUIRES CONSTRUCTION
 TRAILERS LARGER THAN A SINGLE "DOUBLE WIDE" (OR TWO
 "SINGLE WIDE") TO EITHER BE PROTECTED BY AN AUTOMATIC
 SPRINKLER SYSTEM OR COMPLY WITH THE SEPARATION
 REQUIREMENTS OF NFPA 241. TEMPORARY CONSTRUCTION
 TRAILERS OR MODULAR BUILDINGS WILL REQUIRE A PERMIT AND
 COMPLIANCE WITH THE FOLLOWING:
 PER NFPA 241- STANDARD FOR SAFEGUARDING CONSTRUCTION,
 ALTERATION, AND DEMOLITION OPERATIONS, SECTION 4.2:
 TEMPORARY OFFICES, TRAILERS, AND OTHER FACILITIES OF
 COMBUSTIBLE CONSTRUCTION OR HOUSING COMBUSTIBLE
 CONTENTS SHALL BE SEPARATED FROM ADJACENT BUILDINGS,
 TRAILERS OR STRUCTURES IN ACCORDANCE WITH TABLE 4.2.1.
 PER TABLE 4.2.1:
 1) 20 FEET EXPOSED LENGTH SHALL BE SEPARATED FROM
 ADJACENT STRUCTURES BY AT LEAST 30 FEET
 2) 30 FEET EXPOSED LENGTH SHALL BE SEPARATED FROM
 ADJACENT STRUCTURES BY AT LEAST 35 FEET
 3) 40 FEET EXPOSED LENGTH SHALL BE SEPARATED FROM
 ADJACENT STRUCTURES BY AT LEAST 40 FEET
 4) 50 FEET EXPOSED LENGTH SHALL BE SEPARATED FROM
 ADJACENT STRUCTURES BY AT LEAST 45 FEET
 5) 60 FEET EXPOSED LENGTH SHALL BE SEPARATED FROM
 ADJACENT STRUCTURES BY AT LEAST 50 FEET
 6) GREATER THAN 60 FEET EXPOSED LENGTH SHALL BE
 SEPARATED FROM ADJACENT STRUCTURES BY AT LEAST 60 FEET
  
 WESLEY JOLIN
 ASSISTANT FIRE MARSHAL
 WEST PALM BEACH FIRE RESCUE
 [email protected]
  

Review Stop I INCOMING/PROCESSING
Rev No 2 Status P Date 2018-02-26 Cont ID  
Sent By shill Date 2018-02-23 Time 08:02 Rev Time 0.00
Received By shill Date 2018-01-29 Time 15:43 Sent To  
Notes
2018-01-30 15:43:44C03

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2017-11-08 Cont ID  
Sent By shill Date 2017-11-08 Time 07:42 Rev Time 0.00
Received By shill Date 2017-09-07 Time 10:25 Sent To  
Notes
2017-09-15 10:25:52C03

Review Stop IMPACT COUNTY IMPACT FEES
Rev No 3 Status N Date 2018-02-26 Cont ID  
Sent By aclange Date 2018-02-26 Time 12:53 Rev Time 0.00
Received By aclange Date 2018-02-26 Time 12:53 Sent To  
Notes
2018-02-26 12:58:27PALM BEACH COUNTY IMPACT FEE DUE BEFORE THE BUILDING
 PERMIT FOR THE ELEVATED BUILDING IS ISSUED.
  

Review Stop IMPACT COUNTY IMPACT FEES
Rev No 2 Status F Date 2018-02-01 Cont ID  
Sent By aclange Date 2018-02-01 Time 09:39 Rev Time 0.00
Received By aclange Date 2018-02-01 Time 09:38 Sent To  
Notes
2018-02-01 09:39:37BEFORE A PERMIT TO CONSTRUCT, MAY BE ISSUED, IMPACT
 FEES MUST BE PAID TO PALM BEACH COUNTY. THE ACTUAL
 PERMIT SET OF PLANS MUST BE STAMPED BY THAT OFFICE, AND
 A COPY OF THE PAID RECEIPT ATTACHED TO THE PERMIT
 APPLICATION. PLEASE CALL (561)233-5025 FOR MORE
 INFORMATION.

Review Stop IMPACT COUNTY IMPACT FEES
Rev No 1 Status F Date 2017-11-07 Cont ID  
Sent By aclange Date 2017-11-07 Time 15:44 Rev Time 0.00
Received By aclange Date 2017-11-07 Time 15:44 Sent To  
Notes
2017-11-07 15:44:55BEFORE A PERMIT TO CONSTRUCT, MAY BE ISSUED, IMPACT
 FEES MUST BE PAID TO PALM BEACH COUNTY. THE ACTUAL
 PERMIT SET OF PLANS MUST BE STAMPED BY THAT OFFICE, AND
 A COPY OF THE PAID RECEIPT ATTACHED TO THE PERMIT
 APPLICATION. PLEASE CALL (561)233-5025 FOR MORE
 INFORMATION.

Review Stop NFIP NFIP REVIEW ACTIVITY
Rev No 4 Status N Date 2019-10-18 Cont ID  
Sent By shill Date 2019-10-18 Time 17:42 Rev Time 0.00
Received By shill Date 2019-10-18 Time 17:42 Sent To  
Notes
2019-10-18 17:44:18ALTHOUGH THIS WAS DESIGNED TO COMPLY WITH THE
 REQUIREMENTS OF THE ADJACENT FLOOD ZONE AND FUTURE
 FLOOD MAPS, THIS STRUCTURE WAS NOT LOCATED IN A SFHA AT
 THE TIME OF PERMITTING.
  
  

Review Stop NFIP NFIP REVIEW ACTIVITY
Rev No 3 Status P Date 2018-02-26 Cont ID  
Sent By aclange Date 2018-02-26 Time 13:22 Rev Time 0.00
Received By aclange Date 2018-02-26 Time 13:22 Sent To  
Notes
2018-02-26 13:23:34PROVISO:
 FLOOD ZONE CERTIFICATES:
 FBC BUILDING 1612 AND CITY OF WPB CODE OF ORDINANCES
 SECTION 94-546. STRUCTURE IS LOCATED IN AN "A" FLOOD
 ZONE. A FLOOD ELEVATION CERTIFICATE WILL BE REQUIRED.
 DURING THE PERMITTING OF THIS STRUCTURE THERE WILL BE
 REQUIRED (3) DIFFERENT FLOOD ZONE CERTIFICATES
 REQUIRED:
 (1) A FLOOD ZONE CERTIFICATE IS REQUIRED AS PART OF THE
 PLAN REVIEW DOCUMENTS WITH THE PROPOSED FINISH FLOOR
 HEIGHT.
 (2) ONCE THE FIRST FLOOR SLAB IS POURED THE 2ND
 ELEVATION CERTIFICATE IS REQUIRED.
 (3) BEFORE THE ISSUANCE OF A CERTIFICATE OF OCCUPANCY
 OR A CERTIFICATE OF COMPLETION THE 3RD FLOOD ZONE
 CERTIFICATE IS REQUIRED WITH THE HEIGHT OF ALL EXTERIOR
 ATTENDANTS A/C PADS OR OTHER SLABS FOR GENERATORS.
  

Review Stop NFIP NFIP REVIEW ACTIVITY
Rev No 2 Status F Date 2018-02-01 Cont ID  
Sent By aclange Date 2018-02-01 Time 09:37 Rev Time 0.00
Received By aclange Date 2018-02-01 Time 09:37 Sent To  
Notes
2018-02-01 09:38:07SEE BUILDING REVIEW.

Review Stop NFIP NFIP REVIEW ACTIVITY
Rev No 1 Status F Date 2017-11-08 Cont ID  
Sent By shill Date 2017-11-08 Time 07:44 Rev Time 0.00
Received By shill Date 2017-11-08 Time 07:44 Sent To  
Notes
2017-11-08 07:44:35SEE BUILDING REVIEW
  
  

Review Stop P PLUMBING
Rev No 2 Status P Date 2018-02-20 Cont ID  
Sent By gjohnson Date 2018-02-20 Time 13:41 Rev Time 0.00
Received By gjohnson Date 2018-02-20 Time 13:41 Sent To  
Notes
2018-02-20 14:01:56PROVISO:
  
 PROVIDE APPROVED BY BUILDING DEPARTMENT BEFORE 1ST
 ROUGH INSPECTION.
  
 1. STORM AND PARKING AREA DRAIN ISOMETRIC.
 2. ROOF DRAIN COLLECTION ISOMETRIC.
 3. PAN AND CONDENSATE COLLECTION ISOMETRIC.
  
  
 GEORGE JOHNSON
 PLUMBING PLANS EXAMINER
 CITY OF WEST PALM BEACH
  561-805-6711
 [email protected]
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  

Review Stop P PLUMBING
Rev No 1 Status F Date 2017-10-18 Cont ID  
Sent By gjohnson Date 2017-10-18 Time 15:02 Rev Time 0.00
Received By gjohnson Date 2017-10-18 Time 09:08 Sent To  
Notes
2017-10-18 15:01:591ST REVIEW: FBC 2014 5TH EDITION
  
 PLUMBING COMMENTS:
  
 1. SHT. PF 1.1.1A+B+C PLEASE LABEL THE GREASE LINES AS
 GREASE NOT SANITARY. PER WPB AMEND TO FBC 107.2.1
  
 2. SHT. PF 1.1.1B NEAR GRID LINE L + 2.5 THERE IS A
 SRORM DRAIN LABELED AS A SANITARY PLEASE CLARIFY.PER
 WPB AMEND TO FBC 107.2.1
  
 3. PROVIDE A SANITARY COLLECTION ISOMETRIC DRAWING
 INCLUDING DFU LOAD. PER WPB AMEND TO FBC
 107.3.5.1.3(13)
  
 4. PROVIDE A STORM DRAIN COLLECTION ISOMETRIC DRAWING
 INCLUDING SQFT THAT IS BEING DRAINED. PER WPB AMEND TO
 FBC 107.3.5.1.3(13)
  
 5. PLEASE PLACE NOTE ON PLAN SEPARATE PERMITS ARE
 REQUIRED FOR DOMESTIC WATER BACKFLOW AND FIRE LINE
 BACKFLOW. PER WPB UTILITIES DEPT.
  
 PLEASE NOTE THAT SUBMITTAL OF ADDITIONAL AND/OR REVISED
 MATERIALS MAY RESULT IN NEW PLAN REVIEW COMMENTS.
 WHEN RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE
 LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY
 RE-SUBMITTAL FORM. PLEASE, ADDITIONALLY, INSERT
 CORRECTED PAGES INTO TO SUBMITTAL AND REMOVE OR VOID
 THE PREVIOUSLY REVIEWED SHEETS.
  
 GEORGE JOHNSON
 PLUMBING PLANS EXAMINER
 CITY OF WEST PALM BEACH
  561-805-6711
 [email protected]
  

Review Stop THRESHOLD THRESHOLD INSPECTOR DOCUMENTS
Rev No 4 Status P Date 2018-03-07 Cont ID  
Sent By aclange Date 2018-03-07 Time 08:18 Rev Time 0.00
Received By aclange Date 2018-03-07 Time 08:18 Sent To  
Notes
2018-03-07 08:23:27RECEIVED ORIGINAL SI AGREEMENTS AND PERMIT APPLICATION.
 EMAILED RANDY AT STILES TO SET UP A PRECONSTRUCTION
 MEETING WITH KEN CONRAD.

Review Stop THRESHOLD THRESHOLD INSPECTOR DOCUMENTS
Rev No 3 Status P Date 2018-02-28 Cont ID  
Sent By shill Date 2018-02-28 Time 16:36 Rev Time 0.00
Received By shill Date 2018-02-28 Time 16:36 Sent To  
Notes
2018-02-28 16:38:45RESUMES FOR THE INSPECTORS ARE REQUIRED PRIOR TO
 COMMENCEMENT
  
  
  

Review Stop THRESHOLD THRESHOLD INSPECTOR DOCUMENTS
Rev No 2 Status F Date 2018-02-01 Cont ID  
Sent By aclange Date 2018-02-01 Time 09:36 Rev Time 0.00
Received By aclange Date 2018-02-01 Time 09:35 Sent To  
Notes
2018-02-01 09:37:29EMAILED THRESHOLD INSPECTION APPLICATION PACKAGE TO TIM
 MOORE CONTRACTOR ON THIS PROJECT 1/31/18 4:23PM

Review Stop THRESHOLD THRESHOLD INSPECTOR DOCUMENTS
Rev No 1 Status F Date 2017-11-08 Cont ID  
Sent By shill Date 2017-11-08 Time 07:44 Rev Time 0.00
Received By shill Date 2017-11-08 Time 07:44 Sent To  
Notes
2017-11-08 07:44:13SEE BUILDING REVIEW
  
  
  

Review Stop Z ZONING
Rev No 2 Status P Date 2018-02-23 Cont ID  
Sent By aaponte Date 2018-02-23 Time 10:05 Rev Time 0.00
Received By aaponte Date 2018-02-23 Time 10:05 Sent To  
Notes
***NONE***

Review Stop Z ZONING
Rev No 1 Status F Date 2017-10-17 Cont ID  
Sent By aaponte Date 2017-10-17 Time 15:28 Rev Time 0.00
Received By aaponte Date 2017-10-17 Time 15:28 Sent To  
Notes
2017-10-17 15:29:15FOR FOUNDATION PERMIT ONLY, PLEASE SUBMIT A SITE PLAN