| 2017-09-19 09:20:54 | 1ST REVIEW FBC-2014 MECHANICAL |
| | PERMIT #17090153 |
| | 9/19/17 |
| | |
| | PLAN REVIEW RESULTS: DENIED. |
| | |
| | 1) PROVIDE A LIFE SAFETY PLAN THAT IDENTIFIES THE |
| | LOCATIONS OF ALL NEW OR EXISTING FIRE-RATED WALLS AND |
| | ASSEMBLIES, AND THE TYPES AND HOURLY RATINGS OF EACH. |
| | IF THE MEN'S BATHROOM/CORRIDOR WALL AND THE MECHANICAL |
| | EQUIPMENT ROOM WALL ARE FIRE/SMOKE BARRIERS THEN THE |
| | DUCTS PENETRATING THEM SHALL BE PROTECTED BY FIRE/SMOKE |
| | DAMPERS THAT ARE LISTED AND LABELED IN ACDCORDANCE WITH |
| | UL 555 AND 555S- SECTION 607.3.1. |
| | |
| | 2) SHEET ST-1: THE PLAN INDICATES THE BUILDING HAS AN |
| | EXISTING SMOKE CONTROL/SMOKE EXHAUST SYSTEM. CLARIFY IF |
| | THERE IS AN EXISTING RATIONAL ANALYSIS REPORT THAT |
| | DETAILS THE DESIGN OF THE SYSTEM, AND THE INSTALLATION |
| | AND ACCEPTANCE TESTING PROCEDURES. THE PROPOSED |
| | ALTERATIONS TO THE SYSTEM MUST BE IN COMPLIANCE WITH |
| | THE ORIGINAL DESIGN OR A NEW RATIONAL ANALYSIS SHALL BE |
| | SUBMITTED. PLEASE NOTE THAT ALL NEW DUCTS AND DAMPERS |
| | THAT ARE PART OF THE SYSTEM SHALL BE IN COMPLIANCE WITH |
| | SECTION 513.10.2. PLEASE ADD DUCT LEAK TESTING TO THE |
| | SMOKE TEST PROCEDURE. |
| | |
| | 3) ST-1: PLEASE ENLARGE THE PRINT IDENTIFYING MOTORIZED |
| | DAMPERS #1 & 2 AND PROVIDE EQUIPMENT SCHEDULES ON THE |
| | PLAN FOR EACH. PLEASE NOTE THAT THESE DAMPERS SHALL BE |
| | LISTED AND LABELED FOR THEIR INTENDED USE IN ACCORDANCE |
| | WITH SECTION 513.10.4. |
| | |
| | 4) ST-1: PROVIDE EQUIPMENT SCHEDULES ON THE PLANS FOR |
| | THE SMOKE EXHAUST AND SUPPLY FANS. THE SMOKE EXHAUST |
| | FAN SHALL BE RATED CERTIFIED BY THE MANUFACTURER FOR |
| | THE PROBABLE TEMPERATURE RISE PER SECTION 513.10.1 AND |
| | AND SHALL BE UL LISTED AND LABELED FOR IT'S INTENDED |
| | USE. |
| | |
| | CHRISTOPHER L. COLE |
| | MECHANICAL PLANS EXAMINER |
| | 401 CLEMATIS STREET |
| | WEST PALM BEACH FL 33401 |
| | 561-805-6719 |
| | [email protected] |
| | |