Plan Review Details - Permit 17070621
Plan Review Stops For Permit 17070621
Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status P Date 2017-11-14 Cont ID  
Sent By shill Date 2017-11-14 Time 14:59 Rev Time 0.00
Received By shill Date 2017-11-14 Time 14:59 Sent To  
Notes
***NONE***

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status P Date 2017-08-02 Cont ID  
Sent By shill Date 2017-08-02 Time 17:37 Rev Time 0.00
Received By shill Date 2017-08-02 Time 17:04 Sent To  
Notes
***NONE***

Review Stop E ELECTRICAL
Rev No 1 Status P Date 2017-08-14 Cont ID  
Sent By jpearson Date 2017-08-14 Time 07:53 Rev Time 0.00
Received By jpearson Date 2017-08-14 Time 07:53 Sent To  
Notes
***NONE***

Review Stop FIRE FIRE DEPARTMENT
Rev No 2 Status P Date 2017-10-20 Cont ID  
Sent By pleduc Date 2017-10-20 Time   Rev Time 0.00
Received By pleduc Date 2017-10-20 Time 10:10 Sent To  
Notes
***NONE***

Review Stop FIRE FIRE DEPARTMENT
Rev No 1 Status F Date 2017-07-21 Cont ID  
Sent By pleduc Date 2017-07-21 Time   Rev Time 0.00
Received By pleduc Date 2017-07-21 Time 12:28 Sent To  
Notes
2017-07-21 14:50:17THIS PLAN WAS REVIEWED AND FAILED BY PETER LEDUC, FIRE
 MARSHAL, WITH THE FOLLOWING COMMENTS:
  
  
  
 1) SHEET A 601 - THE IS A DOOR SCHEDULE INDICATING ONE
 DOOR INVLOVED IN THE PROJECT, DOOR 100, ON THE FIRST
 FLOOR STAIRWELL. THERE IS NOT INDICATIONS ON THE DOOR
 SCHEDULE IF THE DOOR IS REQUIRED TO BE RATED, IS IT
 EXISTING, THE TYPE OF HARDWARE, TYPE OF EXIT DEVICES,
 ETC.
  
 PLEASE REVIEW, CLARIFY OR CORRECT.
  
  
  
 2) SHEET AD 1.01 - DOOR 100 COULD NOT BE LOCATED OR
 IDENTIFIED. THERE ARE NO NOTE CALL-OUTS INDICATING
 REMOVING THIS DOOR,
  
 PLEASE REVIEW, CLARIFY OR CORRECT.
  
  
 3) SHEET A 1.0 - DOOR 100 COULD NOT BE LOCATED OR
 IDENTIFIED.
  
 PLEASE REVIEW, CLARIFY OR CORRECT.
  
  
  
 4) SHEET A 3.01 - THERE ARE NO INDICATIONS OF A
 LIGHWEIGHT TRUSS SIGN.
  
 PER FLORIDA 69A-60.0081; NOTICE SIGNAGE IS REQUIRED FOR
 STRUCTURES WITH LIGHT-FRAME TRUSS-TYPE CONSTRUCTION.
 ANY COMMERCIAL, INDUSTRIAL, OR ANY MULTIUNIT
 RESIDENTIAL STRUCTURE OF THREE UNITS OR MORE WHICH USES
 HORIZONTAL OR VERTICAL LIGHT-FRAME TRUSS-TYPE
 CONSTRUCTION IN ANY PORTION SHALL BE MARKED WITH A
 MALTESE CROSS SIGN MEASURING 8 INCHES HORIZONTALLY AND
 8 INCHES VERTICALLY, OF A BRIGHT RED REFLECTIVE COLOR.
 THE APPROVED SYMBOL SHALL BE PLACED WITHIN 24 INCHES TO
 THE LEFT OF THE MAIN ENTRY DOOR.
 1. STRUCTURES WITH LIGHT-FRAME TRUSS ROOFS SHALL BE
 MARKED WITH THE LETTER "R".
 2. STRUCTURES WITH LIGHT-FRAME TRUSS FLOOR SYSTEMS
 SHALL BE MARKED WITH THE LETTER "F".
 3. STRUCTURES WITH LIGHT-FRAME TRUSS FLOOR AND ROOF
 SYSTEMS SHALL BE MARKED WITH THE LETTERS "R/F".
  
  
 PLEASE PROVIDE AS APPLICABLE PER THE ROOF AND FLOOR
 DESIGN.
  
  
  
 5) WHEN RESUBMITTING, PLEASE PROVIDE PLAN SHEET
 REVISION CLOUDS OR NUMBERED NARRATIVE RESPONSES TO THE
 ABOVE.
  
  
  
 6) ADDITIONAL COMMENTS MAY BE PROVIDED ON THE
 RE-SUBMITTAL OF THE ABOVE.
  
  
 PETER LEDUC
 FIRE MARSHAL
 561-804-4709
 [email protected]
  
  

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2017-11-15 Cont ID  
Sent By cpuell Date 2017-11-15 Time 16:34 Rev Time 0.00
Received By cpuell Date 2017-10-17 Time 15:57 Sent To  
Notes
2017-11-15 16:29:21TO LAURA MERCHANT.
2017-10-18 15:57:18C14

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2017-08-25 Cont ID  
Sent By cpuell Date 2017-08-25 Time 16:41 Rev Time 0.00
Received By cpuell Date 2017-07-17 Time 11:13 Sent To  
Notes
2017-08-24 13:53:38TO C PUELL FOR PROCESSING.
2017-07-19 11:14:12C09

Review Stop M MECHANICAL (A/C)
Rev No 2 Status P Date 2017-11-07 Cont ID  
Sent By ccole Date 2017-11-07 Time 16:29 Rev Time 0.00
Received By ccole Date 2017-11-07 Time 15:58 Sent To  
Notes
***NONE***

Review Stop M MECHANICAL (A/C)
Rev No 1 Status F Date 2017-08-16 Cont ID  
Sent By ccole Date 2017-08-15 Time 16:29 Rev Time 0.00
Received By ccole Date 2017-08-15 Time 16:25 Sent To  
Notes
2017-08-15 16:54:291ST REVIEW FBC-2014 MECHANICAL , WPB AMENDMENTS TO THE
 FBC
 PERMIT #17070621
 8/15/17
  
 PLAN REVIEW RESULTS: DENIED.
  
 1) THE DRAWING INDEX ON SHEET M-1 INDICATES HVAC PLANS
 FOR THE 1ST, 2ND, AND 3RD FLOORS, HOWEVER THE 1ST FLOOR
 IS NOT INCLUDED ON SHEET M-2.
  
 2) M-2: SHOW THE LOCATION OF THE 5-TON AIR HANDLER FOR
 AC 2-2 ON THE FLOOR PLAN.
  
 3) M-1: INCLUDE AC 3-2 AND MS-2 IN THE EQUIPMENT
 SCHEDULE ON M-1.
  
 4) M-2: PROVIDE RETURN AIR FROM THE 2ND FLOOR OFFICES
 #1-6- SECTION 601.5.
  
 5) M-2: PLEASE EXPLAIN THE REASON WHY THE THREE
 DIFFUSERS IN SPACE 203 ARE BEING CAPPED. HOW WILL AIR
 BE SUPPLIED TO THE NORTH SECTION OF THE SPACE?
  
 6) M-2: THE 2ND FLOOR PLAN APPEARS TO BE CUT OFF-
 PLEASE PROVIDE THE ENTIRE LAYOUT PLAN,
  
 CHRISTOPHER L. COLE
 MECHANICAL PLANS EXAMINER
 401 CLEMATIS STREET
 WEST PALM BEACH FL 33401
 561-805-6719
 [email protected]
  

Review Stop R ROOF PLAN REVIEW
Rev No 1 Status   Date   Cont ID  
Sent By   Date   Time   Rev Time 0.00
Received By skennedy Date 2018-07-10 Time 16:14 Sent To  
Notes
2018-07-10 16:14:22SEE 18070043

Review Stop Z ZONING
Rev No 2 Status P Date 2017-11-15 Cont ID  
Sent By aaponte Date 2017-11-15 Time 15:23 Rev Time 0.00
Received By aaponte Date 2017-11-15 Time 15:23 Sent To  
Notes
2017-11-15 16:21:50PROVISO: 1. A SEPARATE TREE REMOVAL AND LANDSCAPE
 PERMIT SHALL BE SUBMITTED.
 2. LIGHTING PLAN SHALL BE SUBMITTED TO CONFIRM
 COMPLIANCE WITH THE MINIMUM 0.6 FOOTCANDLE REQUIRED ONE
 FOOT ABOVE THE SIDEWALK AT THE BACK OF THE CURB.
  

Review Stop Z ZONING
Rev No 1 Status P Date 2017-08-24 Cont ID  
Sent By aaponte Date 2017-08-24 Time 13:52 Rev Time 0.00
Received By aaponte Date 2017-08-24 Time 13:52 Sent To  
Notes
2017-08-24 13:53:10PROVISO: A SEPARATE PERMIT SHALL BE SUBMITTED FOR TREE
 REMOVAL AND LANDSCAPE.