Plan Review Details - Permit 17030196
Plan Review Stops For Permit 17030196
Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status P Date 2017-05-05 Cont ID  
Sent By rmcdouga Date 2017-05-05 Time 19:00 Rev Time 0.00
Received By rmcdouga Date 2017-05-05 Time 19:00 Sent To  
Notes
2017-05-05 19:02:35REMODEL PERMIT #17041218 HAS BEEN APPLIED FOR.

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status F Date 2017-03-17 Cont ID  
Sent By rmcdouga Date 2017-03-17 Time 17:21 Rev Time 0.00
Received By rmcdouga Date 2017-03-17 Time 17:18 Sent To  
Notes
2017-03-17 17:21:32PLAN
 REVIEW COMMENTS
  
 1ST REVIEW: FBC FIFTH EDITION (2014)
 ROBERT MCDOUGAL, CBO
 COMMERCIAL COMBINATION PLANS EXAMINER
 (561) 805-6714
 [email protected]
  
 DENIED BY BUILDING
 PLEASE ADDRESS THE ITEMS NOTED BELOW:
  
 1) AN INTERIOR DEMOLISION PERMIT FOR A SINGLE FAMILY
 RESIDENCE WILL NOT BE ISSUED UNTIL THE REMODEL PERMIT
 HAS BEEN SUBMITTED.

Review Stop E ELECTRICAL
Rev No 2 Status P Date 2017-05-04 Cont ID  
Sent By vperez Date 2017-05-04 Time 10:36 Rev Time 0.00
Received By vperez Date 2017-05-04 Time 10:36 Sent To  
Notes
***NONE***

Review Stop E ELECTRICAL
Rev No 1 Status P Date 2017-03-13 Cont ID  
Sent By vperez Date 2017-03-13 Time 10:34 Rev Time 0.00
Received By vperez Date 2017-03-13 Time 10:34 Sent To  
Notes
2017-03-13 10:34:56DEMO ONLY
  
 NEW ELECTRICAL TO BE SUBMITTED REFLECTING NEW INSTALLS
  
 V. PEREZ
 *6717

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2017-05-05 Cont ID  
Sent By rmcdouga Date 2017-05-05 Time 19:00 Rev Time 0.00
Received By rmcdouga Date 2017-04-26 Time 09:51 Sent To  
Notes
2017-04-28 09:51:30R07

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2017-03-17 Cont ID  
Sent By rmcdouga Date 2017-03-17 Time 17:28 Rev Time 0.00
Received By rmcdouga Date 2017-03-06 Time 11:21 Sent To  
Notes
2017-03-08 11:22:07R07

Review Stop M MECHANICAL (A/C)
Rev No 2 Status P Date 2017-05-05 Cont ID  
Sent By rmcdouga Date 2017-05-05 Time 18:55 Rev Time 0.00
Received By rmcdouga Date 2017-05-05 Time 18:55 Sent To  
Notes
2017-05-05 18:56:11DEMOLITION AND REMOVAL OF MECHANICAL EQUIPMENT ONLY. A
 SEPARATE PERMIT, APPLICATION AND REVIEW IS REQUIRED FOR
 ANY ADDITION MECHANICAL WORK.

Review Stop M MECHANICAL (A/C)
Rev No 1 Status P Date 2017-03-17 Cont ID  
Sent By rmcdouga Date 2017-03-17 Time 17:25 Rev Time 0.00
Received By rmcdouga Date 2017-03-17 Time 17:25 Sent To  
Notes
2017-03-17 17:28:06DEMOLITION AND REMOVAL OF MECHANICAL EQUIPMENT ONLY. A
 SEPARATE PERMIT, APPLICATION AND REVIEW IS REQUIRED FOR
 ANY ADDITION MECHANICAL WORK.

Review Stop P PLUMBING
Rev No 2 Status P Date 2017-05-02 Cont ID  
Sent By gjohnson Date 2017-05-02 Time 18:21 Rev Time 0.00
Received By gjohnson Date 2017-05-02 Time 15:43 Sent To  
Notes
***NONE***

Review Stop P PLUMBING
Rev No 1 Status F Date 2017-03-09 Cont ID  
Sent By gjohnson Date 2017-03-09 Time 15:24 Rev Time 0.00
Received By gjohnson Date 2017-03-09 Time 15:24 Sent To  
Notes
2017-03-09 15:48:231ST REVIEW
  
 GEORGE JOHNSON
 PLUMBING PLANS EXAMINER LL
 CITY OF WEST PALM BEACH
 DEVELOPMENT SERVICES
 BUILDING DIVISION
 561-805-6711
 [email protected]
  
 PLUMBING COMMENTS:
  
 1. THE NOTE ON THE PLUMBING SEE PLUMBING RISER NO RISER
 WAS PROVIDED REMOVE NOTE OR PROVIDE RISER. PER WPB
 AMENT TO
  
 DUE TO THE DEFICIENCIES OF THIS PLAN A COMPLETE AND
 THOROUGH REVIEW CANNOT BE DONE AT THIS TIME. UPON
 RESUBMITTAL THERE MAYBE ADDITIONAL COMMENTS.
  
 WHEN RESUBMITTING PLANS, REMOVE AND REPLACE ANY PAGES
 AS NECESSARY. A NARRATIVE LISTING THE ORIGINAL REVIEW
 COMMENT NUMBER WITH A DESCRIPTION OF THE CHANGES MADE
 AND IDENTIFYING THE SHEET OR SPECIFICATION PAGE WHERE
 THE CHANGE CAN BE FOUND WILL HELP EXPEDITE THE REVIEW.
  