| Plan Review Stops For Permit 17030122 |
| Review Stop |
FIRE |
FIRE DEPARTMENT |
| Rev No |
1 |
Status |
P |
Date |
2017-03-07 |
|
|
Cont ID |
|
| Sent By |
pleduc |
Date |
2017-03-07 |
Time |
|
Rev Time |
0.00 |
| Received By |
pleduc |
Date |
2017-03-07 |
Time |
09:53 |
Sent To |
E |
|
| Notes |
| 2017-03-07 11:36:29 | THIS PLAN WAS REVIEWED AND APPROVED BY PETER LEDUC, | | | FIRE MARSHAL, WITH THE FOLLOWING COMMENTS: | | | | | | PLEASE CONSIDER THE FOLLOWING AS PROVISO: | | | | | | THESE PROVISO COMMENTS WILL BE VERIFIED AND CONFIRMED | | | AT THE TIME OF FIRE INSPECTION. FAILURE TO FOLLOW THESE | | | PROVISO COMMENTS WILL RESULT IN A FAILED FIRE | | | INSPECTION. | | | | | | | | | 1) TEST AT WORKING PRESSURE FOR 2 HRS PER NFPA 13. | | | | | | | | | 2) ENSURE A PRESSURE GAUGE IS INSTALLED. | | | | | | 3) IF A FIRE PUMP IS EXISTING, CALCULATE TEST PRESSURE | | | AS WORKING PRESSURE. | | | | | | | | | | | | PETER LEDUC | | | FIRE MARSHAL | | | 561-804-4709 | | | [email protected] | | | |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
1 |
Status |
N |
Date |
2017-03-14 |
|
|
Cont ID |
|
| Sent By |
ccole |
Date |
2017-03-14 |
Time |
07:43 |
Rev Time |
0.00 |
| Received By |
ccole |
Date |
2017-03-02 |
Time |
12:53 |
Sent To |
|
|
| Notes |
| 2017-03-03 12:53:59 | ROUTED TO FIRE INBOX |
|
|
| Review Stop |
M |
MECHANICAL (A/C) |
| Rev No |
1 |
Status |
P |
Date |
2017-03-14 |
|
|
Cont ID |
|
| Sent By |
ccole |
Date |
2017-03-14 |
Time |
07:43 |
Rev Time |
0.00 |
| Received By |
ccole |
Date |
2017-03-14 |
Time |
07:43 |
Sent To |
|
|
| Notes |
|
|
|