| 2017-02-28 07:13:42 | 1) SUBMIT A SITE PLAN SHOWING THE LOCATION OF BOTH |
| | GENERATORS IN RELATION TO OPERABLE WINDOWS, DOORS AND |
| | ANY OTHER OPENINGS INTO THE STRUCTURE. WPB AMEND. TTO |
| | FBC SEC. 107.2.1. |
| | 2) SHOW THE DISTANCES FROM THE GENERATOR EXHAUST TO ALL |
| | OPERABLE WINDOWS AND DOORS AND ANY OTHER OPENINGS INTO |
| | THE STRUCTURE. COMPLY WITH NFPA 58 & NFPA 37. WPB |
| | AMEND. TTO FBC SEC. 107.2.1. |
| | 3) SHOW THE LOCATION OF THE EXISTING LP TANK ON THE |
| | SITE PLAN. WPB AMEND. TTO FBC SEC. 107.2.1. |
| | 4) THE PLANS REFERENCE TWO PE SIZING TABLES IN THE FUEL |
| | GAS CODE BUT YOU HAVE ALSO SUBMITTED A SIZING TABLE |
| | FROM THE MANUFACTURER. CLARIFY. |
| | 5) THE PLANS SHOW THE UNDERGROUND LP PIPING AS EXISTING |
| | BUT YOU HAVE SUBMITTED MANUFACTURER'S SPECIFICATIONS |
| | FOR PE PIPING. CLEARLY INDICATE ON THE PLANS IF ANY NEW |
| | PE PIPING IS BEING INSTALLED AND LIST THE TOTAL |
| | DEVELOPED LENGTH AND PSI OF THE SYTEM ON THE NEW PE |
| | PIPE. WPB AMEND. TTO FBC SEC. 107.2.1.THE PLANS NOTE |
| | THIS AS A DISCONNECT/RECONNECT.CLARIFY. |
| | 6) THE PLANS SHOW ONE OF THE GENERATORS WITH A BTU LOAD |
| | OF 340,000. THERE ARE TWO GENERATORS BEING INSTALLED SO |
| | THE BTU LOAD SHOULD BE 680,000 BUT THE TOTAL LOAD SHOWN |
| | ON THE PLAN IS 340,000. CLARIFY. THE PIPING SHALL BE |
| | SIZED FOR THE TOTAL BTU LOAD ON THE SYSTEM.AS SHOWN, |
| | THE SYSTM IS UNDERSIZED. |
| | 7) SHOW THE DEVELOPED LENGTH OF THE SCH. 40 METALLIC |
| | PIPE FROM THE STEP- DOWN REGULATOR TO EACH GENERATOR. |
| | 8) THE GAS SIZING TABLES THAT ARE REFERENCED ON THE |
| | PLAN FROM THE 2014 FBC-FUEL GAS CODE ARE FOR NATURAL |
| | GAS AND THIS IS AN LP GAS SYSTEM. REFERENCE THE CORRECT |
| | APPLICABLE SIZING TABLES ON THE PLANS. INCLUDE THE |
| | REFERENCE TO THE CORRECT TABLE FOR THE METALLIC PIPE. |
| | WPB AMEND. TTO FBC SEC. 107.2.1. |
| | 9) CLARIFY THE PIPE RUN OF 30 FEET SHOWN ON THE |
| | PLANS.IS THIS FOR THE EXISTING UNDERGROUND? INDICATE |
| | THE PSI OF THE EXISTING SYSTEM FROM THE LP TANK TO THE |
| | REGULATOR. WPB AMEND. TTO FBC SEC. 107.2.1. |
| | |
| | TIM LARGE |
| | CHIEF PLUMBING INSPECTOR |
| | PLUMBING PLAN REVIEW |
| | 561-805-6692 |
| | [email protected] |
| | |
| | |
| | |
| | |