Plan Review Details - Permit 17010896
Plan Review Stops For Permit 17010896
Review Stop G GAS REVIEW
Rev No 2 Status P Date 2017-02-13 Cont ID  
Sent By tklarge Date 2017-02-13 Time 06:35 Rev Time 0.00
Received By tklarge Date 2017-02-13 Time 06:21 Sent To  
Notes
***NONE***

Review Stop G GAS REVIEW
Rev No 1 Status F Date 2017-01-27 Cont ID  
Sent By tklarge Date 2017-01-27 Time 06:01 Rev Time 0.00
Received By tklarge Date 2017-01-27 Time 05:45 Sent To  
Notes
2017-01-27 06:01:471) PROPER DOCUMENTS HAVE NOT BEEN SUBMITTED TO REVIEW
 AND ISSUE A GAS PERMIT. SUBMIT THE FOLLOWING
 INFORMATION FOR THE GAS PERMIT:
 2) SUBMIT AN ISOMETRIC DRAWING THAT CLEARLY SHOWS THE
 LENGTH OF ALL CUT SECTIONS OF PIPE PER 2014 FBC-FUEL
 GAS, SECS. 402.4.1, 402.4.2. OR 2014 FBC-RES SEC.
 G2413.
 3) SHOW THE TYPE OF PIPE MATERIAL BEING INSTALLED, ALL
 PIPE SIZES, AND THE CORRESPONDING EHD NUMBER OF THE
 CORRUGATED STAINLESS STEEL TUBING ( IF APPLICABLE) FOR
 EACH PIPE SIZE. WPB AMENDMENTS TO FBC SEC.107.2.1.
 4) TYPE OF GAS (LP OR NATURAL).
 5) BTU LOAD OF EACH APPLIANCE AND THE TOTAL BTU LOAD ON
 THE SYSTEM. REFER TO THE 2014 FBC-FUEL GAS SECS.401.8
 THRU 402.6.1 AND TABLES 402.4 (1) THRU 402.4 (37) OR
 2014 FBC-RES. SEC. G2413.
 6) SHOW THE DISTANCE FROM THE POINT OF DELIVERY, (GAS
 METER / MP REGULATOR / LP TANK) TO THE MOST REMOTE
 OUTLET IN THE BUILDING AND / OR SYSTEM PER THE 2014
 FBC-FUEL GAS SEC.402.4.1 OR 2014 FBC-RES. SEC. G
 2413.3.
 7) INDICATE THE DELIVERY PRESSURE (PSI) OF THE SYSTEM
 ON THE PLAN PER 2014 FBC-FUEL GAS SEC.402.2 OR FBC RES.
 SEC. G2413.2. .
 8) SUBMIT A DETAIL SHOWING THE TYPE, LOCATION, SIZE AND
 TERMINATION OF THE GAS VENTS PER 2014 FBC-FUEL GAS
 SECS. 502 THRU 505 OR 2014 FBC-RES. SEC.G2426.
 9) SUBMIT MANUFACTURER?S SPECIFICATION SHEETS /
 INSTALLATION MANUAL FOR ALL GAS EQUIPMENT TO VERIFY
 COMPLIANCE WITH STANDARDS NFPA 54, NFPA 58, AND
 FBC-2014 FUEL GAS CODE SEC. 402.2, AND 301.3 OR 2014
 FBC-RES. SEC. G2404.3. GAS APPLIANCES SHALL BE LISTED
 AND LABELED. THE INSTALLATION MANUALS FOR ALL GAS
 APPLIANCES / EQUIPMENT SHALL BE ONSITE AT THE TIME OF
 INSPECTION. FGC SEC.305.1, FBC-RES. SEC.G2408.1.
 10) SUBMIT TWO COPIES OF THE SIZING TABLES USED IN THE
 DESIGN FOR THIS GAS SYSTEM OR PLACE A NOTE ON BOTH SETS
 OF PLANS LISTING THE SIZING TABLES FROM THE GAS CODE OR
 OTHER STANDARD THAT WERE USED IN THE DESIGN OF THIS
 SYSTEM. FGC SEC.402.3, FBCR SEC. G 2413.3.
 11.) INDICATE ON THE PLAN IF THE POOL HEATER IS THE
 ONLY GAS APPLIANCE ON THIS SYSTEM. IF NOT, SUBMIT A
 COMPLETE GAS RISER SHOWING ALL PIPE SIZES, TYPE OF
 PIPE, THE DEVELOPED LENGTH TO THE FURTHEST GAS OUTLET,
 THE BTU LOAD OF EACH APPLIANCE, THE PSI OF THE SYSTEM,
 THE TYPE OF GAS AND THE TOTAL BTU LOAD ON THE SYSTEM.
 THESE REQUIREMENTS ALSO APPLY TO A NEW GAS SYSTEM.
  
 TIM LARGE
 CHIEF PLUMBING INSPECTOR
 PLUMBING PLAN REVIEW
 561-805-6692
 [email protected]
  

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2017-02-13 Cont ID  
Sent By tklarge Date 2017-02-13 Time 06:35 Rev Time 0.00
Received By tklarge Date 2017-02-09 Time 12:03 Sent To  
Notes
2017-02-10 12:03:31RESUB ROUTED TO TKLARGE

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2017-01-27 Cont ID  
Sent By tklarge Date 2017-01-27 Time 06:02 Rev Time 0.00
Received By tklarge Date 2017-01-25 Time 11:30 Sent To  
Notes
2017-01-26 11:30:20PLUMB <5K