Plan Review Details - Permit 16111013
Plan Review Stops For Permit 16111013
Review Stop ENG ENGINEERING CSD
Rev No 1 Status N Date 2016-12-05 Cont ID  
Sent By ccole Date 2016-12-05 Time 13:58 Rev Time 0.00
Received By ccole Date 2016-12-05 Time 13:58 Sent To  
Notes
***NONE***

Review Stop FIRE FIRE DEPARTMENT
Rev No 2 Status P Date 2016-12-13 Cont ID  
Sent By pleduc Date 2016-12-13 Time   Rev Time 0.00
Received By pleduc Date 2016-12-13 Time 15:14 Sent To M
Notes
***NONE***

Review Stop FIRE FIRE DEPARTMENT
Rev No 1 Status P Date 2016-11-23 Cont ID  
Sent By pleduc Date 2016-11-28 Time   Rev Time 0.00
Received By pleduc Date 2016-11-23 Time 16:57 Sent To M
Notes
2016-11-23 17:24:36THIS PLAN WAS REVIEWED AND APPROVED BY PETER LEDUC,
 FIRE MARSHAL, WITH THE FOLLOWING COMMENTS:
  
 PLEASE CONSIDER THE FOLLOWING AS PROVISO:
  
  
 THESE PROVISO COMMENTS WILL BE VERIFIED AND CONFIRMED
 AT THE TIME OF FIRE INSPECTION. FAILURE TO FOLLOW THESE
 PROVISO COMMENTS WILL RESULT IN A FAILED FIRE
 INSPECTION.
  
  
 1) PROVIDE AN ISOLATION VALVE TO DUST COLLECTOR SYSTEM
 AND TEST AT 200PSI.
  
 THE PROPOSED PROJECT IS ADDING ALL NEW PIPING AND
 HEADS, IT DOES NOT INVOLVE RELOCATED HEADS AND, IT CAN
 BE ISOLATED.
  
 24.2.1.4 MODIFICATIONS AFFECTING 20 OR FEWER SPRINKLERS
 SHALL NOT REQUIRE TESTING IN EXCESS OF SYSTEM WORKING
 PRESSURE.
 24.2.1.6 MODIFICATIONS THAT CANNOT BE ISOLATED, SUCH AS
 RELOCATED DROPS, SHALL NOT REQUIRE TESTING IN EXCESS OF
 SYSTEM WORKING PRESSURE.
  
 ADDITIONALLY, THIS IS A HIGHER THAN NORMAL HAZARD
 PROTECTION SYSTEM WHERE SYSTEM INTEGRITY IS ESSENTIAL.
  
  
 2) ADDITIONALLY, AN ISOLATION VALVE WILL ALSO FUNCTION
 IN THE CASE OF COLLECTOR SPRINKLER ACTIVATION AND SHUT
 DOWN WHILE MAINTAINING PORTECTION THROUGHOUT THE
 BUILDING.
  
  
 PETER LEDUC
 FIRE MARSHAL
 561-804-4709
 [email protected]
  
  
  
  
  

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2016-12-19 Cont ID  
Sent By ccole Date 2016-12-19 Time 07:17 Rev Time 0.00
Received By ccole Date 2016-12-08 Time 10:58 Sent To  
Notes
2016-12-09 10:58:18RESUB ROUTED TO FIRE INBOX

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2016-12-05 Cont ID  
Sent By ccole Date 2016-12-05 Time 13:58 Rev Time 0.00
Received By ccole Date 2016-12-05 Time 13:58 Sent To  
Notes
2016-11-23 07:44:15ROUTED TO FIRE INBOX

Review Stop M MECHANICAL (A/C)
Rev No 2 Status P Date 2016-12-19 Cont ID  
Sent By ccole Date 2016-12-19 Time 07:17 Rev Time 0.00
Received By ccole Date 2016-12-19 Time 07:17 Sent To  
Notes
***NONE***

Review Stop M MECHANICAL (A/C)
Rev No 1 Status F Date 2016-12-05 Cont ID  
Sent By ccole Date 2016-12-05 Time 12:57 Rev Time 0.00
Received By ccole Date 2016-12-05 Time 12:57 Sent To  
Notes
2016-12-05 13:55:191ST REVIEW FBC-2014 MECHANICAL
 PERMIT #16111013
 12/5/16
  
 1) CORRECT THE NOTE INDICATING ALL ABOVEGROUND PIPE
 2-1/2- 8" IS EXISTING. THE PLAN SHOWS NEW PIPING TO BE
 INSTALLED.
  
 2) INDICATE HOW THE NEW 2-1/2 AND 1" SPRINKLER PIPING
 WILL BE SUPPORTED AT THE BUILDING AND AT THE DUST
 COLLECTOR. THE CUT AND PASTE DETAIL OF THE BAR JOIST
 HANGER IS NOT APPLICABLE.
  
 3) ALL INFORMATION, DRAWINGS, SPECIFICATIONS AND
 ACCOMPANYING DATA SHALL BEAR THE NAME AND SIGNATURE OF
 THE PERSON RESPONSIBLE FOR THE DESIGN- SECTION 107.2.1
 WPB AMENDMENTS TO THE FBC. (SEE ALSO SECTION 107.3.5).
  
 CHRISTOPHER L. COLE
 MECHANICAL PLANS EXAMINER
 561-805-6719
 [email protected]
  