Plan Review Details - Permit 16110189
Plan Review Stops For Permit 16110189
Review Stop ENG ENGINEERING CSD
Rev No 1 Status P Date 2017-02-28 Cont ID  
Sent By mgonzale Date 2017-02-28 Time 12:48 Rev Time 0.50
Received By mgonzale Date 2017-02-28 Time 12:48 Sent To I
Notes
2017-02-28 12:49:29PROJECT HAS EXISTING WATER AND SEWER AVAILABLE.
 MGONZALEZ
 [email protected]
 (561)4941085

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2016-11-14 Cont ID  
Sent By mgonzale Date 2017-02-28 Time 12:49 Rev Time 0.00
Received By tklarge Date 2016-11-04 Time 13:39 Sent To  
Notes
2016-11-08 13:39:37ROUTED TO PLUMB PER SAK

Review Stop P PLUMBING
Rev No 3 Status N Date 2017-03-01 Cont ID  
Sent By tklarge Date 2017-03-01 Time 05:03 Rev Time 0.00
Received By tklarge Date 2017-03-01 Time 05:03 Sent To  
Notes
***NONE***

Review Stop P PLUMBING
Rev No 2 Status F Date 2017-03-01 Cont ID  
Sent By tklarge Date 2017-03-01 Time 05:03 Rev Time 0.00
Received By tklarge Date 2017-03-01 Time 04:40 Sent To  
Notes
2017-03-01 04:41:341) A GENERAL CONTRACTOR CAN INSTALL THE WET TAP TO THE
 WATER MAIN & THE SEWER LATERAL BUT CANNOT INSTALL THE
 CONTINUATION OF EITHER OF THESE LINES TO THE BUILDING
 PER FL. STATUTE 489.113 (3)(D). A LICENSED PLUMBING
 CONTRACTOR SHALL DO THE CONTINUATION OF THE WATER AND
 SEWER LINES.SEE BELOW. 2ND REQUEST.
 (D) A GENERAL CONTRACTOR SHALL NOT BE REQUIRED TO
 SUBCONTRACT THE CONSTRUCTION OF A MAIN SANITARY SEWER
 COLLECTION SYSTEM, STORM COLLECTION SYSTEM, OR WATER
 DISTRIBUTION SYSTEM, NOT INCLUDING THE CONTINUATION OF
 UTILITY LINES FROM THE MAINS TO THE BUILDINGS, AND MAY
 PERFORM ANY OF THE SERVICES, ON PUBLIC OR PRIVATE
 PROPERTY, FOR WHICH A LICENSE AS AN UNDERGROUND UTILITY
 AND EXCAVATION CONTRACTOR IS REQUIRED UNDER THIS PART.
 2) A SEPARATE NOTICE OF COMMENCEMENT IS REQUIRED FOR
 THIS WORK. THE NOC THAT WAS SUBMITTED IS FOR REPAIRS TO
 A STORAGE BUILDING. THIS WORK WAS NOT SHOWN ON THE
 ORIGINAL PLANS.FL. STATUTE 713.13. 2ND REQUEST
 3) INDICATE SIZE OF THE WATER SERVICE AND THE SEWER
 LINE ON THE PLANS. 2ND REQUEST.
  
 TIM LARGE
 CHIEF PLUMBING INSPECTOR
 PLUMBING PLAN REVIEW
 561-805-6692
 [email protected]
  
  

Review Stop P PLUMBING
Rev No 1 Status F Date 2016-11-14 Cont ID  
Sent By tklarge Date 2016-11-14 Time 05:39 Rev Time 0.00
Received By tklarge Date 2016-11-14 Time 05:11 Sent To  
Notes
2016-11-10 14:20:131) A GENERAL CONTRACTOR CAN INSTALL THE WET TAP TO THE
 WATER MAIN & THE SEWER LATERAL BUT CANNOT INSTALL THE
 CONTINUATION OF EITHER OF THESE LINES TO THE BUILDING
 PER FL. STATUTE 489.113 (3)(D). A LICENSED PLUMBING
 CONTRACTOR SHALL DO THE CONTINUATION OF THE WATER AND
 SEWER LINES.SEE BELOW.
 (D) A GENERAL CONTRACTOR SHALL NOT BE REQUIRED TO
 SUBCONTRACT THE CONSTRUCTION OF A MAIN SANITARY SEWER
 COLLECTION SYSTEM, STORM COLLECTION SYSTEM, OR WATER
 DISTRIBUTION SYSTEM, NOT INCLUDING THE CONTINUATION OF
 UTILITY LINES FROM THE MAINS TO THE BUILDINGS, AND MAY
 PERFORM ANY OF THE SERVICES, ON PUBLIC OR PRIVATE
 PROPERTY, FOR WHICH A LICENSE AS AN UNDERGROUND UTILITY
 AND EXCAVATION CONTRACTOR IS REQUIRED UNDER THIS PART.
 2) A SEPARATE NOTICE OF COMMENCEMENT IS REQUIRED FOR
 THIS WORK. THE NOC THAT WAS SUBMITTED IS FOR REPAIRS TO
 A STORAGE BUILDING. THIS WORK WAS NOT SHOWN ON THE
 ORIGINAL PLANS.FL. STATUTE 713.13.
 3) INDICATE SIZE OF THE WATER SERVICE AND THE SEWER
 LINE ON THE PLANS.
  
 TIM LARGE
 CHIEF PLUMBING INSPECTOR
 PLUMBING PLAN REVIEW
 561-805-6692
 [email protected]
  
  