| | 1. SUBMIT AN ISOMETRIC DRAWING THAT CLEARLY SHOWS THE |
| | LENGTH OF ALL CUT SECTIONS OF PIPE PER 2014 FBC-FUEL |
| | GAS, SECS. 402.4.1, 402.4.2. OR 2014 FBC-RES SEC. |
| | G2413. |
| | 2) SUBMIT CALCULATIONS FOR COMBUSTION AIR FOR THE |
| | DRYER, TANKLESS WATER HEATERS, STOVE AND FIREPLACE PER |
| | THE 2014 FBC-FUEL GAS CODE SEC.304.1 OR 2014 FBC-RES. |
| | SEC. G 2407. |
| | 3) SUBMIT MANUFACTURER'S SPECIFICATION SHEETS / |
| | INSTALLATION MANUAL FOR ALL GAS EQUIPMENT TO VERIFY |
| | COMPLIANCE WITH STANDARDS NFPA 54, NFPA 58, AND |
| | FBC-2014 FUEL GAS CODE SEC. 402.2, AND 301.3 OR 2014 |
| | FBC-RES. SEC. G2404.3. GAS APPLIANCES SHALL BE LISTED |
| | AND LABELED. THE INSTALLATION MANUALS FOR ALL GAS |
| | APPLIANCES / EQUIPMENT SHALL BE ONSITE AT THE TIME OF |
| | INSPECTION. FGC SEC.305.1, FBC-RES. SEC.G2408.1. |
| | 4) SUBMIT TWO COPIES OF A HOUSE PLAN SHOWING THE |
| | LOCATION OF THE TANKLESS WATER HEATER AND THE LOCATION |
| | OF ANY OPERABLE DOORS OR WINDOWS. THE LOCATION OF THE |
| | WATER HEATER SHALL COMPLY WITH THE MANUFACTURER'S |
| | INSTALLATION INSTRUCTIONS. |
| | 5) SUBMIT COPIES OF THE SIZING TABLES BEING USED TO |
| | DESIGN THE SYSTEM OR REFERENCE THE SPECIFIC TABLES ON |
| | THE PLANS. A REVIEW COULD NOT BE DONE ON THE PIPNG |
| | SYSTEM DUE TO THE LACK OF THIS INFORMATION. |
| | 6) SHOW THE MEASUREMENT (LENGTH) OF THE PIPING FROM THE |
| | SECOND STAGE REGULATOR TO THE APPLIANCE.2014 FGC SEC. |
| | 402.4.1. |
| | 7) SUBMIT MANUF. SPECIFICATIONS FOR THE SECOND STAGE |
| | REGULATORS. HOW WILL THEY BE VENTED? |
| | 8) SUPPLY THE CORRESPONDING EHD FOR EACH SIZE THE |
| | WARDFLEX PIPE.FBC SEC. 107.2.1. |
| | 9) THE FUTURE OUTLET FOR THE FIREPLACE SHALL BE VALVED |
| | AND CAPPED. |
| | |
| | TIM LARGE |
| | CHIEF PLUMBING INSPECTOR |
| | PLUMBING PLAN REVIEW |
| | 561-805-6692 |