Plan Review Details - Permit 16061295
Plan Review Stops For Permit 16061295
Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2016-07-14 Cont ID  
Sent By ccole Date 2016-07-14 Time 07:28 Rev Time 0.00
Received By ccole Date 2016-07-13 Time 13:24 Sent To  
Notes
2016-07-13 13:24:17RESUB OF REVISION ROUTED TO CCOLE

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2016-06-23 Cont ID  
Sent By ccole Date 2016-06-23 Time 11:11 Rev Time 0.00
Received By ccole Date 2016-06-22 Time 09:02 Sent To M
Notes
***NONE***

Review Stop M MECHANICAL (A/C)
Rev No 2 Status P Date 2016-07-14 Cont ID  
Sent By ccole Date 2016-07-14 Time 07:28 Rev Time 0.00
Received By ccole Date 2016-07-14 Time 07:28 Sent To  
Notes
***NONE***

Review Stop M MECHANICAL (A/C)
Rev No 1 Status F Date 2016-06-23 Cont ID  
Sent By ccole Date 2016-06-23 Time 11:12 Rev Time 0.00
Received By ccole Date 2016-06-23 Time 11:12 Sent To  
Notes
2016-06-23 11:21:281ST REVIEW: FBC 2014 MECHANICAL
 REVISION #16061295
 MASTER #16040429
 6/23/16
  
 1) I HAVE COPIED AND PASTED BY PROVISO FOR THE MAIN
 PERMIT APPROVAL BELOW- PLEASE READ. THE SUBMITTED
 REVISION HAS A NOTE REFERENCING STRUCTURAL DRAWINGS FOR
 ANCHORING THE CURB TO THE STRUCTURE- PLEASE PROVIDE THE
 DRAWINGS AND THE WIND LOAD DESIGN CRITERIA FOR THE
 PROJECT.
  
 MECHANICAL PROVISO
 PERMIT #16040429
 6/3/16
  
 1) A REVISION IS REQUIRED FOR COMPLETE ENGINEERED TIE
 DOWN DETAILS FOR ANCHORING THE RTU AND CURB TO THE ROOF
 STRUCTURE.
  
 CHRISTOPHER L. COLE
 MECHANICAL PLANS EXAMINER
 561-805-6719
 [email protected]
  
  