Plan Review Details - Permit 16061051
Plan Review Stops For Permit 16061051
Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status P Date 2016-09-09 Cont ID  
Sent By shill Date 2016-09-09 Time 08:04 Rev Time 0.00
Received By shill Date 2016-09-09 Time 08:04 Sent To  
Notes
2016-09-16 16:19:311 HOUR FLOORS REQUIRED PER ARCHITECT FBC TABLE 601
  

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status F Date 2016-07-13 Cont ID  
Sent By shill Date 2016-07-15 Time 17:58 Rev Time 0.00
Received By shill Date 2016-07-14 Time 14:21 Sent To  
Notes
2016-07-13 17:58:59****CORRECTIONS****
  
 SAMANTHA HILL
 BUILDING PLANS EXAMINER
 [email protected]
 561-805-6724
  
 1. SHEET A020, LEVEL 4, STATES THAT THE EXIT CAPACITY
 IS 330 OCCUPANTS, BUT THE STAIR WIDTH (48.75IN) HAS A
 CAPACITY OF 162 EACH; REVISE EXIT CAPACITY TO 324 OR
 CONTACT ME TO DISCUSS, FBC1003.6, 1005.
  
 2. SHEET A020, LEVEL 4, PROPOSED OCCUPANT LOAD OF 359
 OCCUPANTS EXCEEDS THE CAPACITY OF 324, FBC 1003.6.
  
 3. SHEET A020, LEVEL 4, OCCUPANT LOADS WERE ROUNDED
 DOWN IN TWO CASES, BUT, SINCE IT?S NOT POSSIBLE TO HAVE
 A FRACTION OF A PERSON, IT APPEARS THAT ALL OCCUPANT
 LOAD CALCS SHOULD ROUND UP, FBC 1004. IT APPEARS THAT
 THE TABULAR OCCUPANT LOAD SHOULD BE 361, AND HALF THE
 REQUIRED WIDTH WOULD THEN BE 36.1IN FOR DOORS, 54.15
 FOR STAIRS.
  
 IF USING THE OCCUPANT LOAD ON A020, OCCUPANT LOAD OF
 359 RESULTS IN CAPACITY OF 36.1 AND 35.9, DOOR AND
 STAIR, REQUIRED.
  
 BASED ON THE INFORMATION PROVIDED, THE LOSS OF AN EXIT
 WILL RESULT IN LOSS OF OVER HALF THE REQUIRED CAPACITY,
 SEE FBC 1005.5.
  
 IT APPEARS THAT A THIRD EXIT COULD BE APPROPRIATE.
  
 4. FBC 5TH EDITION ACCESSIBILITY 604.4, SEE SHEET A120,
 TOILET DETAILS DEPICT DIMENSIONS TO THE TOP OF THE LID.
 THIS SHOULD BE MEASURED TO THE TOP OF THE SEAT; PLEASE
 REVISE.
  
 5. FBC 5TH EDITION ACCESSIBILITY 609.4, THE GRAB BAR IS
 TO BE MEASURED TO THE TOP OF THE GRIPPING SURFACE. THE
 DETAIL DEPICTS THIS AS 36IN MAX, BUT TO THE CENTER OF
 THE GRAB BAR; PLEASE REVISE.
  
 6. THE SHOWER SEAT IS TO BE WITHIN 3IN OF THE
 COMPARTMENT ENTRY, FBC 5TH EDITION ACCESSIBILITY 610.
  
 7. PLEASE SEE PLUMBING PLAN REVIEW FOR THE BUILDING
 PERMIT 15091225 (THE MASTER FOR THIS REVISION). THE
 PLUMBING COMMENTS IN THIS REVIEW ARE REPEAT COMMENTS
 FROM A PREVIOUS REVIEW. IT APPEARS THAT THE MASTER
 FAILED PLUMBING ACCESSIBILITY, THE PLANS WERE
 CORRECTED, PERMIT ISSUED, PLANS REVISED BACK TO THE NON
 COMPLIANT DIMENSIONS AND DETAILS FROM THE PREVIOUS
 REVIEW.
  
 PLEASE CONFIRM THAT ALL ACCESSIBILITY ITEMS ARE
 COMPLIANT, IN PARTICULAR THE ONES WHICH WERE CHANGED
 PREVIOUSLY AND THEN REVISED. IF THEY HAVE BEEN CHANGED
 BACK TO ORIGINAL DESIGN BECAUSE YOU DISAGREE WITH THE
 COMMENTS, PLEASE CONTACT ME (OR PLUMBING REVIEWER) TO
 DISCUSS PRIOR TO RESUBMITTAL. IF THIS IS AN OVERSIGHT,
 PLEASE CONFIRM ALL AND REVISE.
  
 8. PLEASE ADVISE AS TO WHERE THE DOOR HARDWARE LEGEND
 IS LOCATED. SHEET A605 INCLUDES A DOOR SCHEDULE. IF
 THIS IS LOCATED IN THE SPEC BOOK, PLEASE INCORPORATE
 INTO THE PLAN AS THE SPEC BOOK IS NOT A PART OF THIS
 REVIEW.
  
 9. ALL GATES WHICH ARE IN THE MEANS OF EGRESS EXIT
 DISCHARGE FOR THE ASSEMBLY OCCUPANCY (FOR INSTANCE, SEE
 SHEET A107, PEDESTRIAN GATE J3) ARE TO HAVE PANIC
 DEVICES OR FIRE EXIT HARDWARE (1008.1.10, ASSEMBLY OVER
 50 AND 1008.2, GATES TO MEET SAME REQUIREMENTS AS
 DOORS). REVISE PLAN TO SHOW COMPLIANCE. IT IS SUGGESTED
 TO INCLUDE PEDESTRIAN GATES IN OR NEAR THE DOOR
 SCHEDULE.
  
 10. AS I WAS NOT ABLE TO LOCATE THE HARDWARE SCHEDULE,
 PLEASE CONFIRM THAT ALL DOORS IN THE MEANS OF EGRESS
 FOR THE 4TH FLOOR, ASSEMBLY OCCUPANCY INCLUDE PANIC
 DEVICES OR FIRE EXIT HARDWARE AND REVISE PLAN TO SHOW
 COMPLIANCE, FBC 5TH EDITION 1008.1.10 (OR ADVISE AS TO
 THE LOCATION OF THE HARDWARE SCHEDULE); REVISE AS
 NECESSARY.
  
 11. A003, BUILDING DATA, REVISE TO INCLUDE THE NEW
 OCCUPANCY. AS THIS IS A NON SEPARATED MIXED OCCUPANCY
 BUILDING, THE BUILDING HEIGHT AND DATA SHOULD UTILIZE
 THE NUMBERS FOR A2. TO DOCUMENT COMPLIANCE WITH FBC
 TABLE 503, PLEASE ALSO INCLUDE THE SF AREA ALLOWED,
 PLUS SPRINKLER INCREASE, TO CLEARLY DEMONSTRATE
 COMPLIANCE.
  
 12. A751 AND ANY OTHER LOCATIONS AS APPLICABLE, REVISE
 POS DETAIL TO SHOW COMPLIANCE WITH FBC 5TH EDITION
 ACCESSIBILITY 904, SALES AND SERVICE COUNTERS.
  
 13. DESIGN SERVICES DESK AND COUNTER (SUCH AS ON SHEET
 A102 BUT MAY ALSO BE IN OTHER LOCATIONS), EITHER
 PROVIDE A DETAIL SHOWING COMPLIANCE WITH ACCESSIBILITY
 OR THIS REVISION WILL BE ISSUED WITH PROVISO TO PROVIDE
 PRIOR TO INSTALLATION.
  
 14. REGARDING WM. SMITH, PE AND JACOB HEMKE, PE, PLEASE
 PROVIDE EVIDENCE OF THE ADVANCED FBC COURSE (UNLESS THE
 WEBSITE MYFLORIDALICENSE.COM HAS BEEN UPDATED TO
 REFLECT THAT THESE TWO ENGINEERS HAVE TAKEN THE
 COURSE).
  
 ALL ENGINEERS ARE REQUIRED TO TAKE A FLORIDA BUILDING
 CODE COURSE BY JUNE 30, 2016 (PER FS 471.0195,
 FAC61G15-22.001). FLORIDA STATUTE 471.0195 REQUIRES
 THAT ENGINEERS WHO HAVE NOT TAKEN THE COURSE BY THIS
 DATE BE REPORTED TO FBPE.
  
  
  
  
  
  
  
  
  

Review Stop E ELECTRICAL
Rev No 1 Status P Date 2016-07-19 Cont ID  
Sent By albarran Date 2016-07-19 Time 18:06 Rev Time 0.00
Received By albarran Date 2016-07-12 Time 12:37 Sent To  
Notes
2016-07-19 18:20:34ELECTRICAL SCOPE OF REVIEW IS LIMITED ONLY TO THE DELTA
 5 CLOUDED AREAS.
2016-07-15 17:33:31SHEETS WERE FIXED INTERNALLY. PLEASE RE-INITIATE FIRST
 REVIEW.
2016-07-12 13:40:41NOTES FOR INITIAL REVIEW OF 7/12/16
 1ST ELECTRICAL REVIEW NOTES
 REVIEWED FOR COMPLIANCE WITH:
 5TH EDITION FBC 2014 & NFPA 70 2011 (NEC)
  
 1. THERE ARE NUMEROUS SHEETS WHICH ARE CORRUPTED AND
 THUS NOT LOADING PROPERLY MAKING IT IMPOSSIBLE TO
 PERFORM A PROPER ELECTRICAL REVIEW. SOME SHEETS ARE
 MISSING THE TITLE BLOCK OTHERS ARE MISSING THE SHEET
 CONTENT.
 2. ONCE SHEETS ARE PROPERLY UPLOADED IT IS ESSENTIAL
 THAT YOU PROVIDE A DETAILED NARRATIVE INDICATING WHAT
 CHANGES WERE MADE FROM THE ORIGINAL DESIGN.
 WHEN RESUBMITTING, FOR A QUICKER RETURN ON YOUR
 RE-SUBMITTAL, PLEASE PROVIDE A RESPONSE LETTER
 (NARRATIVE) ADDRESSING EACH ITEM AND THE PAGE NUMBER
 WHERE THE CORRECTIONS APPEAR ALONG WITH THE STANDARD
 CITY RE-SUBMITTAL FORM. ADDITIONALLY, PLEASE INSERT
 CORRECTED PAGES INTO THE SUBMITTAL PACKAGE. MARK VOID
 AND LEAVE THE PREVIOUSLY REVIEWED SHEETS FOR
 COMPARATIVE REVIEW. CLOUDING THE CHANGES WILL BE
 GREATLY APPRECIATED.
  
 IF YOU HAVE FURTHER QUESTIONS, PLEASE DON?T HESITATE TO
 CONTACT ME DIRECTLY.
  
 THANK YOU,
 MIKE ALBARRAN
 ELECTRICAL PLANS EXAMINER
 PH: 561-805-6746
 EMAIL: [email protected]
  

Review Stop ENG ENGINEERING CSD
Rev No 1 Status P Date 2016-09-27 Cont ID  
Sent By mgonzale Date 2016-09-27 Time   Rev Time 1.00
Received By mgonzale Date 2016-09-27 Time   Sent To I
Notes
***NONE***

Review Stop FIRE FIRE DEPARTMENT
Rev No 2 Status P Date 2016-08-24 Cont ID  
Sent By pleduc Date 2016-08-24 Time   Rev Time 0.00
Received By pleduc Date 2016-08-24 Time 16:36 Sent To  
Notes
***NONE***

Review Stop FIRE FIRE DEPARTMENT
Rev No 1 Status F Date 2016-07-14 Cont ID  
Sent By pleduc Date 2016-07-14 Time   Rev Time 0.00
Received By pleduc Date 2016-06-27 Time 11:02 Sent To  
Notes
2016-06-27 12:03:56THIS PLAN WAS REVIEWED AND FAILED BY PETER LEDUC, FIRE
 MARSHAL, WITH THE FOLLOWING COMMENTS:
  
  
 1) SHEET A 020 - THE SHEET INDICATES FIRE EXTINQUISHER
 LOCATIONS WITHIN THE STAIRWELLS. AN ALTERNATIVE
 LOCATION SHALL BE INDICATED BASED ON THE FOLLOWING CODE
 REFERENCES
  
 NFPA 101, CHAPTER 36
  
 36.3.5.3 PORTABLE FIRE EXTINGUISHERS SHALL BE PROVIDED
 IN ALL MERCANTILE OCCUPANCIES IN ACCORDANCE WITH
 9.7.4.1.
  
 NFPA 101, CHAPTER 9
  
 9.7.4 MANUAL EXTINGUISHING EQUIPMENT.
 9.7.4.1* WHERE REQUIRED BY THE PROVISIONS OF ANOTHER
 SECTION OF THIS CODE, PORTABLE FIRE EXTINGUISHERS SHALL
 BE SELECTED, INSTALLED, INSPECTED, AND MAINTAINED IN
 ACCORDANCE WITH NFPA 10, STANDARD FOR PORTABLE FIRE
 EXTINGUISHERS.
  
 NFPA 10
 6.1.3 PLACEMENT.
 6.1.3.1 FIRE EXTINGUISHERS SHALL BE CONSPICUOUSLY
 LOCATED WHERE THEY ARE READILY ACCESSIBLE AND
 IMMEDIATELY AVAILABLE IN THE EVENT OF FIRE.
 6.1.3.2 FIRE EXTINGUISHERS SHALL BE LOCATED ALONG
 NORMAL PATHS OF TRAVEL, INCLUDING EXITS FROM AREAS.
 6.1.3.3 VISUAL OBSTRUCTIONS.
 6.1.3.3.1 FIRE EXTINGUISHERS SHALL NOT BE OBSTRUCTED OR
 OBSCURED FROM VIEW.
  
 ADDITIONALLY:
  
 NFPA 101, CHAPTER 7
  
 7.1.3.2.3* AN EXIT ENCLOSURE SHALL NOT BE USED FOR ANY
 PURPOSE THAT HAS THE POTENTIAL TO INTERFERE WITH ITS
 USE AS AN EXIT AND, IF SO DESIGNATED, AS AN AREA OF
 REFUGE. (SEE ALSO 7.2.2.5.3.)
  
 A.7.1.3.2.3 THIS PROVISION PROHIBITS THE USE OF EXIT
 ENCLOSURES FOR STORAGE OR FOR INSTALLATION OF EQUIPMENT
 NOT NECESSARY FOR SAFETY. OCCUPANCY IS PROHIBITED OTHER
 THAN FOR EGRESS, REFUGE, AND ACCESS. THE INTENT IS THAT
 THE EXIT ENCLOSURE ESSENTIALLY BE ?STERILE? WITH
 RESPECT TO FIRE SAFETY HAZARDS.
  
 THE FIRE EXTINGUISHERS CAN BE LOCATED PRIOR TO THE
 STAIRWAY EXIT DOOR, NOT INSIDE THE STAIRWELL.
  
  
  
 2) SHEET LS 020 - THE INDICATED EXIT CAPACITY ON THE
 FOURTH FLOOR IS 330; HOWEVER, THE EXIT STAIRWAY
 CAPACITY IS 162 EACH, AN EXIT CAPACITY OF 324.
  
 ADDING ALL THE OCCUPANCY LOADS INDICATES A TOTAL 331.
  
 PLEASE CORRECT OR VERIFY.
  
  
  
 3) SHEETS A 003 & FA 160 - THE HOOD SYSTEM IN THE
 KITCHEN AREA SHALL BE PERMITTED UNDER SEPARATE SHOP
 DRAWINGS AND INSTALLED PER NFPA 96.
  
 NFPA 101, CHAPTER 36
 36.3.2.3 COOKING EQUIPMENT. COOKING EQUIPMENT SHALL BE
 PROTECTED IN ACCORDANCE WITH 9.2.3, UNLESS THE COOKING
 EQUIPMENT IS ONE OF THE FOLLOWING TYPES:
 (1) OUTDOOR EQUIPMENT
 (2) PORTABLE EQUIPMENT NOT FLUE-CONNECTED
 (3) EQUIPMENT USED ONLY FOR FOOD WARMING
  
 NFPA 101, CHAPER 9
  
 9.2.3 COMMERCIAL COOKING EQUIPMENT. COMMERCIAL COOKING
 EQUIPMENT SHALL BE IN ACCORDANCE WITH NFPA 96, STANDARD
 FOR VENTILATION CONTROL AND FIRE PROTECTION OF
 COMMERCIAL COOKING OPERATIONS, UNLESS SUCH
 INSTALLATIONS ARE APPROVED EXISTING INSTALLATIONS,
 WHICH SHALL BE PERMITTED TO BE CONTINUED IN SERVICE.
  
 NFPA 96
  
 NFPA 96, CHAPTER 4 GENERAL REQUIREMENTS
 4.1 GENERAL.
 4.1.1 COOKING EQUIPMENT USED IN PROCESSES PRODUCING
 SMOKE OR GREASE-LADEN VAPORS SHALL BE EQUIPPED WITH AN
 EXHAUST SYSTEM THAT COMPLIES WITH ALL THE EQUIPMENT AND
 PERFORMANCE REQUIREMENTS OF THIS STANDARD.
  
 10.1.2* COOKING EQUIPMENT THAT PRODUCES GREASE-LADEN
 VAPORS AND THAT MIGHT BE A SOURCE OF IGNITION OF GREASE
 IN THE HOOD, GREASE REMOVAL DEVICE, OR DUCT SHALL BE
 PROTECTED BY FIRE-EXTINGUISHING EQUIPMENT.
  
 PLEASE PROVIDE A NOTE INDICATING THE ABOVE.
  
  
  
 4) ADDITIONAL COMMENTS MAY BE PROVIDED ON THE
 RE-SUBMITTAL OF THE ABOVE.
  
 PETER LEDUC
 FIRE MARSHAL
 561-804-4709
 [email protected]
  

Review Stop G GAS REVIEW
Rev No 2 Status P Date 2016-09-22 Cont ID  
Sent By gjohnson Date 2016-09-22 Time 12:36 Rev Time 0.00
Received By gjohnson Date 2016-09-20 Time 15:37 Sent To  
Notes
***NONE***

Review Stop G GAS REVIEW
Rev No 1 Status F Date 2016-07-21 Cont ID  
Sent By gjohnson Date 2016-07-21 Time 10:00 Rev Time 0.00
Received By gjohnson Date 2016-07-21 Time 10:00 Sent To  
Notes
2016-07-21 10:12:301ST REVIEW
  
  
  
 GEORGE JOHNSON
 PLUMBING PLANS EXAMINER LL
 CITY OF WEST PALM BEACH
 DEVELOPMENT SERVICES
 BUILDING DIVISION
 561-805-6711
 [email protected]
  
  
 GAS COMMENTS:
  
 1. SUBMIT AN ISOMETRIC DRAWING THAT CLEARLY SHOWS ALL
 CUT SECTIONS OF PIPE AND CORRESPONDING LENGTHS PER
 FBC-2014 FUEL GAS, SECS. 402.4.1, 402.4.2.
  
  
 2. BTU LOAD OF EACH APPLIANCE AND THE TOTAL BTU LOAD ON
 THE SYSTEM. REFER TO THE FBC-2014 FUEL GAS SECS. 401.8
 THRU 402.6.1 AND TABLES 402.4(1) THRU 402.4(37).
  
  
 3. SUBMIT CALCULATIONS FOR COMBUSTION AIR PER THE
 FBC-2014 FUEL GAS CODE SEC. 304.
  
 4. SUBMIT MANUFACTURER?S SPECIFICATION SHEETS FOR ALL
 GAS EQUIPMENT TO VERIFY COMPLIANCE WITH STANDARDS NFPA
 54, NFPA 58, AND FBC-2014 FUEL GAS SEC. 402.2
  
 5. SUBMIT A DETAIL SHOWING THE TYPE, LOCATION, SIZE AND
 TERMINATION OF THE GAS VENTS PER FBC-2014 FUEL GAS CODE
 SEC. 502 THRU 505.
  
 6. PROVIDE TABLES YOUR USING FOR SIZING PIPE. PER WPB
 AMEND. TO FBC 107.2.1
  
 7. SHOW SHUT OFF VALVES AND DRIP LEGS. PER WPB AMEND.
 TO FBC 107.2.1
  
  
 DUE TO THE DEFICIENCIES OF THIS PLAN A COMPLETE AND
 THOROUGH REVIEW CANNOT BE DONE AT THIS TIME. UPON
 RESUBMITTAL THERE MAYBE ADDITIONAL COMMENTS.
  
 WHEN RESUBMITTING PLANS, REMOVE AND REPLACE ANY PAGES
 AS NECESSARY. A NARRATIVE LISTING THE ORIGINAL REVIEW
 COMMENT NUMBER WITH A DESCRIPTION OF THE CHANGES MADE
 AND IDENTIFYING THE SHEET OR SPECIFICATION PAGE WHERE
 THE CHANGE CAN BE FOUND WILL HELP EXPEDITE THE REVIEW.
  

Review Stop I INCOMING/PROCESSING
Rev No 3 Status N Date 2016-10-19 Cont ID  
Sent By skennedy Date 2016-10-19 Time 14:12 Rev Time 0.00
Received By skennedy Date 2016-09-29 Time 16:32 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2016-09-27 Cont ID  
Sent By lmarchan Date 2016-09-27 Time 15:47 Rev Time 0.00
Received By lmarchan Date 2016-08-22 Time 11:28 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2016-08-19 Cont ID  
Sent By lmarchan Date 2016-08-19 Time 15:09 Rev Time 0.00
Received By lmarchan Date 2016-06-24 Time 07:54 Sent To  
Notes
***NONE***

Review Stop IMPACT COUNTY IMPACT FEES
Rev No 2 Status P Date 2016-10-19 Cont ID  
Sent By skennedy Date 2016-10-19 Time 14:12 Rev Time 0.00
Received By skennedy Date 2016-10-19 Time 14:12 Sent To  
Notes
***NONE***

Review Stop IMPACT COUNTY IMPACT FEES
Rev No 1 Status F Date 2016-07-12 Cont ID  
Sent By shill Date 2016-07-12 Time 12:50 Rev Time 0.00
Received By shill Date 2016-07-14 Time 14:20 Sent To  
Notes
2016-07-12 12:50:52****CORRECTIONS****
  
 SAMANTHA HILL
 BUILDING PLANS EXAMINER
 [email protected]
 561-805-6724
  
 1. IMPACT FEE ASSESSMENT BY PALM BEACH COUNTY IS
 REQUIRED AS THE SQUARE FOOT AREAS AND USE HAS CHANGED.
 PLEASE CONTACT 561-233-5025 FOR MORE INFORMATION.
  
  

Review Stop M MECHANICAL (A/C)
Rev No 3 Status P Date 2016-10-05 Cont ID  
Sent By ccole Date 2016-10-05 Time 14:07 Rev Time 0.00
Received By ccole Date 2016-10-05 Time 13:27 Sent To  
Notes
2016-10-05 14:08:42SEE PROVISOS AND HOLDS UNDER MASTER PERMIT #15091225
 CCOLE- 10/5/2016

Review Stop M MECHANICAL (A/C)
Rev No 2 Status F Date 2016-09-14 Cont ID  
Sent By ccole Date 2016-09-14 Time 12:33 Rev Time 0.00
Received By ccole Date 2016-09-13 Time 12:14 Sent To  
Notes
2016-09-14 12:34:012ND REVIEW FBC-2014 MECHANICAL
 PERMIT #16061051
 RESTORATION HARDWARE RE-DESIGN
 9/14/16
  
 1) THE REQUESTED AC COOLING AND HEATING CALCULATIONS
 FOR HP-9 & HP-10 WERE NOT SUBMITTED.
  
 2) THE RESUBMITTED ENERGY CALCULATIONS DO NOT PROVIDE
 COMPLIANCE DATA FOR THE NEW HP-9 AND HP-10, AND THE
 ERV.
  
 3) THE COMPLIANCE DATA IN THE RESUBMITTED CALCULATIONS
 DOES NOT MATCH THE DATA IN THE EQUIPMENT SCHEDULES IN
 TERMS OF COOLING AND HEATING CAPACITIES I.E. THE 336
 MBH HP-3 WHICH HAS BEEN GROUPED TOGETHER WITH HP-1 &
 HP-2.
  
 4) SHEET MP100 & FS-210: SHOW THE LOCATION OF THE
 COLDZONE ROOFTOP REFRIGERATION UNIT.
  
 5) THE REQUESTED COMBUSTION, EXHAUST, AND AIR BALANCE
 CALCULATIONS WERE SUBMITTED AS UNSIGNED DOCUMENTS.
 PLEASE PLACE THE CALCULATIONS AND THE AIR BALANCE
 DIAGRAM ON THE PLANS AT THE APPROPRIATE LOCATIONS.
  
 6) M-101, 102, 103, 104: PLEASE PLACE A KEYED NOTE ON
 EACH PLAN SHEET TO CLARIFY THE CONTROL OPERATIONS OF
 THE DUCT SMOKE DETECTORS- SEE SECTION 606.4.
  
 7) M-103 & M-104: PROVIDE AN FD SYMBOL FOR THE DUCTS
 PENETRATING THE FIRE-RATED FLOOR/CEILING ASSEMBLY THE
 LEVEL 4 RESTAURANT AND WINE VAULTS.. THE FD DETAIL ON
 SHEET M301 DOES NOT APPEAR TO BE COMPATIBLE WITH THE
 TYPE OF FLOOR REGISTERS SPECIFIED ON M402. PLEASE NOTE
 ENGINEER APPROVED SUBMITTALS FOR ALL FD'S AND FSD'S ARE
 REQUIRED.
  
 8) M-104: PROVIDE A MEANS OF MAKEUP AIR FOR THE
 CONDENSATE HOOD.
  
 9) PLEASE PROVIDE A REFIGERANT PIPING RISER DRAWING
 WITH PIPE SIZES AND SPECIFICATIONS.
  
 10) AS NOTED IN THE FIRST REVIEW, ALL PROVISOS LISTED
 UNDER THE MASTER PERMIT #15091225 ARE NOW APPLICABLE TO
 THIS REVISION PERMIT, INCLUDING THE REQUIRED REVISIONS
 TO THE REMOVABLE AC PLATFORMS. IT IS HIGHLY RECOMMENDED
 THAT THE DESIGN PROFESSIONALS AND CONTRACTORS PUT
 TOGETHER A SUBMITTAL PACKAGE ADDRESSING ALL PROVISOS AS
 SOON AS POSSIBLE TO AVOID DELAYS DURIONG CONSTRUCTION.
  
 CHRISTOPHER L. COLE
 MECHANICAL PLANS EXAMINER
 561-805-6719
 [email protected]
  

Review Stop M MECHANICAL (A/C)
Rev No 1 Status F Date 2016-07-08 Cont ID  
Sent By ccole Date 2016-07-08 Time 08:30 Rev Time 0.00
Received By ccole Date 2016-07-06 Time 08:30 Sent To  
Notes
2016-07-08 08:40:541ST REVIEW: FBC 2014 MECHANICAL
 PERMIT REVISION #16061051
 MASTER PERMIT #15091225
 RESTORATION HARDWARE
 7/6/2016
  
 1) PLEASE PROVIDE A SHEET-BY-SHEET NARRATIVE ITEMIZING
 ALL CHANGES MADE TO THE ORIGINAL MECHANICAL PLANS.
 PLACE CLOUDS AND DELTA TRIANGLE SYMBOLS ON THE REVISED
 PLANS TO HIGHLIGHT ALL CHANGES SUCH AS THE NEW AND
 RELOCATED VRV'S AND DUCT WORK, THE NEW EXHAUST FANS,
 THE NEW HEAT PUMPS AND OAI UNITS ETC.
  
 2) SUBMIT REVISED AC COOLING AND HEATING CALCULATIONS
 FOR ALL SYSTEMS INCLUDING THE NEW HEAT PUMPS- 9 & 10,
 AND THE DUCTLESS TRASH ROOM AC SYSTEM SECTION C403.2.1
 FBC-14 ENERGY CONSERVATION.
  
 3) SUBMIT REVISED ENERGY CALCULATIONS PER SECTION
 C401.2
  
 4) ADVISORY: SEPARATE PERMITS ARE REQUIRED FOR THE
 KITCHEN EXHAUST HOODS AND FIRE SUPPRESSION SYSTEMS.
 PLEASE PLACE A NOTE ON THE PLAN ACCORDINGLY.
  
 5) PROVIDE COMPLETE KITCHEN PLANS AND A KITCHEN
 EQUIPMENT SCHEDULE. CLARIFY IF WALK-IN COOLERS AND
 FREEZERS ARE TO BE INSTALLED AND SHOW THEIR LOCATIONS
 ON THE PLANS (SEPARATE PERMITS REQUIRED FOR WALK-INS
 AND REFRIGERATION). PLEASE NOTE IF GAS-FIRED COOKING
 APPLIANCES ARE TO BE INSTALLED, A GAS PIPING ISOMETRIC
 DRAWING AND COMBUSTION AIR CALCULATIONS WILL BE
 REQUIRED FOR REVIEW- SEE
 SECTIONS 304 & 401 FBC-14 FUEL GAS.
  
 6) REFER TO TABLE 403.3 AND PROVIDE EXHAUST VENTILATION
 CALCULATIONS FOR THE KITCHEN, THE TRASH ROOM, THE
 COOKING OIL STORAGE ROOM, AND THE JANITOR'S CLOSET- SEE
 THE NEW EF SCHEDULE ON SHEET M.401.
  
 7) PROVIDE AIR BALANCE CALCULATIONS FOR LEVEL-4.
  
 8) PROVIDE AN EQUIPMENT SCHEDULE FOR MUA-1.
  
 9) SHEET M-101: PROVIDE INDEPENDENT VENTILATION OR AC
 SYSTEMS FOR THE ELEVATOR CONTROL ROOMS 194 & 197.
  
 10) M-101: INDICATE THE REQUIRED CLEARANCES FOR THE
 EF-12 TERMINATION SHOWN AT THE NORTH SIDE- SEE SECTION
 501.3.1, AND PROVIDE A FLORIDA PRODUCT APPROVAL OR
 MIAMI-DADE NOA FOR THE EXHAUST LOUVER WITH SHOP DRAWING
 APPROVAL BY THE ENGINEER OF RECORD.
  
 11) M-101: KEYED NOTE #7 IS MISSING AT THE NORTH SHAFT.
  
 12) M-101, 102, 103, & 104: BECAUSE EACH FLOOR HAS A
 COMMON PLENUM, DUCT SMOKE DETECTORS ARE REQUIRED IN THE
 RETURN AIR SYSTEMS OF ALL VRV'S SHOWN ON THE PLAN-
 REFER TO SECTION 606.2.2. PLACE A SD SYMBOL AT EACH VRV
 LOCATION.
  
 13) M-101, 102, 103, 104: PROVIDE EQUIPMENT SCHEDULES
 AND SUBMITTALS FOR THE F/S DAMPERS AND ACCESS DOORS.
 SHOW THE DUCT CONNECTIONS TO THE FLOOR GRILLS ON THE
 4TH LEVEL AT THE WINE VAULT AREAS, AND PROVIDE DETAILS
 FOR INSTALLATION OF FIRE DAMPERS AT THESE LOCATIONS.
  
 14) M-103: THE 24X16 TRANSFER GRILL CONVEYING 1500 CFMS
 FROM THE RETAIL AREA IS UNDERSIZED PER SECTION 601.5:
 50 SQUARE INCHES PER 100 CFM IS REQUIRED.
  
 15) M-104: PLEASE CLEARLY LABEL THE KITCHEN HOOD
 EXHAUST AND MAKE UP AIR DUCTS AT THE HOOD LOCATION.
  
 16) M-104: REMOVE THE NOTE INDICATING O/A DUCT
 CONNECTION FROM OAI-1 TO VRV-48. VRV-48 HAS O/A SUPPLY
 FROM OAI-4.
  
 17) M-104: MOTORIZED DAMPERS ARE REQUIRED FOR THE O/A
 INTAKE DUCTS FOR THE 4TH FLOOR VRV'S- REFER TO SECTION
 C404.2.4.4 FBC-14 ENERGY CONSERVATION.
  
 18) M-104: DEMAND CONTROLLED VENTILATION IS REQUIRED
 FOR THE DINING AND WINE VAULT AREAS PER SECTION
 C403.2.5.1. PROVIDE A SYSTEM THAT MEETS COMPLIANCE.
  
 19) M-402: THE OUTSIDE AIR SCHEDULE APPEARS TO SHOW
 DEFICIENCIES IN SOME OF THE PROVIDED O/A CFMS WHEN
 COMPARED WITH THE CFMS SHOWN AS REQUIRED.
  
 20) ADVISORY: COPIED BELOW ARE THE PROVISOS FROM THE
 MASTER PERMIT #15091225. THESE WIIL NOW APPLY TO THIS
 REVISION PERMIT #16061051.
  
 IN ADDITION PLEASE NOTE THAT THE ENGINEER'S LETTERS TO
 THE BUILDING OFFICIAL REGARDING THE AC STANDS AND
 REMOVABLE PLATFORMS THAT WERE SUBMITTED UNDER THE
 MASTER PERMIT MUST BE MODIFIED AND ATTACHED TO THIS
 REVISION PERMIT APPLICATION.
  
 MECHANICAL PROVISOS:
 PERMIT #15091225
 2/18/16
  
 1 ) C408.2 FBC-14 ENERGY CONSERVATION: MECHANICAL
 SYSTEMS COMMISSIONING AND COMPLETION REQUIREMENTS.
 PRIOR TO PASSING THE FINAL MECHANICAL INSPECTION, THE
 REGISTERED DESIGN PROFESSIONAL SHALL PROVIDE EVIDENCE
 OF MECHANICAL SYSTEMS COMMISSIONING AND COMPLETION IN
 ACCORDANCE THE PROVISIONS OF THIS SECTION.
 CONSTRUCTION DOCUMENT NOTES SHALL CLEARLY INDICATE
 PROVISIONS FOR COMMISSIONING AND COMPLETION
 REQUIREMENTS IN ACCORDANCE WITH THIS SECTION AND ARE
 PERMITTED TO REFER TO SPECIFICATIONS FOR FURTHER
 REQUIREMENTS. COPIES OF ALL DOCUMENTATION SHALL BE
 GIVEN TO THE OWNER AND MADE AVAILABLE TO THE CODE
 OFFICIAL UPON REQUEST IN ACCORDANCE WITH SECTIONS
 C408.2.4 AND C408.2.5.
 A) C408.2.1 COMMISSIONING PLAN.
 A COMMISSIONING PLAN SHALL BE DEVELOPED BY A REGISTERED
 DESIGN PROFESSIONAL OR APPROVED AGENCY AND SHALL
 INCLUDE THE FOLLOWING ITEMS:
 1. A NARRATIVE DESCRIPTION OF THE ACTIVITIES THAT WILL
 BE ACCOMPLISHED DURING EACH PHASE OF COMMISSIONING,
 INCLUDING THE PERSONNEL INTENDED TO ACCOMPLISH EACH OF
 THE ACTIVITIES.
 2. A LISTING OF THE SPECIFIC EQUIPMENT, APPLIANCES OR
 SYSTEMS TO BE TESTED AND A DESCRIPTION OF THE TESTS TO
 BE PERFORMED.
 3. FUNCTIONS TO BE TESTED, INCLUDING, BUT NOT LIMITED
 TO CALIBRATIONS AND ECONOMIZER CONTROLS.
 4. CONDITIONS UNDER WHICH THE TEST WILL BE PERFORMED.
 AT A MINIMUM, TESTING SHALL AFFIRM WINTER AND SUMMER
 DESIGN CONDITIONS AND FULL OUTSIDE AIR CONDITIONS.
 5. MEASURABLE CRITERIA FOR PERFORMANCE.
  
 B) C408.2.2 AIR DISTRIBUTION SYSTEM TESTING, ADJUSTING
 AND BALANCING.
 CONSTRUCTION DOCUMENTS SHALL REQUIRE THAT A WRITTEN
 BALANCE REPORT BE PROVIDED TO THE OWNER OR THE
 DESIGNATED REPRESENTATIVE OF THE BUILDING OWNER FOR
 HVAC SYSTEMS SERVING ZONES WITH A TOTAL CONDITIONED
 AREA EXCEEDING 5000 SQUARE FEET (465 M2). AIR
 DISTRIBUTION SYSTEMS SHALL BE TESTED, ADJUSTED, AND
 BALANCED BY A LICENSED ENGINEER OR A COMPANY OR
 INDIVIDUAL HOLDING A CURRENT CERTIFICATION FROM A
 RECOGNIZED TESTING AND BALANCING AGENCY ORGANIZATION IN
 ACCORDANCE WITH GENERALLY ACCEPTED ENGINEERING
 STANDARDS.
  
 C) C408.2.4 PRELIMINARY COMMISSIONING REPORT.
 A PRELIMINARY REPORT OF COMMISSIONING TEST PROCEDURES
 AND RESULTS SHALL BE COMPLETED AND CERTIFIED BY THE
 REGISTERED DESIGN PROFESSIONAL OR APPROVED AGENCY AND
 PROVIDED TO THE BUILDING OWNER. THE REPORT SHALL BE
 IDENTIFIED AS ?PRELIMINARY COMMISSIONING REPORT? AND
 SHALL IDENTIFY:
 1. ITEMIZATION OF DEFICIENCIES FOUND DURING TESTING
 REQUIRED BY THIS SECTION THAT HAVE NOT BEEN CORRECTED
 AT THE TIME OF REPORT PREPARATION.
 2. DEFERRED TESTS THAT CANNOT BE PERFORMED AT THE TIME
 OF REPORT PREPARATION BECAUSE OF CLIMATIC CONDITIONS.
 3. CLIMATIC CONDITIONS REQUIRED FOR PERFORMANCE OF THE
 DEFERRED TESTS.
  
 D) C408.2.4.1 ACCEPTANCE OF REPORT.
 BUILDINGS, OR PORTIONS THEREOF, SHALL NOT PASS THE
 FINAL MECHANICAL INSPECTION UNTIL SUCH TIME AS THE CODE
 OFFICIAL HAS RECEIVED A LETTER OF TRANSMITTAL FROM THE
 BUILDING OWNER ACKNOWLEDGING THAT THE BUILDING OWNER
 HAS RECEIVED THE PRELIMINARY COMMISSIONING REPORT.
  
 E) C408.2.4.2 COPY OF REPORT.
 THE CODE OFFICIAL SHALL BE PERMITTED TO REQUIRE THAT A
 COPY OF THE PRELIMINARY COMMISSIONING REPORT BE MADE
 AVAILABLE FOR REVIEW BY THE CODE OFFICIAL.
  
 F) C408.2.5.4 FINAL COMMISSIONING REPORT.
 A REPORT OF TEST PROCEDURES AND RESULTS IDENTIFIED AS
 "FINAL COMMISSIONING REPORT" SHALL BE DELIVERED TO THE
 BUILDING OWNER AND SHALL INCLUDE:
 1. RESULTS OF FUNCTIONAL PERFORMANCE TESTS.
 2. DISPOSITION OF DEFICIENCIES FOUND DURING TESTING,
 INCLUDING DETAILS OF CORRECTIVE MEASURES USED OR
 PROPOSED.
 3. FUNCTIONAL PERFORMANCE TEST PROCEDURES USED DURING
 THE COMMISSIONING PROCESS INCLUDING MEASURABLE CRITERIA
 FOR TEST ACCEPTANCE, PROVIDED HEREIN FOR REPEATABILITY.
 EXCEPTION: DEFERRED TESTS WHICH CANNOT BE PERFORMED AT
 THE TIME OF REPORT PREPARATION DUE TO CLIMATIC
 CONDITIONS.
  
 2) DEFERRED SUBMITTAL: 107.3.4.2 DEFERRED SUBMITTALS.
 FOR THE PURPOSES OF THIS SECTION, DEFERRED SUBMITTALS
 ARE DEFINED AS THOSE PORTIONS OF THE DESIGN THAT ARE
 NOT SUBMITTED AT THE TIME OF THE
 APPLICATION AND THAT ARE TO BE SUBMITTED TO THE
 BUILDING OFFICIAL WITHIN A SPECIFIED PERIOD. DEFERRAL
 OF ANY SUBMITTAL ITEMS SHALL HAVE THE PRIOR APPROVAL OF
 THE BUILDING OFFICIAL. THE REGISTERED DESIGN
 PROFESSIONAL IN RESPONSIBLE CHARGE SHALL LIST THE
 DEFERRED SUBMITTALS ON THE CONSTRUCTION DOCUMENTS FOR
 REVIEW BY THE BUILDING OFFICIAL.
 DOCUMENTS FOR DEFERRED SUBMITTAL ITEMS SHALL BE
 SUBMITTED TO THE REGISTERED DESIGN PROFESSIONAL IN
 RESPONSIBLE CHARGE WHO SHALL REVIEW THEM AND FORWARD
 THEM TO THE BUILDING OFFICIAL WITH A NOTATION
 INDICATING THAT THE DEFERRED SUBMITTAL DOCUMENTS HAVE
 BEEN REVIEWED AND FOUND TO BE IN GENERAL CONFORMANCE TO
 THE DESIGN OF THE BUILDING. THE DEFERRED SUBMITTAL
 ITEMS SHALL NOT BE INSTALLED UNTIL THE DEFERRED
 SUBMITTAL DOCUMENTS HAVE BEEN APPROVED BY THE BUILDING
 OFFICIAL.
 A) DEFERRED SUBMITTAL. 2010 FBC 107.3.4.1 PRODUCT
 APPROVALS. THOSE PRODUCTS WHICH ARE REGULATED BY THE
 DCA RULE 9N-03 SHALL BE REVIEWED AND APPROVED IN
 WRITING BY THE DESIGNER OF RECORD PRIOR TO SUBMITTAL
 FOR JURISDICTIONAL APPROVAL.
  
 3) FINAL APPROVAL OF THE ALTERNATE METHOD OF
 CONSTRUCTION OF THE ACCESS PANELS FOR ABOVE CEILING AC
 EQUIPMENT MECHANICAL IS CONTINGENT ON A LETTER OF
 ACKNOWLEDGEMENT FROM THE RESTORATION HARDWARE FACILITY
 MANAGER, AND YOU ALSO INCLUDE THE DISASSEMBLY PROCEDURE
 INSTRUCTIONS IN THE O & M MANUAL THAT THE
 CONTRACTOR/DESIGN TEAM WILL PROVIDED TO RESTORATION
 HARDWARE.
  
 CHRISTOPHER L. COLE
 MECHANICAL PLANS EXAMINER
 561-805-6719
 [email protected]
  

Review Stop P PLUMBING
Rev No 2 Status P Date 2016-09-22 Cont ID  
Sent By gjohnson Date 2016-09-22 Time 13:00 Rev Time 0.00
Received By gjohnson Date 2016-09-20 Time 15:38 Sent To  
Notes
***NONE***

Review Stop P PLUMBING
Rev No 1 Status F Date 2016-07-20 Cont ID  
Sent By tklarge Date 2016-07-20 Time 14:37 Rev Time 0.00
Received By gjohnson Date 2016-07-02 Time 12:33 Sent To  
Notes
2016-07-20 15:48:561ST REVIEW
  
  
  
 GEORGE JOHNSON
 PLUMBING PLANS EXAMINER LL
 CITY OF WEST PALM BEACH
 DEVELOPMENT SERVICES
 BUILDING DIVISION
 561-805-6711
 [email protected]
  
  
 PLUMBING COMMENTS:
  
 1. SHT. P-301 PLEASE PROVIDE PLUMBING FIXTURE SCHEDULE.
 PER WPB AMEND.TO FBC SEC. 107.2.1
  
 2. SHT. P-101 IT APPEARS YOU MOVED THE MOP SINK ON THE
 FIRST FLOOR AT GRID LINES A-5.3 AND B5.3 IT IS NOT
 CLEAR ON THE FLOOR PLAN PLEASE CLOUD EVERY CHANGE. PER
 WPB AMEND.TO FBC SEC. 107.2.1
  
 3. SHT. P202.1 THE 2IN. FITTING ON THE VENT FOR TROUGH
 DRAIN IS SHOWN IN THE WRONG FLOW DIRECTION. PER WPB
 AMEND.TO FBC SEC. 107.2.1
  
 4. SHT. P202.1 THE VENT FOR THE MOP SINK ON FIRST FLOOR
 NEEDS TO CONNECT VERTICALLY TO TO HORIZONTAL DRAIN
 SHALL COMPLY WITHE FBC PL SEC. 905.3 VENT CONNECTION TO
 DRAINAGE SYSTEM.
 EVERY DRY VENT CONNECTING TO A HORIZONTAL DRAIN SHALL
 CONNECT ABOVE THE CENTERLINE OF THE HORIZONTAL DRAIN
 PIPE.
  
 905.4 VERTICAL RISE OF VENT.
 EVERY DRY VENT SHALL RISE VERTICALLY TO A POINT NOT
 LESS THAN 6 INCHES (152 MM) ABOVE THE FLOOD LEVEL RIM
 OF THE HIGHEST TRAP OR TRAPPED FIXTURE BEING VENTED.
  
 5.SHT. P 202.1 THE LAV STACK NEXT TO URINAL CAN NOT
 REDUCE IN SIZE FROM 2IN TO 11/2 AND BACK TO 2IN.
  
 6. SHT. P201.1 A NOTE SHOW CONDENSATE DRAIN IN WALL TO
 DISCHARGE INTO FLOOR SINK CONDENSATE SHALL NOT
 DISCHARGE INTO SANITARY SYSTEM. PER FBC SEC. [M]
 314.2.1 / WPB CODE OF ORD. SEC. 90-126.(5)
  
 7. SHT. P203 THE 2IN VENTS FOR THE FLOOR SINKS ARE
 HORIZONTAL DRY VENTS WHICH ARE NOT ALLOWED THEY SHALL
 COMPLY WITH FBC PL SEC. 905.3-905.4
  
 8. SHT. P201.1/ P301 THESE EQUIPMENT NUMBERS ARE
 MISSING ON THE PLUMBING EQUIPMENT SCHEDULE 3.13, 2.12,
 2.13, 2.14 .PLEASE CLARIFY PER WPB AMEND.TO FBC SEC.
 107.2.1
  
 9. SHT. 201.1 THE EQUIPMENT NUMBERS ARE MISSING 5.02,
 5.03, 5.04, 5.05, 5.06, 5.07, 3.27 PLEASE CLARIFY PER
 WPB AMEND.TO FBC SEC. 107.2.1
  
 10. SHOW FLOW ARROWS ON HOT WATER RECIRCULATION SYSTEM.
 PER WPB AMEND.TO FBC SEC. 107.2.1
  
 11. PROVIDE MANUFACTURE SPEC AND INSTILLATION GUIDES
 FOR TANKLESS HEATERS AND VENTS. PER WPB AMEND.TO FBC
 SEC. 107.2.1
  
 12. PROVIDE DETAIL FOR VENTING ON TANKLESS HEATERS. PER
 WPB AMEND.TO FBC SEC. 107.2.1
  
 13. THE HAND SINKS IN KITCHEN SHALL DISCHARGE INTO
 SANITARY NOT THE GREASE SYSTEM. PER FBC PL
 1003.3.1/1003.2
  
 14. SHT. P206 SHOW SQFT ON STORM RISER DIAGRAM. PER WPB
 AMEND.TO FBC SEC. 107.2.1
  
  
 DUE TO THE DEFICIENCIES OF THIS PLAN A COMPLETE AND
 THOROUGH REVIEW CANNOT BE DONE AT THIS TIME. UPON
 RESUBMITTAL THERE MAYBE ADDITIONAL COMMENTS
  
 WHEN RESUBMITTING PLANS, REMOVE AND REPLACE ANY PAGES
 AS NECESSARY. A NARRATIVE LISTING THE ORIGINAL REVIEW
 COMMENT NUMBER WITH A DESCRIPTION OF THE CHANGES MADE
 AND IDENTIFYING THE SHEET OR SPECIFICATION PAGE WHERE
 THE CHANGE CAN BE FOUND WILL HELP EXPEDITE THE REVIEW.
  
  
  
  
  
  
  

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 1 Status P Date 2016-10-19 Cont ID  
Sent By skennedy Date 2016-10-19 Time 14:12 Rev Time 0.00
Received By skennedy Date 2016-10-19 Time 14:12 Sent To  
Notes
2016-10-05 14:07:32MECHANICAL SIGNATURES VERIFIED INCLUDING PLAN SHEETS,
 ENERGY AND AC CALCULATIONS.
 CCOLE 10/5/2016
2016-09-09 07:38:219/9/16 THE FOLLOWING DOCUMENTS DIGITAL SIGNATURE HAVE
 BEEN VERIFIED:
  
 NEW SUPPORTING DOCS DATED 8/22/16:
 FLORIDA ENERGY CALCS INPUT
 FLORIDA ENERGY CALCS
 STANDPIPE CALCS
  
 DRAWINGS:
 ARCHITECTURAL SHEETS
 STRUCTURAL SHEETS
 FIRE SPRINKLER SHEETS
 FIRE ALARM SHEETS
 WF (WATER FOUNTAIN) SHEETS
 CIVIL SHEETS
 LANDSCAPE
 FOOD SERVICE
  
  
2016-07-12 07:23:347/12 VERIFIED SUPPORTING DOCUMENTS - STANDPIPE
 HYDRAULIC CALCS PREPARED BY WM SMITH, PE
 VERIFIED ARCH & STRUCT SHEETS DIGITAL SIGNATURES OK
  
 WM.SMITH (FS), JACOB HEMKE (FA) DO NOT HAVE FBC COURSE
 PER WEBSITE, SENT EMAIL 7/12/16
 ALL OTHER PES VERIFIED 7/11/16 (DID NOT CHECK CIVIL
 ENGINEER)
  
  
  
  
  

Review Stop Z ZONING
Rev No 2 Status P Date 2016-09-16 Cont ID  
Sent By eschneid Date 2016-09-16 Time 16:39 Rev Time 2.00
Received By eschneid Date 2016-09-12 Time 08:46 Sent To  
Notes
***NONE***

Review Stop Z ZONING
Rev No 1 Status F Date 2016-08-19 Cont ID  
Sent By eschneid Date 2016-08-19 Time 10:15 Rev Time 7.00
Received By eschneid Date 2016-08-19 Time 10:15 Sent To  
Notes
2016-08-19 10:16:11FAILED
  
 PLEASE PROVIDE WRITTEN RESPONSES.
  
 1) THE SITE LAYOUT SHOWN ON THE PLANS IS DIFFERENT FROM
 THE APPROVED PLANS. THE PROPOSED SITE LAYOUT IS
 SCHEDULED TO BE HEARD BY THE CITY COMMISSION ON AUGUST
 29, 2016. ZONING CANNOT GIVE FINAL APPROVAL OF THE
 PERMIT UNTIL AFTER THE COMMISSION APPROVAL AND
 EFFECTIVE DATE OF THE RESOLUTION.
  
 2) SHEETS WILL BE APPROVED IF THE AMENDMENT PASSES
 A-003, A-010, A-101, A-102, A-103, A-104, A-105, A-120,
 A-201, A-201A, A-202, A-202A, A-203, A-204, A-418,
 A-420, A-421, 424, 426, A-450, A-451, A-452 THROUGH
 A-457, A-460 THROUGH A-464, MP-100, C4.02
  
 3) PROVIDE THE VERSION OF SHEET A-050 THAT IS BEING
 CONSIDERED AS PART OF RESOLUTION NO. 260-16, LEVEL III
 SITE PLAN AMENDMENT
  
 4) IN ACCORDANCE WITH SECTION 94-111(E)(1) OF THE
 ZONING AND LAND DEVELOPMENT REGULATIONS, SINCE TANDEM
 PARKING SPACES ARE BEING USED TO PROVIDE REQUIRED
 PARKING THE APPLICANT SHALL RECORD A RESTRICTIVE
 COVENANT, APPROVED BY THE CITY ATTORNEY'S OFFICE,
 REQUIRING THAT THE SURFACE PARKING LOT BE MAINTAINED AS
 A VALET ONLY FACILITY. THE RESTRICTIVE COVENANT SHALL
 BE RECORDED PRIOR TO THE ISSUANCE OF THE CERTIFICATE OF
 COMPLETION FOR THE SURFACE PARKING LOT AND THE
 CERTIFICATE OF OCCUPANCY FOR THE RESTORATION HARDWARE
 GALLERY.
  
 5) SEE SEPARATE PERMITS FOR COMMENTS REGARDING
 NON-BUILDING ELEMENTS OF THE PLANS.
  
 6) SIGNS REQUIRE SEPARATE PERMITS, WITH PLANS.
  
 7) PLEASE REMEMBER THAT IN ACCORDANCE WITH RESOLUTION
 NO. 206-15, PRIOR TO THE ISSUANCE OF THE C.O., THE
 FOLLOWING SHALL OCCUR:
  
 A. RECORD A PUBLIC ACCESS EASEMENT FOR ANY PUBLIC
 SIDEWALKS OR UTILITIES ON THE SITE. THE EASEMENT
 LANGUAGE SHALL BE APPROVED BY THE CITY ATTORNEY'S
 OFFICE.
 B. ABANDON THE UNUSED FPL EASEMENT ON THE NORTH
 PROPERTY LINE.
 C. CONSTRUCT THE PEDESTRIAN CROSSING OF WESTBOUND
 OKEECHOBEE BOULEVARD FROM THE CITYPLACE OFFICE PARCEL
 TO THE RESTORATION HARDWARE PARCEL IN ACCORDANCE WITH A
 FLORIDA DEPARTMENT OF TRANSPORTATION RIGHT-OF-WAY
 PERMIT APPROVAL AND TIE IT INTO THE SIDEWALK NETWORK ON
 THE EAST SIDE OF THE RESTORATION HARDWARE SITE. A COPY
 OF THE FLORIDA DEPARTMENT OF TRANSPORTATION
 RIGHT-OF-WAY PERMIT SHALL BE PROVIDED TO THE PLANNING
 DIVISION.
 D. CONSTRUCT THE MODIFICATIONS TO THE PEDESTRIAN
 CROSSING OF OKEECHOBEE BOULEVARD AT ROSEMARY AVENUE
 (EAST SIDE) TO BE IN COMPLIANCE WITH PLANS APPROVED BY
 THE FLORIDA DEPARTMENT OF TRANSPORTATION AND THE CITY.
 A COPY OF THE FLORIDA DEPARTMENT OF TRANSPORTATION
 RIGHT-OF-WAY PERMIT SHALL BE PROVIDED TO THE PLANNING
 DIVISION.
  
 CONTACT ERIC SCHNEIDER @ (561) 822-1446.
  


Account Summary | Usage Policy | Privacy Policy